Professional Documents
Culture Documents
Parapet/Handrail/Crash Barrier
11-12) Plastering work shall be done on parapet along with painting works
Protection works
13-14) If protection works are in fair condition, it shall be retained with routine maintenance.
If damaged partially like poor bonding between the materials, it shall be repaired by compacting, cleaning
15-16)
vegetation etc.
If partial scouring is observed i.e. less than 30cm thick, it shall be repaired by providing approach protection
17-18)
at scoured locations.
If damage is severe like scouring >30 cm thick and more than 50% of its volume eroded it shall be protected
19-20)
by providing new approach protections.
If side slope protection is severally damaged i.e. more than 50% of its volume eroded it shall be provided
21-22)
with new side slope protection.
21A-22A) Guide walls to be provided on either side along the stream.
23-24) If Chute and catch pit is partially damaged i.e. <50% it as to be repaired.
25-26) If Chute and catch pit is severally damaged i.e. >50% it as to be replaced.
Head Wall
Vegetation
39) If spalling is observed, it as to be repaired/treated with high strength non-shrink cementitious grout.
If reinforcement bars are visible it shall be wire brushed, cleaned and treated with anticorrosion coating and
40)
the exposed surface to be patched up with high strength non-shrink cementitious grout.
42) If pipe is severely damaged and has lost it shape/alignment, it shall be replaced with new Pipe.
If structure element is severely damaged and has lost it shape/alignment, it shall be replaced with new
43) structure element. If abutment or box or portal type structures are damaged as above i.e. beyond repair it
shall be recommended for reconstruction of culvert.
44-45) Plastering work shall be done on Return wall/ Wing wall/ Abutments/ Side walls.
46) New parapet /crash barrier shall be provided on approaches along with painting works.
47) New floor protection works with rigid apron shall be provided at culvert location.
S. No Maintenance works/Items for Bridges
Polymer Modified Repair Mortar over leached, honey combed and spalled concrete surface and exposed
7
steel reinforcement shall be provided.
8 All Structural Connections shall be checked and weak joints shall be strengthened.
Chip off loose concrete or delaminated concrete or honey combed concrete till sound concrete surface is
9
encountered without causing Structural Damage to the Girder / Slab / Diaphragms / pier cap.
10 Apply suitable Polymer Bond coat or Epoxy bonding to ensure bond between old and new concrete.
12 Shotcrete/ Guniting/ Grouting or polymer concrete shall be applied to the cleaned surface.
13 Epoxy based protective coatings shall be provided for all steel surfaces.
Safety measures such as Rumble strips / Road humps / Sign Boards shall be provided on either side of
14
bridge to slow down the moving traffic over the bridge.
16 Clean the surface of the sound concrete with wire brush or alternative by sand blasting
22 Seepage/water leakage shall be sealed with passing polyurethane grouting injection system
Settlement of backfill is considered on approach slab at the back of parapet to keep the road surface flat
23
even if backfill settlement occurs
24 General cleaning of Stream bed, road surface, approaches and others elements
25 Plastering works shall be provided for Return wall/ Wing wall/ Abutments/ Side walls
27 New parapet/ Hand Rail/ Crash barrier shall be provided along with painting works