MEASUREMENT
Rev. No. : 3
OF Page : 1 of 5
PAYMENT Date : 15-Nov-2017
(Civil Work)

MEASUREMENT
OF
PAYMENT

(Civil Work)

CONTRACTOR JOB NO. : XXXXX

PROJECT NAME :

CLIENT :

SITE :

3 15-Nov-2017 Revision
2 17-Sep-2015 Revision
1 31-Oct-2014 Revision
0

REV. DATE DESCRIPTION PRPD CHKD APPD QA CLIENT


Doc. No. :
MEASUREMENT
Rev. No. : 3
OF Page : 2 of 5
PAYMENT Date : 15-Nov-2017
(Civil Work)

MEASUREMENT OF PAYMENT
(Civil Work)

This measurement of payment(civil work) shall be applied for measurement of (construction direct
cost for) Subcontractor Progress Payment.

The calculation for Progress Payment is as below:


Progress Payment = Work Quantity * Unit Price * Weighted Factor of applicable Stage/Step

The measurement of Work Quantity is referred to “appendix E (Definition and Measurement for Work)
– Sec. IV Appendix – Overseas standard contract and ITB” and calculated by discipline.

Unit Price is identified according to each contract between Contractor and Subcontractors.

Construction discipline is divided to each Work Stage/Step and Weighted Factor is decided by the
Work Stage/Step. Refer to following contents for Weighted Factor of Work Stage/Step.

Contents

1. Site Development. (FWBS CODE: C11200)


2. Subsoil Improvement (FWBS CODE : C11300)
3. Piling (FWBS : C11400)
4. Earth Structure (FWBS : C11500)
5. Sewer and Drainage (FWBS : C11600)
6. Road and Paving (FWBS : 1700)
7. Fence & Gate (FWBS : C11800)
8. Shore Work (FWBS : C11900)
9. Concrete (FWBS : C12000)
Doc. No. :
MEASUREMENT
Rev. No. : 3
OF Page : 3 of 5
PAYMENT Date : 15-Nov-2017
(Civil Work)

1. Site Development. (FWBS CODE: C11200)


Doc. No. :
MEASUREMENT
Rev. No. : 3
OF Page : 4 of 5
PAYMENT Date : 15-Nov-2017
(Civil Work)

Stage Weighted Factor Remark


Work Completion & Inspection 95  
Punch Clear 5  
Total 100  

2. Subsoil Improvement (FWBS CODE : C11300)


Stage Weighted Factor Remark
Work Completion & Inspection 95  
Punch Clear 5  
Total 100  

3. Piling (FWBS : C11400)


Stage Weighted Factor Remark
Work Completion & Inspection 90  
Punch Clear 10  
Total 100  

4. Earth Structure (FWBS : C11500)


Stage Weighted Factor Remark
Work Completion & Inspection 90  
Punch Clear 10  
Total 100  

5. Sewer and Drainage (FWBS : C11600)


Stage Weighted Factor Remark
Work Completion & Inspection 90  
Punch Clear 10  
Total 100  

6. Road and Paving (FWBS : C11700)


Stage Weighted Factor Remark
Work Completion & Inspection 90  
Punch Clear 10  
Total 100  

7. Fence & Gate (FWBS : C11800)


Doc. No. :
MEASUREMENT
Rev. No. : 3
OF Page : 5 of 5
PAYMENT Date : 15-Nov-2017
(Civil Work)

Stage Weighted Factor Remark


Work Completion & Inspection 90  
Punch Clear 10  
Total 100  

8. Shore Work (FWBS : C11900)


Stage Weighted Factor Remark
Work Completion & Inspection 90  
Punch Clear 10  
Total 100  

9. Concrete (FWBS : C12000)


Stage Weighted Factor Remark
Work Completion & Inspection 90  
Punch Clear 10  
Total 100  