A) Status: Level II
B) Anchored at vicinity 1,900yards North off Sangley PT, Cavite city.
C) Personnel:
LD601 - Ships Crew
Total Assigned-117 (Officer-16; EP-101)
D) Machinery status: All machineries are operational, except SSDG no.3 - on going
repair.
• LCU no. 1 and RHIB no. 1- On-going repair.
• LCU no. 2 and RHIB no. 2- Operational
E) Significant Activities:
• Arrived and anchored at vicinity 1,900 yards North off Sangley Point, Cavite city -
111844H Dec 2020.
• Departed Pier 13, South Harbor, Manila - 111734H Dec 2020
• Repainted lining of helideck, ships number of top deck and forecastle bulkhead.
• Conducted servicing of anchor winch at LCU nr 1.
• Cleaned condenser of hydraulic pack room nr 1 and nr 2.
• Cleaned condenser of chiller unit nr 1.
• Cleaned low and high sea chest of engine and auxiliary room.
• Cleaned FO/LO cooler of main engine nr 1 and nr 2, cleaned FO/LO cooler of SSDG nr
1 and NR 2 of LCU nr 1 (CAPAS).
• Cleaned basket type strainer of SSDG nr 1 and nr 2.
• Conducted servicing of port DC motor starter of LCU nr 1 (CAPAS) main engine.
• Cleaned return exhaust grill at O2, O3 and O4 deck.
• Repair of louver at STBD engine casing - 30 % in progress.
• Conducted cleaning of troops room 7 and 8.
• OPNS officer attended conference ICOW Fleet review with fly-by and closing ceremony
of EXER PAGSISIKAP aboard war room this unit via zoom
• COMMS officer attended lecture of HELOPS aboard CIC room via zoom.
• Conducted daily monitoring of body temperature and blood pressure of personnel
aboard ship and observed COVID19 precautionary measures.
• Conducted disinfection of contact spaces.
• Observed Blue Alert status and ECQ ICOW Declaration of State of Public Health
Emergency.
• Maintained cleanliness and tight security measures aboard ship.
F) CMAV activities:
• OVERALL PROGRESS of CMAV - 88%
H) Weather: Cloudy skies, NE’ly winds prevailing from 1-3 knots, sea smooth and
visibility poor.