Draw Pit Draw Pit

Draw Pit Blinding : 20230211 Blinding : 20230211


Draw Pit Blinding : 20230211 Base Slab : 20230215 Base Slab : 20230215
Blinding : 20221231 Base Slab : 20230215 Wall : 20230217 Wall : 20230217
Base Slab : 20230120 Wall : 20230217 Top Slab : 20230217 Top Slab : 20230217
Wall : 20230207 Top Slab : 20230217
20230111 Top Slab : 20230207 20230215
82m (1st Half) 60m (1st Half)
20230112 20230214 POW_GBP_D26 POW_GBP_D19
POW_GBP_D01 63m POW_GBP_D21 20221208
82m (2nd Half) 24m
20221216
24m (150dia. x2nr)

20221124 20221119
11.5m 4m 20230115
20230106 20221128 73m
20221122 20221128
40m 7.7m COM_GBP_D22 46m COM_GBP_D23 14.5m
COM_GBP_D21
20221205
51m
20221213 COM_GBP_D24
87m Draw Pit 20221114 20221130
20221124 Blinding : 20221231 14m 57.5m
6m Base Slab : 20230107
COM_GBP_D20 Wall : 20230119
COM_GBP_D20A Draw Pit
20221128 Top Slab : 20230119 20221116 20221114
Blinding : 20221222
Draw Pit 6.7m 50.6m 38m
Base Slab : 20230107
Blinding : 20230120
Wall : 20230206
Base Slab : 20230207
Draw Pit Top Slab : 20230206
Top Slab : 20230211
Blinding : 20221231
20221224 Base Slab : 20230110
POW_GBP_D27
71m Wall : 20230206
Top Slab : 20230206
Draw Pit
Blinding : 20221222
20221119 Base Slab : 20230120
3m Wall : 20230206
Top Slab : 20230206
Excavation in Progress
20221110
38m 20221110
38.7m

COM_GBP_D31
Draw Pit
Blinding : 20221222
Base Slab : 20221231
Wall : 20230119 POW_GBP_D22
Ducting Progress Draw Pit Progress Top Slab : 20230119
Draw Pit

Total : 943m Total : 13nr Blinding : 20221222


Base Slab : 20221231
Wall : 20230206
Installed : 855m +24m Installed : 13nr 20221031
Top Slab : 20230206

In progress : 88m In progress : 0nr 63.7m


20221031
57.8m

Potable Water Progress Chamber Progress


Total : 135m Total : 2nr
Installed : 71m
0m Installed : 0nr
In progress : 0m In progress : 0nr
20221029 20221029
27.2m 30.4m

Progress of UU Works at Area 3310/03 20221124*


3.6m
20221124*
3.3m

near East Aggregate Mixing Plant


Update : 15 Feb 2023