5. OUTPUT: Proper operation of High level drain pump is required for preservation and backfilling, hydro
test of Boiler and operated in recirculation while sample checking.
6. PROCEDURE:
6.1 Start Prechecks:
7 QUALITY:
8 ENVIRONMENT:
Not applicable.
9. OHSAS:
9.1 Persons deployed on the work must use safety helmets, shoes, goggles, dust masks & hand gloves.
9.2 Before starting of any operation, ensure all standard clearance from main control room and shift in charge.
9.3 Ensure deployment of a group of people (2 or more) while carrying out job in an isolated or deserted
place in night shift.
10. ENERGY:
11. RECORDS: VL/CPP/OPER/FILE/05
12. Amendment Table:
Version Changed:
10.05.2015 03 00 1. Company name changed from SSL to Vedanta Limited
2. Company logo changed.