McLaren Construction UAE DX3.1 Data Centre, Dubai JJJV Black and White Engineering
1 Ensure that all the materials which are used for are as per approved material submittal.
2 Ensure that the installation has been done as per approved shop drawing.
3 Ensure that the piping connection has been made with proper supports.
4 Ensure that all the main line and branch line are installed as per approved shop drawing.
Ensure that the valves and equipment’s are installed at proper level and location for
8
access and maintenance
9
Ensure to provide all the piping labeling and equipment’s tags
Comments/Remarks if any :