2. Assume management want to reduce duration less than one month, we can John help to engineering job part time. As a result, duration changed to 30 day and cost increased. Overallocation of welder occurred. 3. First give overtime hour to finish job. Increase cost 4. Or leveling within the slack-increased duration to 31 day again.