You are on page 1of 8

SCHOOL OF MECHANICAL ENGINEERING

COLLEGE OF ENGINEERING

GROUP REPORT
EVALUATION FORM
COURSE MEM564

CLASS/GROUP EMD5M6B

GROUP NO. 2

No Name Student ID REMARK


MUHAMMAD HARITH HILMI BIN ZEN
1 2019218292 TEAM LEADER
AZHAR
2 MUHAMMAD FARHAN BIN ARIFIN 2019252706 MEMBER
3 MUHAMMAD HARIZ AZFAR BIN AZAHARI 2019257022 MEMBER
4 MUHAMMAD HASIF BIN ILIAS 2019405244 MEMBER
5 MUHAMMAD FARIS BIN KAMAL 2019416056 MEMBER

The group report is to assess Course Learning Outcome 1, 2, 3 and 5 (CLO1, CLO2, CLO3
and CLO5) of the Manufacturing Process Laboratory (MEM564) course.

Selected manufacturing processes laboratory work (such as advanced welding, CAD/CAM,


machining, plastics processing, and the use of metrological instruments) were designed for
students’ engagement in the hands-on activities pertaining to the manufacturing computer
simulation and basic manufacturing practices. The assessment is designed according to the
rubric assessments as appended in the Table 1. This assessment is important to assess the
students’ understanding and reflecting their learning experience.
Instructions:
This is a group work task. Students need to work in a maximum of five (5) members in a group.
Each group must nominate their team leader. Each member is responsible to contribute a
fraction of 10% of the report content as stated in the Table 1. You may highlight your name and
student ID; in the content you have contributed to the report.
WEEKLY WORK CHECKLIST (25%)
WEEK: 10 - 14 DATE: 3/1/2022 - 6/2/2022

TABLE 1: RUBRIC ASSESSMENT FOR MEM564 PROGRESS REPORT


CLO- PO ITEMS/ ASSESSMENT YES NO COMMENTS
CRITERIA

CLO3: Perform laboratory Drawing/simulation


work correctly through progress (5%)
standard operating
procedures with Knowledge about progress
appropriate techniques with (5%)
modern machine and IT
tools/equipment. Work creativity (2%)
PO5: Modern Tool (15%) Follow schedule of planning
(Gantt chart) (3%)

CLO4: Work effectively in a Logbook update (5%)


small group of 3-5
members to collectively Meeting and discussion
undertake and complete evidence (5%)
assigned project.

PO9: Individual and


Google Meet
Teamwork (10%)
Whatsapp

Scoring:
YES: Do it right NO: (1) Do it wrong or (2) No progress at all
Gantt Chart
Progress Report No. : 3 Week No: 10 Date : 03/1/2022 - 09/1/2022

Planning Status Action Plan Person in


charge

Discuss 5/1/2022  We attended the class conducted Every team


Wednesday by Encik Firhan. Lecturer gave us member. Harith,
an explanation about metrology Hariz, Farhan,
via webex meeting. Faris, Hasif.

Discuss 8/1/2022  We had a group discussion on Every team


Saturday whatsapp. member. Harith,
Hariz, Farhan,
 Everybody attended the google Faris, Hasif.
meet link given by Harith and
gave ideas and guidance to
proceed with our project and
progress report.
Progress Report No. : 3 Week No: 11 Date : 10/1/2022 - 16/1/2022

Planning Status Action Plan Person in charge

Online 12/1/2022  Lecturer gave us some Every team


meeting Wednesday explanation about the final member. Harith,
report via webex meeting. Hariz, Farhan,
Faris, Hasif.
 We update our progress
report using google document
platform.

Discuss 14/1/2022  Every group member Every team


Friday attended a google meet and member. Harith,
Hariz presented the progress Hariz, Farhan,
of the mould (core and cavity) Faris, Hasif.

Discuss 15/1/2022  Everybody attended google Every team


Saturday meet and Harith as a leader member. Harith,
distribute task for every Hariz, Farhan,
members for final reports Faris, Hasif.
Progress Report No. : 3 Week No: 12 Date : 17/01/2022 - 23/01/2022

Planning Status Action Plan Person in charge

Class 19/01/22  We joined the class conducted Every team


Wednesday by Encik Firhan, Lecturer who member. Harith,
gave us an explanation of Hariz, Farhan,
fundamental 6, Robotic Faris, Hasif.
Welding and Friction Welding

Discussion 21/01/22  The group members attended Every team


Friday the google meet to work off member. Harith,
and double checked the Hariz, Farhan,
sketch in terms of plate, CNC Faris, Hasif.
program and simulation.

 Group members guide for


other plate sketches.

Discussion 23/01/2022  Team leader invited us to Every team


Sunday discuss the final report on member. Harith,
Google Meet. Hariz, Farhan,
Faris, Hasif.
 Harith assigned task to each
group members to update our
progress on lab project.
Progress Report No. : 3 Week No: 13 Date : 24/1/2022 - 30/1/2022

Planning Status Action Plan Person in charge

Discuss 25/1/2022 Every team


Tuesday  Discuss about the Report member. Harith,
Progress 3. Hariz, Farhan,
Faris, Hasif.
 Update Gant chart, logbook,
and the video simulation

 The discussion have been


made thru Whatsapp.

Simulation 27/2/2021  We discuss and completing Every team


Thursday the simulation member. Harith,
Hariz, Farhan,
 The discussion have been Faris, Hasif.
made thru Whatsapp.
Progress Report No. : 3 Week No: 14 Date : 31/1/2022 - 6/2/2022

Planning Status Action Plan Person in charge

Prepare 2/2/2022 Every team


for Report Wednesday  Discuss about the progress for member.
Progress 3 final report. Harith, Hariz,
and Final Farhan, Faris,
Report  Discuss about Report Hasif.
Progress 3. The discussion
have been made by using
google meet.