You are on page 1of 3

Location / Area : Verification

Sign-off

Sl. Activities / Items to be Inspected Engineer


No.
Check all materials to be used have an approved submittal.
1.
Ensure drawings used for installation are current and approved.
2
3 Inspect all the pipes, insulation and other material used are
new and undamaged and installed in good workman like
manner.
4 Check that only eccentric reducers with level side up are used for
reduction in pipe sizes.
5 Check that only properly fabricated fittings are used for
changes in directions, shapes, sizes and connections.
6 The Joints and flanges are correctly made, jointed and sealed
with approved methods / material and as per manufacturer’s
instructions, as applicable.
7 Check that installed piping is free of sags and bends
8 Check that gap is maintained between two parallel pipes to
permit valve servicing.
9 The pipe routing is checked as per approved drawings. Should
be properly leveled & aligned. Coordinated with other electro –
mechanical services.
10 Flexible connectors are installed at equipment connections as per
requirements / approved drgs.
11 Check drains are installed as per specifications at the lowest
point of risers, branches and main lines.
12 Check the spacing of supports and hangers as per
specifications.
:2:

Location / Area : Verification


Sign-off

Sl. Activities / Items to be Inspected Engineer


No.
13 Check strainers, valves, test plugs, air vents etc. are installed
correctly and as per approved drawings.
14 Check sleeves are installed for pipes passing through walls /
partitions as required.
15 Check that sleeves are cut to length for mounting flush with
both surfaces.
16 Hydro static pressure of piping completed satisfactorily and test
results recorded and documented. (To submit ‘ RFW ‘ for
M/s. Roberts & Partners witness)
17 Insulation is installed as per manufacturer’s instructions /
specifications and finished with smooth & even surface
without any damages.
18 Check all the insulation joints and seams are sealed properly.
19 Check nuts, bolts , screws, brackets drop rods etc. are tight and
aligned properly.
20 Openings around pipes crossing the walls, partitions etc., are
sealed properly.
21 Metal jacketing provided over insulation for the required
sections of the piping as per specifications with smooth,
straight and even surface.
22 Inspect the installation of meters and gages as per the
specifications & approved drawings.
23 Ensure adequate space is available for maintenance and
removal of valves, meters, gauges and strainers, as applicable.
:3:

Location / Area : Verification


Sign-off

Sl. Activities / Items to be Inspected Engineer


No.
24 Installed piping is protected from damages for the remainder
of the construction period.
25 Ensure identifications, flow directions and valve tags are
provided as per specifications.
Check coordination of pipe work with other services.
26
27 Final round of inspection of complete installation prior to
cover up.

Comments / Remarks, if any

QA/QC ENGINEER
Signature

Name

Date

You might also like