Project Description

Building Number of Approximate


# Building Name
Number Storeyed Area
Development of 20 Acre Land

1 BA1 Main Lecture Hall / Auditorium 3 Storeyed 3454

2 BB1 Library 2 Storeyed 1,414

3 BC1 Pre-Clinical Building 3 Storeyed 8,233

4 BD1 Canteen B + Ground 915

5 BE1 Entrance Building Single Storeyed 151

6 BF1 Student Accommodation - Male G + 3 Storeyed 2,587

7 BF2 Student Accommodation - Female G + 4 Storeyed 3,625

8 BG1 Staff Accommodation 1 G + 3 Storeyed 880

9 BG2 Staff Accommodation 2 G + 3 Storeyed 921

10 BG3 Dean’s Quarters 2 Storeyed 244

11 BG4 Guest Quarters 2 Storeyed 347

12 BH1 Security Hut Single Storeyed 81

13 BH2 Security Hut Single Storeyed 22

Development of Professorial Unit at Teaching Hospital Rathnapura

14 BI1 Professorial Unit GF+ 8 Floors 23,169

Total 46,043
 I wish to give below the details of Work Stages attended during the period ending December 2022
A). Consultancy Services Contract signed on 31/12/2020.  
1. Lead Consultant - DAR Engineering (Saudi Arabia), Local Consultant - Q SERVE (Pvt) Ltd
2. Contract Price - 5,372,290.00 Saudi Riyal 
 Following stages of Consultancy Contract attended during the period. 
1. Final stages of Schematic Design Phase-      100 % Completed. 
2. Site Investigation works -                                100% Completed. 
3. Detail Design Phase -                                       100% Completed.
4. Preparation of Bidding Document -               100% Completed.
5. Procurement Process -                                     Commenced. 
a. Originals of Bidding Document Package was sent to SFD on 10/04/2022 and awaiting their
concurrence to proceed with the Balance Procurement Process. Reminders sent to SFD to
receive the Concurrence. SFD team is scheduled to visit SL soon.
6. Preliminary Planning Clearance-                    Received from UDA. 
7. Development Permit from UDA-                   
Related official request letters from the Client to receive recommendation were sent and
received by us as follows.
o Central Environmental Authority -                      Clearance Report Received.

o National Building Research Organization -  Preparation of final report is in Progress. 

o Ceylon Electricity Board -                                    Clearance Letter received. 

o National Water Supply & Drainage Board -         Clearance Letter received. 

o Fire Department-                                                  Clearance Report Received. 

o Green Building Application (UDA) -                    Registration Number received. 

o Full set of Drawings and relevant letters from various local authorities handed over to
UDA To obtain Development Permit in December 2022
o TIA Meeting held at UDA Colombo Office on 22/12/2022.

o UDA Meeting held on 17/01/2023 at Rathnapura UDA office and approval given to issue
the Development Permit for both Professorial Unit and 20 Acre Land.

8. Meeting held with the Secretary Ministry of Education to discuss recommendations issued by
RAMP (Chaired by Secretary to Prime Minister).      
B). Financial progress of the Project 
1. Payments to the Consultant (From SFD- Saudi Fund for Development)
Withdrawal
Date Amount Currency Status
Number

W/A 1 553,290.15 SAR Settled


28/04/2021
W/A 2 8,647.06 SAR Settled

W/A 3 62,467.63 SAR Settled


13/12/2021
W/A 4 553,290.15 SAR Settled

W/A 5 25/03/2022 663,948.17 SAR Settled

Total Settled 1,841,643.16 SAR

W/A 6 28/11/2022 64,536.67 SAR Pending

2. Budget Allocation for Year 2023

Ministry of Education (Higher Education Section)


Allocation of Funds for Year 2023 (Rs Million)
Item Description Finance Code Amount (Rs Million)
2102 12 500
Furniture and Equipment
  17 60
  Sub Total 560
2104 12 375
Building and Structures
  17 55
  Sub Total 430
2509 Other 17 10
  Grand Total 1000

3. PMU - Project Management Expenditure (Up to End of January 2023) – 0.544 Million SLR
(GOSL Funds) 
C). Expected Time Line of the Project – See the Annexure 1

 
Eng. G D A Piyatilake
Project Director
Construction of Faculty of Medicine Project at the Sabaragamuwa University of SriLanka 
Address:  18, Ward place, Colombo 07
Tel:           +94 773 721 021 Email:      pd-fomsab@mail.mohe.gov.lk

You might also like