Professional Documents
Culture Documents
City of Iloilo
TECHNICAL INSTITUTE OF ILOILO CITY
MOLO CAMPUS
M.H del Pilar St., Molo, Iloilo City
Email: tiicmolocampusic@yahoo.com Tel. No. (033) 337-6711
Print book
Performing Roughing-In Activities, Wiring and Cabling Works for Single-Phase Distribution, Power, Lighting
Course:
and Auxiliary Systems
Printed
Rekhnor Magbanua
by:
Table of contents
Introduction
TOPIC 1: Installing PVC Moulding, PVC Trunking and Cable Duct
o Task Sheet: Installing PVC Trunking
o Task Sheet: Installing Cable Trays
We have learned in the previous lesson the different types and purposes of wireways and cable trays.
When installing them, it is important to keep in mind the permitted conditions in order to maximize
these raceways’ purpose.
In this lesson, we will discuss the installation procedures of the different raceways.
NOTE: Ensure that the entire installation conforms to and follows the design intent of the project for the
Electrical and Low Voltage System. It must also adhere to and comply with the specifications and
approved shop drawings based on the Local and International Standards.
Cable trays must be laid in a single-tier on the cable tray unless otherwise accepted and neatly
installed
Cuts on cable trays must only be along a line of plain metal and not through perforations.
o all cut edges must be prepared and treated accordingly to the metal’s original finish
o If the cable tray has been welded and galvanized, treat it with a zinc-rich paint
To prevent damage to the PVC covering, the holes cut in cable trays used for the passage of
PVC covered cables must have grommets or brushed/lined to Cable Tray 853/11
The cable tray must be made from perforated mild steel and hot-dipped galvanized finish
Cable trays must have the following dimensions:
Bends and tees, and straight trays must have the same material, finish, and thickness.
o There should be a minimum of 100mm straight run at each end of the bends and tees.
Mild steel galvanized brackets must support cable trays at regular intervals of 1.2 mm
maximum, and at 255 mm from bends and tees. Use mushroom-headed steel roofing bolts and
nuts to install and connect trays. There must be enough depth in the cable tray brackets to
make the tray’s rear accessible for PVC saddle type fixings installation.
Secure all cables to cable trays using PVC-covered copper saddles of the two screw-fixing type
or PVC-covered metal strips with non-corrodible cheese-headed screws and nuts. The shanks
of the screws must protrude beyond the nut by more than three threads.
o The horizontal and vertical clearance between cables must be sufficient enough not to
have rating reductions.
Install a continuous run of 25 mm x 3 mm tinned copper strip to the tray’s full length to ensure
earth continuity. Provide jumper links for all breaks in cable trays and at connections. A
complete run of the tray must be earthed using 25 mm x 3 mm tinned copper strips as
necessary. Occupy only 40% of the cable tray space. Forward the calculation for acceptance.
Increase the cable tray size if required in order to meet the calculation without extra cost.
Advantages
1. Lower Cost – Less copper is used due to the free air rating of equipment (no de-rating of
cables) and provides savings on materials and installation.
2. Reliable – Faulty splices are prevented since the runs of cable are continuous.
3. Flexible – Compared to non-segregated phase bus ducts, cable bus can accommodate field
adjustments due to unforeseen obstructions during installation.
Cable buses can withstand harsh environments. Also, their enclosures are ventilated, which removes
the need for thermostats or heater strips. Hence, the chances of failure are lessened.
Cable buses can also be used for any voltage and current for which the conductors are approved.
They can be used in exposed locations and in corrosive and wet locations only if approved for the
purpose. The conductors are required to have an insulation rating of 75 degrees C or higher and be
1/0 or larger.
o splice plates
o side rails
o termination box
o mounting clips
fire stop
environmental seal
terminal lugs
termination kits
Installation:
3. Layout the cable bus housing bottom section from one termination end to the other end,
including the termination accessories as needed. Mount the fire stops and wall seals.
4. Install support blocks and covers while pulling the cables in place.
5. Pull cables through the cable bus route using appropriate cable pulling tools to guarantee there
is no excessive tension nor excessive force on the cable themselves. While installing, ensure
that the bending radius is not violated and that the cable bus housing sections do not scratch or
scrape the cable.
When pulling the cables through the routing, make sure they are in place inside the support
blocks' groove before fastening the support block. This will ensure the block does not pinch the
cables.
splice plates
side rails
termination box
fire stop
environmental seal
power cables
terminal lugs
termination kits
mounting clips
silicone sealant
Installation:
1. Lay the bottom section along the route on top of the supports
4. Tighten the 6 mounting hardware, washers, bolts, and nuts to ensure the housing section's
electrical integrity.
9. Apply silicone sealant along the edge of the bottom seal block
11. Apply silicone sealant at the center of the seal block. This will ensure that there is a weather-
proof seal around the cable.
12. Make sure cables fit inside the support blocks' grooves before fastening the bolts.
13. Make sure cables have enough length to terminate without straining the cables.
14. Terminate cables with lugs and heat sink/cold shrink as needed.
TOPIC 3: Installing Auxiliary Gutter
An auxiliary gutter is a sheet metal enclosure that supplements wiring spaces at meter centers,
distribution centers, switchboards, and similar points of wiring systems. The enclosure features hinged
or removable covers to contain and protect electrical wires, cables, and busbars.
Substantial construction - auxiliary gutters must be in substantial construction and must provide
a complete enclosure for the contained conductors. All surfaces both interior and exterior must
be suitably protected from corrosion.
Smooth rounded edges - suitable bushing shields or fittings having smooth rounded edges
must be present where conductors pass between gutters through partitions, around bends,
between gutters and cabinets or junction boxes, and at other locations where necessary to
avoid abrasion of the insulation of the conductors.
Outdoor use - auxiliary gutters installed in wet locations must be in rain tight construction.
ADA compliant
There are 48 in- and 72 in- long wireway segments that can be field-cut to a specific length and
combined as needed for the application. Clear-anodized aluminum is used as a finishing for the
segment. Each segment has a wireway base track and top cap; wire management clips; pre-applied
foam tape; and concrete screws and drill bit.
Installation of floor-mounted raceways is an ideal alternative to costly core drilling and trenching. Aside
from being convenient, the installation of these surface-connected track raceways is also adaptable,
fast, and affordable.
There is also a variety of optional accessories that can be added to the floor-mounted wireways
including:
Grommets
Communication boxes
Wall channels
Corner kits
Rough-in boxes
Duplex and Quad Receptacles
Installation:
Final Checklist
1. Inspect openings in the junction boxes. Each opening must be fitted with ducts, conduit
adapters, or box enclosures.
4. All presets must be leveled no less than ⅛ in beneath the leveled floor.
6. Make sure all bonding screws, clips, locking screws on junction boxes, duct supports, and
couplings are securely tightened.
7. Use a waterproof sealing compound or duct tape to secure all joints against moisture and
concrete.