In tracking page lets change some activity duration as below:
Assume:
Jack up delayed 3 day due to weather condition, so it will start 20 th of February.
Assume seafastening need more to day two complete. And engineering job finished in 10 day instead of 8 days. We cas see that some critical path not critical any more.