VOLUME HITUNGAN PIPA HVAC HOTEL SANTIKA DEPOK

No Jenis Pekerjaan Panjang Lebar Jumlah Volume Satuan


1 Pipa AC FCU Ballroom 01
- Pipa AC 2" 32.5 32.50 m1
- Pipa AC 1" 4.00 4.00 m1
2 Pipa AC FCU Ballroom 02
- Pipa AC 2" 52.87 52.87 m1
- Pipa AC 1" 4.00 4.00 m1
3 Pipa AC FCU Ballroom 03
- Pipa AC 2" 62 62.00 m1
- Pipa AC 1" 4.00 4.00 m1
4 Pipa AC FCU Ballroom PreFunction
- Pipa AC 2" 42.19 42.19 m1
- Pipa AC 1" 36.20 36.20 m1
5 Pipa Drain AC
- Pipa Drain 2" All Ballroom 40.06 40.06 m1
- Pipa Drain 2" Prefunction 36.44 36.44 m1
- Pipa Drain 1" All Ballroom 3.00 3.00 m1
- Pipa Drain 1" Prefunction 1.00 1.00 m1
6 Pipa Fresh Air
- Pipa Fresh Air 3" Prefunction 9.78 9.78 m1
- Pipa Fresh Air 3" All Ballroom 1.20 1.20 m1
- Pipa Fresh Air 6" All Ballroom 25.08 25.08 m1

REKAPITULASI
Volume Pipa AC FCU 2" 189.56 m1
Volume Pipa AC FCU 1" 48.20 m1
Volume Pipa Drain AC 2" 76.50 m1
Volume Pipa Drain AC 1" 4.00 m1
Volume Pipa Fresh Air 3" Prefunction 9.78 m1
Volume Pipa Fresh Air 3" All Ballroom 1.20 m1
Volume Pipa Fresh Air 6" All Ballroom 25.08 m1