You are on page 1of 4

Doc. No.

:
MEASUREMENT
Rev. No. : 3
OF Page : 1 of 4
PAYMENT
Date : 15-Nov-2017
(Insulation Work)

MEASUREMENT
OF
PAYMENT
(Insulation Work)

CONTRACTOR JOB NO. : XXXXX

PROJECT NAME :

CLIENT :

SITE :

3 15-Nov-2017 Revision
2 17-Sep-2015 Revision
1 31-Oct-2014 Revision
0
REV. DATE DESCRIPTION PRPD CHKD APPD QA CLIENT

MEASUREMENT OF PAYMENT
(Insulation Work)

This measurement of payment(insulation work) shall be applied for measurement of


(construction direct cost for) Subcontractor Progress Payment.
Doc. No. :
MEASUREMENT
Rev. No. : 3
OF Page : 2 of 4
PAYMENT
Date : 15-Nov-2017
(Insulation Work)

The calculation for Progress Payment is as below:


Progress Payment = Work Quantity * Unit Price * Weighted Factor of applicable Stage/Step

The measurement of Work Quantity is referred to “appendix E (Definition and Measurement


for Work) – Sec. IV Appendix – Overseas standard contract and ITB” and calculated by
discipline.

Unit Price is identified according to each contract between Contractor and Subcontractors.

Construction discipline is divided to each Work Stage/Step and Weighted Factor is decided by
the Work Stage/Step. Refer to following contents for Weighted Factor of Work Stage/Step.

Contents

1. Insulation - Equipment ( Unit : M2 )


2. Insulation - Piping ( Unit : LM )
3. Inspection plug (Unit : EA)
Doc. No. :
MEASUREMENT
Rev. No. : 3
OF Page : 3 of 4
PAYMENT
Date : 15-Nov-2017
(Insulation Work)

1. Insulation - Equipment ( Unit : M2 )


- FWBS Code: C191*1 (Equipment/Flange cover)
Stage Weighted Factor Remark
Shop Fab. 30
Scaffolding Installation 20
Insulation and Jacketing 40
Punch Clear / Final Inspection 10
Total 100

Material Supply(Sub-Con Scope)


Stage Weighted Factor Remark
Material Delivery at Site 0 *Note
Shop Fab. 30
Scaffolding Installation 20
Insulation and Jacketing 40
Punch Clear / Final Inspection 10
Total 100
*Note : Material Cost will be paid separately once material delivered .

2. Insulation - Piping ( Unit : LM)


- FWBS Code: C191*2 (Piping)
Stage Weighted Factor Remark
Shop Fab. 30
Scaffolding Installation 20
Insulation and Jacketing 40
Punch Clear / Final Inspection 10
Total 100

Valve Removable (Unit : EA)


- FWBS Code: C191*2 (Valve removable)
Stage Weighted Factor Remark
Work Completion (Incl.Inspection) 100
Total 100

Material Supply(Sub-Con Scope)


Stage Weighted Factor Remark
Material Delivery at Site 0 *Note
Shop Fab. 30
Doc. No. :
MEASUREMENT
Rev. No. : 3
OF Page : 4 of 4
PAYMENT
Date : 15-Nov-2017
(Insulation Work)

Scaffolding Installation 20
Insulation and Jacketing 40
Punch Clear / Final Inspection 10
Total 100
*Note : Material Cost will be paid separately once material delivered .

3. Inspection plug (Unit : EA)


- FWBS Code: C193 (Inspection plug)
Stage Weighted Factor Remark
Work Completion (Incl.Inspection) 100
Total 100