The undersigned certifies that the above-submitted items have been reviewed in detail and are correct and in strict conformance with all requirements of the contract documents
except as otherwise noted. Note: Approval of items submitted does not relieve contractor from complying with all requirements of the contract documents.
Proyecto 200134
GM Ramos Propulsion Battery Assembly & Electric Motor (US #200420)
ASELEC
Acción:
A - Aprobado / Approved A1 - Aprobado / Revisar AAN1 - Aprobado Como se ha AAN - Aprobado Como se ha
Señalado Señalado/ Approved as Noted
C - Cancelled / Cancelado FONR - File Only, Not Reviewed NR - Not Requested NRNR - Not Requested, Not
Reviewed
R2 - Rechazado R - Rechazado/ Rejected RA - Regresar para Aprobar / R1 - Reviewed
Return for Approval
RC - Reviewed with Comments RR1 - Revisar y volver a RR - Revisar y volver a
presentar presentar/ Revise and Resubmitt
Observaciones
A-E REMARKS
No Exceptions Note Markings
Process Resubmit
DATE: 02/09/2021
Ramos Arizpe, Coahuila a 19 de agosto de 2021.
FOTOGRAFIAS: