To,
Project Manager
OSJI Joint Venture
Kanchpur, Meghna and Gumti Site .
Dear Sir,
We are very much pleased to submit you the reason for making
delay to finish the work. Here the reasons we mentioned below :-
Cause of delay :
1. Due to Civil Foundation Work -
At Gumti Site:
Steel Material delivery date was 20-07-2016. AA STEEL LTD.
was ready for erection on this date but R.C.C (Net cement
finishing) work was incomplete. So steel material erection was
delayed from the date of
20-07-2016 to 07-08-2016. Delay period - 17 days (Due to civil
work)
At Meghna Site:
Material and workers were ready to erection the steel portions
by-02-08-2016.
But RCC work was not ready at that day. So it was delayed from
02-08-16 to 05-08-16). Delay period - 03 days. (Due to civil
work)
At Kanchpur Site:
At Kanchpur site steel material were delivered at 10-08-2016. But
RCC casting of Fuel Station was delayed and it was ready for
steel work at the date of 10-10-2016. So we started erection at
11-10-2016. Delay period 60 days. (Due to civil work)
2. Due to dalay payment -
Bill submit & Payment date:
First partial bill submission : 27-08-16. Received Bill 05/10/16
Second partial bill submission : 27-09-16. Till now we havent
received this running bill
Third payment received : 21-11-16.
03. Other causes of delay :
1. Holiday- EID-UL-AZHA (10-09-16 to 18-09-16) 09 days.
(Due to civil work)
2. Heavy rain & bad weather: 15 days. (Due to civil work)
3. at Meghna Site: The workshop sheeting work was delayed due
to fixing the Crane Rail, Hoist, Pully and Container at Mezzanine.
Delay period 10 Days(Due to civil work)