ALL ISD PROJECT STATUS REPORT

DATE: 19.02.23.

APARTMENT NO. CLIENT SITE VISIT PROJECT STATUS


FOR READY/ NOT
PAYMENT INTRO INITIAL SITE VISIT DIMENSION, DETAIL APPROVAL WORKING READY FOR CONSTRUCTION
SL NO. AISHA ARQAM ARWA NAME PHONE NO. STATUS MEETING BUDGET WITH CLIENT SPECS & DESIGN PRESENTATION BUDGET MEETING DRAWING CONSTRUCTION STATUS COMMENTS

Tiles installed, wiring done, switch


1 A4 Quazi Hasibul Hasan 01715-199884 X √ √ X X X X X X X √ % pending for lack of main door

Tiles installed, wiring done, switch


2 A6 Md. Zahid Hasan Reza 01973-032848 X √ √ X X X X X X X √ % pending for lack of main door

Tiles running, electrical work


3 A9 Md. Atiqul Islam 01708-126969 √ √ √ √ √ √ √ 04.02.23. X √ 06.02.23. X X % done.

Tiles installed, wiring done, switch


4 B5 Md. Mahbubul Haque 01726-523825 √ √ 30.01.23. √ X √ √ √ 19.02.23. X X X √ % pending for lack of main door

X
PENDING
(client busy 1. Render Image sent - 18 Jan
Jan-Feb '23) Mail sent- 29 & 30 Jan. 2. Tiles
Approved installed, wiring done, switch
5 D4 Zarjish Alam 01713-084283 √ √ √ √ √ √ √ 18.01.23. X by phone. X √ % pending for lack of main door

6 D8 Jahangir Alam 01768-533718 X √ X √ X X X X X X √ % Design will start soon.

Remodelling, dismantling
7 A3 Shafiul Haq Sourav 01770-033663 X X X X X X X X X X √ % ongoing. No tiles. No wiring.
Interior Ongoing. All cabinet body
done (Excep Kitchen). পা ার
কাজ চলেছ। Kitchen Top Cabinet
will start. Bottom cabinet after
8 A6 Zaedul Haq Dipu 01793-591982 √ √ √ √ √ √ √ 29.11.22. √ √ 14.12.22. √ √ 75% gas connection.
Single paint coat. Tiles + thai
Kazi Abdullah Al done. Door laquer ongoing.
9 A8 Mahmud 01755-516640 X √ 31.01.23. √ X X X X X X √ % Budget sent- 07.02.23.
X PENDING Remodelling ongoing. , plaster
(Non will be done. Tiles not installed
10 B2 Abdullah Al Ahad 01717-194486 √ √ X √ 11.01.23. √ Rsponsive) X X X X X % yet. Wiring ongoing.

Wiring Done. Tiles 80% complete.


11 B3 Syed Ruhul Amin 01713-444247 PENDING √ 04.02.23. X X X X X X X X X % (Kitchen & Drawing incomplete)

Tiles+Thai complete. Base paint


12 B7 Masud Rana 01755-538004 PENDING √ √ √ √ √ √ 15.12.22. √ √ 31.12.22. √ √ % coat done. Elect Wiring done.