PTP-204A TJCYCW

VALVES
PROJECT DESCRIPTION KHULUD PHASE-02 DEVELOPMENT PROJECT ID No GG400KLD0336
PROJECT
SUB-SYSTEM SCALE INHIBITOR SKID A-651001 SUB-SYSTEM No 27-CI-01
DESCRIPTION
PIPING TEST PACK PIPING TEST PACK PIPING TEST PACK No TP-27-CI-01-01
DESCRIPTION

. TEST MEDIUM
PEFS LOCATION

Lines
FILLING LINE

No. Description of Task Signature OK N/A PL


1 Compare the type, pressure class and material of the valve with the design and specification
requirements
2 Check the valve installation for correct direction of flow, particularly for globe check valves
3 End covers of valves shall be removed only immediately before installation and it shall be
checked that the valve is clean
4 Check the proper torque for the handwheel or mechanical actuator
5 Check for proper lubrication of handwheel bearings, spindles and actuator gearboxes
6 Check for free-running of any chainwheel operation
7 Check for correct installation, commissioning and testing of any electric, mechanical or hydraulic
actuator
8 Check that correct pins are fitted at handwheels
9 Check for proper lubrication and adjustment of taper plug valves
10 Check that valve operates smoothly through its full range
REMARKS / OBSERVATIONS:

Comments:

CONTRACTOR - COMPLETED By CONTRACTOR - APPROVED By PDO - ACCEPTED By


Print Name:

Company:

Date:

Signature:

Page 1 of 1 9 Oct 2022 Revision: 0