Professional Documents
Culture Documents
Seal Oil System Flushing
Seal Oil System Flushing
(A GOVERNMENT OF INDIA
ENTERPRISE) LARSEN & TOUBRO LTD.
COMMENT SHEET
DOC TITLE FLUSHING PROCEDURE FOR SEAL OIL SYSTEM
L&T DOC NO. LM1013GAA015
NTPC DOC NO. 9578-001-110-PVM-W-133
Reviewed By
Review Date / Location
Page 2
NTPC KHARGONE NTPC DOC NO: COS-COMM-KG-COMMG-PRO/016 Page3
2X660MW L&T DOC NO : LM1013GAA015
PLANT AREA : TURBINE GENERATOR
PROCEDURE FOR FLUSHING OF SEAL OIL SYSTEM
Table of Contents
2.0 Objective 5
3.0 Proposal 5
11.0 Restoration of Seal Oil System after completion of 3rd stage flushing 11
13.0 Appendices 11
Fig. 3: Temporary Piping connection for bearing oil pipe line flushing of 14
generator
Attachment-1 21
NTPC KHARGONE NTPC DOC NO: COS-COMM-KG-COMMG-PRO/016 Page4
2X660MW L&T DOC NO : LM1013GAA015
PLANT AREA : TURBINE GENERATOR
PROCEDURE FOR FLUSHING OF SEAL OIL SYSTEM
2.0 Objective
Any mechanical impurity left out inside the seal oil system shall be removed before starting
operation of turbine & generator. The objective is flush seal oil system sufficiently to remove
foreign material.
3.0 Proposal
3.1 Carry out air blow inside seal oil pipes and temporary bypass pipes by using dry compressed
air.
3.2 Carry out Pressure test of seal oil pipes by using oil (ISO VG-32).
3.3 a. Line up the seal oil system piping as per fig.1 & fig.2 to carryout flushing.
Stage1: Flushing of seal oil system pipes shall be carried out with flushing skid and criteria
Stage2: Flushing of seal oil system pipes shall be carried out with flushing skid, Heating &
cooling cycle shall be applied and criteria shall be achieved as mentioned clause no: 10.
Stage3: Flushing of seal oil system pipes shall be carried out with Seal Oil Unit.
3.4 a. Extra turbulence can be created by switching OFF and ON of the running pump of
temporary skid during Stage1 & Stage2 flushing.
b. Extra turbulence can be created by switching OFF and ON any of the pumps of Seal Oil Unit
during 3rd Stage flushing.
3.5 Suitable hammering or vibration arrangement shall be made for field welded Seal Oil piping
joints.
3.6 Suitable heating arrangement shall be made for creating cooling and heating cycles.
3.7 Flushing shall be carried out with Lube oil from approved source and oil grade shall be ISO
VG 32.
3.8 Hammering, cooling & heating should not be applied during 3rd flushing.
For air blow inside seal oil pipes and Pressure test, dry compressed air line shall be
available.
Flushing equipment such as the Flushing Unit, temporary bypass hoses and manifolds etc
shall be available at site.
Required manpower shall be available to carry out the inspection of the Flushing Unit.
NTPC KHARGONE NTPC DOC NO: COS-COMM-KG-COMMG-PRO/016 Page6
2X660MW L&T DOC NO : LM1013GAA015
PLANT AREA : TURBINE GENERATOR
PROCEDURE FOR FLUSHING OF SEAL OIL SYSTEM
Job Safety Analysis should be done before start of the process. Check list shall be prepared
& jointly signed.
Welding / cutting should not be carried out in the oil flushing area once oil has been filled
in seal oil tank.
Load on pumps should not exceed full load current of motor.
Provision of emergency stopping of oil pumps from local / control room should be made.
Buckets containing sand should be available near the process.
First aid kit should be available near process area.
Precaution should be taken to avoid spillage and contamination of oil.
Ensure any scaffolding required is correctly erected and safe for use.
Wear a safety harness when working above ground.
Wear protective eyeglasses and gloves.
Ensure all temporary hoses and connections are secure and adequately supported.
Ensure sufficient fire extinguishers are available and located in the correct positions near the
flushing area.
Barrier tape, fencing and warning notices should be erected.
Take care of removed materials and equipment for flushing system (In order to prevent
damaging).
Oil temperature during flushing should not go beyond 65°C.
Over pressurization/bursting:
In the event of bursting of the pressured line, stop the pumps immediately. Ascertain the
point of bursting and replace the part.
NTPC KHARGONE NTPC DOC NO: COS-COMM-KG-COMMG-PRO/016 Page7
2X660MW L&T DOC NO : LM1013GAA015
PLANT AREA : TURBINE GENERATOR
PROCEDURE FOR FLUSHING OF SEAL OIL SYSTEM
In the case of improper transport of the flushing unit or seal Oil Unit, pressurized or
functional components may become damaged. Ensure that these components do not come
into contact with the attachment devices or lifting tools during transport. Ensure that no
unauthorized persons are within the hazard zone.
Pressure test of Seal oil pipe shall be carried before start of the Seal oil flushing as per
below procedure.
8.1 Setup:
All permanent piping and equipment shall be installed along with pipe supports.
Necessary temporary piping connections and blinds shall be made ready. Blinds shall
be selected by considering the test pressure.
Temporary pressure gauge of suitable ranges shall be used during the testing.
Equipment not subjected to pressure test shall be isolated from the system.
NTPC KHARGONE NTPC DOC NO: COS-COMM-KG-COMMG-PRO/016 Page8
2X660MW L&T DOC NO : LM1013GAA015
PLANT AREA : TURBINE GENERATOR
PROCEDURE FOR FLUSHING OF SEAL OIL SYSTEM
9.0 Methods
Operate the oil pump and raise the oil pressure gradually to about 2.5 to 3.0 kg/cm2 by
adjusting (bypass) valve of Flushing Unit.
Check the following items during oil circulation.
The oil flow adjusted by Open/Close valves (if oil flow is not sufficiently).
In the beginning period, the interval of circulation and inspection are carried out for short
period (As shown in Table.1)
After performing the above work, replacement for the strainer (120 Meshes) and
hammering (As shown in Table 1and table 2) are carried out.
The following confirmation and recording are carried out every 60 minutes during 1st
flushing.
Reuse the oil used in 1st stage flushing by putting in the temporary oil tank through the
200 meshes strainer.
Install 150 meshes strainer in strainer box.
Carry out the oil circulation and inspection of the strainer (as shown in Table 1)
Carry out heat cycle. Heat cycle target value of oil temperature is approximately 65°C.
3rd Stage Flushing
a. The 3rd stage flushing is carried out as shown in Table.1, Table.2, Fig.2, and LM1013SO01
(9578-001-110-PVE-L-008).
b. In this stage, also flushing circuit is divided into two. In each case of valve condition is as
follows. (Refer to Fig.-2)
Drain flushing oil from oil tank in Flushing Unit, pipes and, manifold.
Remove the temporary bypass pipe, manifold, and flushing Unit as shown in Fig.1.
Inspect and clean the drain regulator tank inside and pipe connections.
Set the temporary valve V4, V5, V6, V7 and flushing strainers (special tool) with valve
according to the Fig.2.
Prepare turbine oil used for operation of turbine generator approximately 600L-800L for
flushing.
Remove filter elements mounted in Air side and H2 side Seal oil filters and the pressure
equalizing valves "01MKW91AA085 / 02MKW91AA085 and 01MKW91AA086 /
02MKW91AA086” as shown in LM1013SO01 (9578-001-110-PVE-L-008).
Put the turbine oil used for operation of turbine generator in the Seal Oil Supply Unit.
Check the valve condition in the seal oil unit for open or close condition according to the
drawing LM1013SO01 (9578-001-110-PVE-L-008) and Fig-2.
Operate the seal oil pump and raise the seal oil pressure gradually to 1.5 to 2.0 kg/cm2 by
adjusting 01MKW91AA081/02MKW91AA081 (Pressure differential regulator) and
01MKW91AA122 / 02MKW91AA122 (Bypass valve of H2 side oil pump).
During circulating oil, station surveillance should be carried out to confirm the oil leakage
from pipe connections.
During above item, check the oil level of drain regulator and keep the oil level higher than
normal level.
Carry out flushing through the seal oil cooler at the end of 3rd flushing.
Hammering is not applied in the 3rd flushing.
3rd stage flushing shall be concluded after achieving criteria mention in clause no.10.
As per QSTGM standard, it is allowable to finish each flushing if the following items are satisfied.
NTPC KHARGONE NTPC DOC NO: COS-COMM-KG-COMMG-PRO/016 Page11
2X660MW L&T DOC NO : LM1013GAA015
PLANT AREA : TURBINE GENERATOR
PROCEDURE FOR FLUSHING OF SEAL OIL SYSTEM
11.0 Restoration of Seal Oil System after completion of 3rd stage flushing
Flushing oil is drained from drain regulator tank, loop seal oil tank & pipes and clean
the tanks.
Restore the pipes to the proper position after cleaning.
Install filter elements in the H2 Side and Air side seal oil filters.
Install the pressure equalizing valves in the Seal Oil System.
Ensure that the system is filled with fresh Turbine Oil ISO VG 32.
Run Seal Oil unit system for 8 hours cycle and proceed for commissioning as per
NTPC Document NO: 9578-001-110-PVE-X-005A (Page No: 557 to 591) and 9578-
001-110-PVE-E-002(Page no:31 to 43).
13.0 Appendices
Fig1. 1st and 2nd stage flushing diagram
Page 12
Fig2. 3rd stage flushing diagram
AA421
AA081
Page 13 of 20
Page 13
Page 14
Page 15
Page 16
Page 16 of 20
Page 17
Page 18
Page 19
RV-3
NB40
MHPS 699990
Page 20
Attachment-1
Stage 1 & 2
Attachment-1
Stage 3
Attachment-2
RV-3
NB40
MHPS 699990