Project:- BSNL/MEP/Manpower status 10/03/2023

09/03/2023st
Firefighting

Fire Alarm

Plumbing
Electrical

Hutment
Labour

rength
HVAC

Total
Lift
Sr. No Project-Location Remarks

Present Manpower
1 ATC-Mhow 2 N/A 2 2
2 BTC-Goa 2 N/A 2 2
3 BTC-Jabalpur N/A 0 2
4 RNC-Jaipur 4 4 4
5 RNC-Lucknow 0 0 0
6 RNC-Chandimandir 7 0 1 1 9 14
7 RNC-Pune 5 4 0 9 9
8 RNC-Udhampur N/A 0 0
9 RNC-Kolkata 0 0 0
10 NNC-Delhi 18 2 3 0 23 23
11 NLDC-Delhi 3 N/A N/A 3 3
12 DRNC-Bengaluru 11 4 4 4 0 23 23
13 DRNLDC-Bengaluru N/A N/A 0 0
52 6 8 0 8 1 75 82