Mr.Parimal – Geologist
Malanjkhand Copper Project (MCP) has open pit mine with a capacity of 2 million
TPA of ore with a matching concentrator plant, Tailing Disposal System and other
auxiliary facilities
Sampling:
Sampling is done using automatic sampler
Automatic sampler collects sample for every 40 min
The quantity of sample collected is around 15 litres per shift
Sample preparation:
Copper concentrates and tailings are in the slurry form, so there is no
requirement of any primary crushers
Using coning and quartering the sample size is reduced
The size of ore is reduced from 350 mesh to 200 mesh using coning and
quartering
Drying:
After the sample is prepared it is dried using the oven
Test:
The various chemical analyses undertaken in the lab includes identification of
copper, iron, sulphur and insoluble content