A) Status: Level II
B) Moored starboard side to berth nr 1, Pier 13, South harbor, Manila.
C) Personnel:
LD601 - Ships Crew
Total Assigned-117 (Officer-16; EP-101)
D) Machinery status: All machineries are operational, except SSDG no.3 - on going
repair.
• LCU no. 1 and RHIB no. 1- On-going repair.
• LCU no. 2 and RHIB no. 2- Operational
E) Significant Activities:
• Sixty (60) personnel of this unit conducted swab test at MOA arena
• Painting of STBD freeboard – completed
• OPNS, ENG’G AND COMMS officer attended the presentation of outputs and
tabletop exercise re Exer PAGSISIKAP aboard PMC conference room MBRB ,
FBTC
• Repair of ventilation at machinery auxiliary room – 10% in progress.
• Personnel from Keppel Batangas Shipyard assisted by ships force conducted
swing test of P/S rudder and retighten bolts and packing gland of P/S rudder.
• Conducted daily monitoring of body temperature and blood pressure of personnel
aboard ship and observed COVID19 precautionary measures.
• Conducted disinfection of contact spaces.
• Observed Blue Alert status and ECQ ICOW Declaration of State of Public Health
Emergency.
• Maintained cleanliness and tight security measures aboard ship.
F) CMAV activities:
• OVERALL PROGRESS of CMAV - 88%
H) Weather: Cloudy skies, NE’ly winds with rainshowers prevailing from 1-3 knots, sea
smooth and visibility poor.