Professional Documents
Culture Documents
:
MEASUREMENT
Rev. No. : 3
OF Page : 1 of 5
PAYMENT Date : 15-Nov-2017
(Civil Work)
MEASUREMENT
OF
PAYMENT
(Civil Work)
PROJECT NAME :
CLIENT :
SITE :
3 15-Nov-2017 Revision
2 17-Sep-2015 Revision
1 31-Oct-2014 Revision
0
MEASUREMENT OF PAYMENT
(Civil Work)
This measurement of payment(civil work) shall be applied for measurement of (construction direct
cost for) Subcontractor Progress Payment.
The measurement of Work Quantity is referred to “appendix E (Definition and Measurement for Work)
– Sec. IV Appendix – Overseas standard contract and ITB” and calculated by discipline.
Unit Price is identified according to each contract between Contractor and Subcontractors.
Construction discipline is divided to each Work Stage/Step and Weighted Factor is decided by the
Work Stage/Step. Refer to following contents for Weighted Factor of Work Stage/Step.
Contents