You are on page 1of 1

Bakhaw Labor Cost Total Cost

Item Description qty unit


Electrical
1 Outlet Set 2 gang 3 pcs
3 Electrical Tape 2 pcs
4 Utility Box 6 pcs
5 Junction Box 2 pcs
6 #18 Flat Cord 10 m
7 #16 Flat Cord 10 m
8 Electrical Moulding 3/4" 4 pcs
Plumbing
1 T-shower w/ Faucet 1 set
2 Flexible Hose 1/2"x 1' 1 pcs
3 Lavatory 1 pcs
4 T.B. water tank fittings 1 set
5 2 way valve for ablosion 1/2" 1 pcs
6 End cap 1/2" 1 pcs
7 Lavatory drain 1 pcs
8 Shut Off valve 1/2" 1 pcs
Carpentry
1 Front door 1 set
2 Roof Repair 1 set
3 Head Board 1 set
4 sink cabinet
Painting Works
1 Interior and exterior 161 sq.m
2 Flat white 6 gallon
3 Ceiling 36.21 sq.m
Furniture
1 flat wall boysen 1 gallon
2 Thinner for Enamel 1 bottle
Tiles
1 Tiles wall and floor 17.34 sq.m
2 Tile Grout

You might also like