Mobilization Plan

This document outlines a mobilization plan for a civil infrastructure project in NEOM. It details the project management team and their roles. Key activities in the mobilization plan include staff recruitment to meet local content requirements, procuring necessary equipment, transferring relevant records and documents, and developing a schedule and program for startup activities. The plan aims to allow for a smooth transition and minimize disruption to the public during mobilization.

Uploaded by

Tariq Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
60% found this document useful (10 votes)
10K views6 pages

Mobilization Plan

This document outlines a mobilization plan for a civil infrastructure project in NEOM. It details the project management team and their roles. Key activities in the mobilization plan include staff recruitment to meet local content requirements, procuring necessary equipment, transferring relevant records and documents, and developing a schedule and program for startup activities. The plan aims to allow for a smooth transition and minimize disruption to the public during mobilization.

Uploaded by

Tariq Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
  • Introduction: Provides an overview of the mobilization plan's purpose, objectives, and coordination led by the project manager and supporting staff.
  • Mobilization Plan Scope: Outlines the scope of the mobilization plan including management responsibilities and timelines.
  • Mobilization Team: Describes the organization of the team responsible for implementing the mobilization plan.
  • Activities Within the Mobilization Plan: Lists specific activities required for successfully implementing the mobilization plan, including staff recruitment and equipment procurement.

MOBILIZATION

PLAN
THE LINE SITE PREPARATION
FRAMEWORK

Eng. Hezam AL-Ansi


AL-RAKHEES CONTRACTING COMPANY
TABLE OF CONTENT PAGE
1.1 INTRODUCTION ……………………………………………… 2

1.2 MOBILIZATION PLAN SCOPE …………………………......... 3

1.3 MOBILIZATION TEAM ……………………………………….. 3

1.3.1 Project Management ………………………………………….. 3

1.3.2 Planning and Permitting ………………………………………… 3

1.3.3 Technical Team ……………………………………………….. 4

1.4 ACTIVITIES WITHIN THE MOBILIZATION PLAN ………………………….. 4

1.4.1 Staff Recruitment ………………………………………………………………… 4

1.4.2 Procurement of Equipment …………………………………..…… 4

1.4.3 Securing Consents ……………………………………………….. 4-5

1.4.4 Transfer of Records and Documents …………………………………… 5

1.4.5 Timescales and Key Tasks …………………………………………………… 5

1.4.6 Minimizing Disruption to the Public ………………………………………….. 5


INTRODUCTION
Due to the strict schedule followed by NEOM management team, it is necessary to provide
equipment and work force as soon as possible without any delay after receiving letter of
participation from NEOM.

The intent of this mobilization plan is to represent the general sequence on how the project will
commence. This involves the number of personnel, equipment and materials. However, this plan
summarizes the proposed methodology for executing various phases of the site. This has to do with
the integration of personnel, equipment, materials, and the use of the site for staging, stockpiling
and other activities, and security.

Team led by the current Project Manager to develop and coordinate all contract mobilization tasks.
This will avoid the requirement for a handover. The Contract Mobilization Team will prepare a fully
developed and detailed Mobilization Plan. The Mobilization Plan will indicate how the contract will
move from Close of Contract to Service Commencement Date. At Notice to Proceed to site, Project
Manager starts to oversee the Construction Contract. At that point the Operations Team will take
over the contract. From time to time it may be necessary to change individuals in the team or to
introduce new staff. Any changes in staffing of the team during the mobilization period will be clearly
written to the client’s representative via email.

AL-Rakhees Contracting Company staff is well experienced with mobilization of equipment and
work force because of our previous history of working in NEOM projects for example excavation
and Civil work on W#31 Road with FMSCO and others. We had already mobilized our resources in
NEOM as we have 2 construction site; Dam Mowaileh at Muwaileh,Tabuk and Dam Trium at Trium,
Tabuk.
Managing Director
Hezam Ali Al-Ansi

Project Manager HFS OFFICER


Kamal Ahmed Abdulhakem AL-
Project QA/QC Engineer Shammari
Sunil Deth

Site Engineer Construction Supervisor HSE Officer


Ahmed Sami Mohammed Hilal Reynald Joseph

Surveyor Foreman Site Observer


Nazir Ahmed Najeb Abas Md Shamsuddin

1.2 MOBILISATION PLAN SCOPE

The Contractor will appoint and maintain a Mobilization Team for the duration of the Project until the
Service Commencement Date. It will be made up as a minimum of:
• Project Management and Construction department to provide resource by means of technical
support on engineering and construction considerations in relation to the
Contract; and
• A Maintenance Manager to assist with resolution of any technical issues.
Specifically, the Mobilization Team will work closely with the Project Manager.
• provide a smooth hand-over from all existing arrangements and activities leading up to the
Commencement Date.
• agree a set of activities with the client for all significant events during the mobilization period.
• identify and work with activity specialists within the Contractors’ organization to ensure all
appropriate policies and procedures are put in place in a timely and complete manner to ensure
compliance with all aspects of the Contract obligations.

1.3 MOBILISATION TEAM


The Mobilization Team will be organized by workstream.

1.3.1 Project Management


Eng. Awaz AL-Hakem will be Project Manager of the Mobilization Team, leading the construction
of civil infrastructural facilities project through Close of Contract, the Planning Application and
Permit Application for Service Commencement Date. He is familiar with all work streams in the
project.

1.3.2 Planning and Permitting

Plan has been prepared in coordination with the HSE plan, transportation/ consolidation plan and
Dust control plan.

Upon authorization to proceed, mobilization activities will commence. The construction and set-up
of the primary support/staging area of the project will take place. The site will be utilized as the
primary support/staging area.

1.3.3 Technical Team


The Technical Team will continue to be led by the Project Manager in the Project Management and
Construction Group. The Project Engineer assists the leader by working closely with the
Project Consultant and client’s representative. Maintenance Manager-Operators Maintenance
ensures that all equipment and machines are in order and is responsible to the project Engineer.

1.4 Activities within the Mobilization Plan

1.4.1 Staff Recruitment


Recruitment of staff shall meet Saudi Local content requirement and meet the qualification required
by NEOM.
1.4.2 Procurement of Equipment
All procurement will be carried out in compliance with the Contractors procurement policies and
methods.

1.4.3 Transfer of Records and Documents

Prior to the Contract Commencement Date, AL-Rakhees shall establish a local project office, from
where it will administer “a transfer of records” programme; subject is always to relevant data
protection principles, where applicable. The Contractor will, as part as the overall mobilization plan,
make arrangements for all relevant records, drawings, licenses and relevant certificates applicable
and dedicated solely to the Project to be made available in order to arrange a smooth handover.
The Contractor will ensure that from the early stages of the Contract, the flow of information and
data is effective, accurate and auditable, so that informed management decisions can be made and
Contract Key Performance Indicators, correctly reported in a timely manner.

1.4.5 Timescales and Key Tasks

Key Project Dates will be as indicated in Work Schedule to the project Agreement and which makes
reference to the activities mentioned in this Mobilization Plan. A clearly defined programme for the
startup of the will be developed in consultation with the Authority
.

1.4.6 Minimizing Disruption to the Public


The Contractor will provide an effective and efficient mobilization/transition plan, formulated in such
a way as to cause minimal disruption to the general public, who are the end users of the services in
question.

     
MOBILIZATION 
PLAN
THE LINE SITE PREPARATION 
FRAMEWORK
Eng. Hezam AL-Ansi
AL-RAKHEES CONTRACTING COMPANY
TABLE OF CONTENT                                                     PAGE
1.1 INTRODUCTION    ………………………………………………
INTRODUCTION
Due to the strict schedule followed by NEOM management team, it is necessary to provide 
equipment and work forc
1.2 MOBILISATION PLAN SCOPE
The Contractor will appoint and maintain a Mobilization Team for the duration of the Project unti
• agree a set of activities with the client for all significant events during the mobilization period.
• identify and work wi
1.4.2 Procurement of Equipment
All procurement will be carried out in compliance with the Contractors procurement policies an