Qaran Consultant & Construction Estimated By : Eng Said Abdi Hogoto

Bill of Quantities & Specifications Tell : 0907691244

Sn. Description Quantity Unit Price Total


1 Site Mobilization & Site Clearance 1 L.S $7,000 $ 7,000.00
2 RCC concreting
2.1 Column 37 M3 $ 300.00 $ 11,100.00
2.2 Beam 35 M3 $ 300.00 $ 10,500.00
2.3 Slab 95 M3 $ 300.00 $ 28,500.00
2.4 Staircase 5 M3 $ 300.00 $ 1,500.00
3 Block Works
3.1 200mm Blocks 1429 M2 $ 20.00 $ 28,580.00
3.2 100mm Blocks 185 M2 $ 15.00 $ 2,775.00
4 Finshes
4.1 Wall plastring 3560 M2 $ 8.00 $ 28,480.00
4.2 Floor tiles 725 M2 $ 15.00 $ 10,875.00
4.3 Non Slippery tile 36 M2 $ 20.00 $ 720.00
4.4 Wall tile 251 M2 $ 17.00 $ 4,267.00
4.5 Skirting 536 M2 $ 5.00 $ 2,680.00
4.6 Painting 3945 M2 $ 3.00 $ 11,835.00
4.7 Gypsum Wall partition 53 M2 $ 25.00 $ 1,325.00
5 Prefabricated Steel Roof Structure 1 LS $ 35,000.00 $ 35,000.00
6 Doors
6.1 D1-90 x 210CM 30 nos $ 230.00 $ 6,900.00
6.2 D2-75x210CM 14 nos $ 210.00 $ 2,940.00
6.3 D3-120x210CM 2 nos $ 260.00 $ 520.00
7 Windows
7.1 W-200 x 150 CM 6 nos $ 180.00 $ 1,080.00
7.2 W1- 150 x 150 CM 14 nos $ 150.00 $ 2,100.00
7.3 W2- 100 x 150 CM 8 nos $ 140.00 $ 1,120.00
7.4 W2A - 100 x 90 CM 2 nos $ 130.00 $ 260.00
7.5 V- 60 x 60 CM 12 nos $ 100.00 $ 1,200.00
8 Drainage & Water Supply 1 LS $ 6,000.00 $ 6,000.00
9 Electric instalation 1 LS $ 5,000.00 $ 5,000.00

$ 212,257.00
SL.NO DESCRIPTION TOTAL COST
1 Material cost $ 148,579.90
2 Labor cost $ 63,677.10
NET TOTAL BUDGET $ 212,257.00