TG-F-06-04.1.

28

PROJECT: AMAIA STEPS ALABANG ESPERANZA AREA: EE AND AUXILARY ROOM


SUBJECT:ARCHITECTURAL AND MEPFS PUNCHLIST FLOOR LEVEL:4TH FLOOR
DATE: OCTOBER 14, 2022
PUNCHLIST FORM

ACCEPTED/CLOSED BY:
DATE
ITEM ANNEX/ DATE DATE
SPECIFIC FINDINGS/COMMENTS Sub-Contractor/ General APMC-TG (Close-out CLOSED-OUT REMARKS
NO. PAGE INSPECTED RECTIFIED BY APMC-TG
Supplier Contractor Signature)

Presence of PVC Orange electrical conduits and


1 14/10/2022
connectors at EE and AUX Room

2 Check EE and Aux Room doors threshhold gaps 14/10/2022

3 No provided fire extinguisher at EE and AUX Room 14/10/2022

4 Replace corroded screws in electrical panel boards 14/10/2022

Presence of dust accumulation inside tha panel. Provide


5 14/10/2022
vacuum cleaning for all control panels.

6 Provide name tagging for auxiliary panels. 14/10/2022

No provided phase separator for the main circuit breakers


7 14/10/2022
at electrical panel boards

8 Provide cable tagging. 14/10/2022

9 Remove splash paint at junction box 14/10/2022

Remove smoke detector covers and masking tape at EE


10 14/10/2022
and AUX Room

11 Provide bonding jumpers at all electrical panel boards 14/10/2022

12 Provide wire nut connectors at all splice wires 14/10/2022

All electrical conduits must provide "ORANGE" color bond


13 tape at EE room and "YELLOW" color bond tape at AUX 14/10/2022
room
14 EE Room shall have explosion proof lighting as per Plan 14/10/2022

Rev. 05
Punchlisted by: Witnessed by: Fully Closed-Out by APMC-TG
REMARKS:

HENRY JOSEPH L. FULAY _________________________ ______________________________


APMC-TG Representative Contractor Representative Signature Over Printed name / Date