CT213 FORMULA:

PLATE NO.1 EARTH WORKS PLATE NO.3: MASONRY

Volume Required 0. No. of CHB = TA ÷ Achb


Vrqd = ( Vact - Vcon - V st )1.20
1. For Exterior Wall
TA = P( H ) - Ad - Aw
Volume Actual
Achb = ( h ) w = 0.20 × 0.40
Vact = Vint + Vext

2. For Interior Walls


Vint is Vol. of Interior
No.of CHB = (TA--Ad)(12.5)
Vext is Vol of exterior
Sizes of CHB and uses
A.) Vint = ( FA. × h1 ) , h1 = from NGL to FFL 6 inches for. Exterior Wall
B.) Vext = ( LA -- FA ) h2 h2 = h1 - (no.step)0.20 4 inches for Interior Wall

Vchb = P( 1.0 × 0.30 ) V Sizes in SI in Metric


st = L x W x H. of Septic T. For Exterior Wall 6 Inches
PLATE NO.2 VOLUME OF CONCRETE 0.15m x 0.20m x 0.40m
Achb =0.2(0.4) =0.08 sqm
VOLUME OF FOOTING: No.of CHB = Aw / Achb
VF1 = (No. of Footing 1)(Width of footing No.of CHB = 1m(1m)/0.08 = 12.5 pcs/ sqm
1)(Length of footing 1)(thickness of footing 1)
For Interior Wall 4 Inches
VOLUME OF FOOTING TIE BEAM 0.10m x 0.20m x 0.40m
VFTB1: (Perimeter of FTB1)(Width b of No.of CHB = 12.5 pcs/sqm
FTB1)(Depth d of FTB1) No.CHB=12.5pcs/sq.m(TA)

W is Width of Stairs is 1.0m


VOLUME OF COLUMN D is Diagonal of Stair Slope distance use
VC1 = (No. of Column1)(Width of C1)(Length of
C1)(Height of C1) Pythagorean Theorem To determine
D t is Slab thickness = 10m
VOLUME OF BEAM Vol = W(D)t = 1m( D )0.10m
VB1 = (Perimeter of B1)(Width of B1)(Length of D= Diagonal of Stairs
B1)
Pythagorean Theorem
VOLUME OF SLAB D(squared) = R(squared) + r(squared)
VS1 = (TOTAL AREA OF FLOOR1)(thickness of slab R= No. Of Step. ( 0.30 m )
of F1) r = No. Of step. ( 0.20m ) STEEL WORKS

PLATE NO.4&5:
VOLUME OF STAIRS
FIRST TO SECOND, SECOND TO THIRD Total Length (TL) of Bars
a) VSTEPS = (1/2)(rise r)(Run R)(Width)(NO. Standard Length( SL) of Bar
OF STEPS SUBTRACTED BY 1) Pcs of Bars = TL ÷ SL
b) VWAIST SLAB = (LENGTH OF WAIST
1. TL of Footings
SLAB)(width)(thickness)
TL= no.f1[ (no.B)L+(no.B)W]
c) VLANDING = (width of Landing)(length of
Pcs of Bars = TL ÷ SL
landing)(thickness)
no.B is Number of Bars L is Length,
Width of the Ftg ( See Detail of
FOOTING )
2. TL Footing Tie Beams
TL = P.ftb.1 ( no.B )
Pcs of Bars = (TL ÷ SL)1.05
Additional 5% for Splice See Found.
Plan, Detail

3. TL of. COLUMNS
TL = no.C1( no.VB)H
Pcs of Bars = (TL÷ SL)1.10
Add 10% for Splice & Bend
( VB is Vertical Bars )
(H=Height from Ftg to RB )
Additional 0.30m for Bend See Det. of
CF &Ele v

4. Total Length(TL) BEAMS


TL = Pb1( no.HB)1.10 ÷ SL
Add 10% for Splice & Hook
( HB is Horizontal Bars )
See Flr.Framing Plan,Detail

5. TL for Ties and Stirrups Ties Used for


COLUMN & Stirrups for BEAMS Use
10mm Bar Diameter
(See Detail with Schedule)
a. For Ties TL=no.C1(Pc)no.Ties for
C1
Pc = 2a + 2b for Column
Pb = 2b + 2d for Beams

Pc is P Cross Sec. Column


Pb is P Cross Sec.of Beam

No.ties = H ÷ S
H=Top ftg to(RB)Roof Beam
S=Spacing of Tie & Stirrups

b. For Stirrups
TL of Stirrups for Beams
TL =(no.Strp)(Sec.Beam)
TL = ( Pb1÷ S)(2b + 2d)
Pcs Bars = TL ÷ SL

(See Framing Plan & Detail)