This document summarizes cost estimates and contract amounts for M&E (mechanical and electrical) works at UCS Nsambya. It finds that the estimated costs according to detailed designs exceed the original contract BOQ provisional sums by over 2 billion UGX. Additional contingency analysis finds that realized extra costs so far are over 2 billion UGX more than the original contingencies budget, requiring the total contract sum to increase by nearly 3 billion UGX to a new total of nearly 10 billion UGX.
Original Description:
Original Title
Summary of M-E variation analysis and contigency sum analysis for Nsambya (Option 1B).xlsx
This document summarizes cost estimates and contract amounts for M&E (mechanical and electrical) works at UCS Nsambya. It finds that the estimated costs according to detailed designs exceed the original contract BOQ provisional sums by over 2 billion UGX. Additional contingency analysis finds that realized extra costs so far are over 2 billion UGX more than the original contingencies budget, requiring the total contract sum to increase by nearly 3 billion UGX to a new total of nearly 10 billion UGX.
This document summarizes cost estimates and contract amounts for M&E (mechanical and electrical) works at UCS Nsambya. It finds that the estimated costs according to detailed designs exceed the original contract BOQ provisional sums by over 2 billion UGX. Additional contingency analysis finds that realized extra costs so far are over 2 billion UGX more than the original contingencies budget, requiring the total contract sum to increase by nearly 3 billion UGX to a new total of nearly 10 billion UGX.
• Sanitary ware 470,410,500 390,000,000 80,410,500 Block A 189,241,500 130,000,000 59,241,500 Block B 189,241,500 140,000,000 49,241,500 Block C 91,927,500 120,000,000 (28,072,500) • Domestic services 348,458,250 165,000,000 578,024,250 • Fire-fighting 354,566,000 • Water Supply (NWSC) 40,000,000
3. Additional works 1,109,518,000 - 1,109,518,000
• Fire Detection 78,750,000 - 78,750,000 • AC Pipe work 35,668,000 - 35,668,000 • AC Units 578,650,000 - 578,650,000 • CCTV works 120,450,000 - 120,450,000 • Kitchen hoods 296,000,000 - 296,000,000
4. Civil work associated with Foul/ 105,937,020 - 105,937,020
Soil Water Drainage • Septic tank (3No.) 98,756,700 - 98,756,700 • Soak pit (6No.) 7,180,320 - 7,180,320
Total Variation 2,960,115,770 975,000,000 2,227,615,770
Summary of contigency sum analysis as at 22nd Feb 2023 (Option 1) Civil Works M &E Description Contigency Extra costs Difference Contigency Extra costs sofar Difference (UGX) Contract BOQ sofar realised (UGX) Contract BOQ realised (UGX) (UGX) (UGX) (UGX)
• Block A 71,671,934 - (71,671,934) 11,500,000 152,218,200 140,718,200
• Block B 72,656,221 - (72,656,221) 12,744,001 127,218,200 114,474,200 • Block C 52,095,629 - (52,095,629) 10,000,000 (1,871,400) (11,871,400) • External 36,719,808 52,643,160 15,923,352 - 734,595,750 734,595,750 Approved gate house 17,023,460 Approved Boundary wall and 35,619,700 retaining walls In consideration (M & E) - 734,595,750 734,595,750 • Miscellaneous 14,888,655 1,215,455,020 1,200,566,365
Sub - Total No.1 233,143,592 52,643,160 (180,500,432) 49,132,656 2,227,615,770 2,178,483,114
Additional funds required - 2,178,483,114
Add Preliminaries (3%) 65,354,493.43
Sub - Total No.2 2,243,837,608
Add conitgencies (5%) 112,191,880.38
Sub - Total No.3 2,356,029,488
ADD 18% VAT - 424,085,307.84
Total Additional funds - 2,780,114,796
required
Current contract sum 6,994,805,375
New contract Sum 9,774,920,171
Summary of contigency sum analysis as at 25th Feb 2023 (Option 1) Civil Works M &E Description Contigency Extra costs Difference Contigency Extra costs sofar Difference (UGX) Contract BOQ sofar realised (UGX) Contract BOQ realised (UGX) (UGX) (UGX) (UGX)
• Block A 71,671,934 - (71,671,934) 11,500,000 152,218,200 140,718,200
Sub - Total No.1 233,143,592 52,643,160 (180,500,432) 49,132,656 2,227,615,770 2,178,483,114
Additional funds required - 2,178,483,114
Add Preliminaries (3%) 65,354,493.43 Sub - Total No.2 2,243,837,608 Add conitgencies (5%) 112,191,880.38 Sub - Total No.3 2,356,029,488 ADD 18% VAT - 424,085,307.84 Total Additional funds required - 2,780,114,796 Current contract sum 6,994,805,375 New contract Sum 9,774,920,171