Professional Documents
Culture Documents
There are currently THREE (3) development wells that are planned to come on stream from 01
January 2021. Figure 1 also presents the proposed gas production facility with known pressure and
temperatures. The unknown conditions are also required to complete the design tasks.
Key Assumptions
N2 0.09877 28.01
C1 0.8 16.04
C2 0.0600 30.07
C3 0.03431 44.01
i-C4 0.005 58.124
n-C4 0.0019 58.124
Totals 1.00000
1
Figure 1: Processing facility for the gas oil field
Based on the gas production data in table 2 . Provide an estimate of the following (Indicate on the
graph and show all workings)
2
QUESTION 2 : NATURAL GAS WELL DELIVERABILITY (15 MARKS)
With Production to be considered from three (3) gas wells and assuming each has similar
performance. The following data is presented as reservoir and well conditions during an
isochronal well test for one of the gas wells
Reservoir pressure = 6000 psia, Rock permeability = 1 mD. Tubing inside diameter = 3 in,
Fanning Friction factor = 0.0044 , Average gas deviation factor = 0.93,
Length of well = 13000 ft , average gas viscosity = 0.0137 cp, well head test pressure = 650
psia, Gas production test rate = 10MMSCFD. The result of the well test made it possible to
provide an IPR for each gas well as shown in figure 2 .
7000
IPR
6000 TPR
5000
4000
Pwf (psia)
3000
2000
1000
0
0 3000 6000 9000 12000 15000
Q (MSCD)
a. Determine the bottom hole flowing pressure , Pwf and hence the total pressure drop along
the production tubing that corresponds to the test rate assuming a single-phase gas flows
though the production tubing.( 5 marks)
b. Determine the natural flowing conditions ( i.e., Pwf and corresponding gas production rate
of a typical gas well.
3
(HINT: sketching on figure 2, derive the Tubing performance relationship (TPR) based
on the test bottom hole pressure and production rates) (5 marks)
c. What is the AOF of each well. ( 2 marks)
d. Determine the total operating production rate in MMSCF for all 3 gas wells? (3marks)
The processing sequence on the surface facility is to separate the gas from contaminants and water,
dehydrate the gas, and compress the gas for pipeline transport. Currently, there is need a for design
of surface equipment to process the gas. Key parameters such as vessel pressures and temperature
and sizes of vessels to process the gas from the 3 wells are required.
A two-stage separation has been selected for the production facility based on well stream flow
rate, separation pressures and temperatures. With flashing conditions in each vessel water and
condensates are expected to drop out of solution. A condense rate of 10 bbl/ MMSCF and water
rate of 100bwpd of the total production is expected.
It is also considered to use 2 mins retention time for 2 phase flow and 5 mins for three phase flow
conditions
Given that the separation stage pressure ratio is 1.1 and neglecting pressure drop due to piping
between separators, size vertical and horizontal separators for the flow stream (Note : consider
½ full for the horizontal separator )
Vertical separator
4
Horizontal separator
For the purpose of gas dehydration, size a trayed type TEG glycol dehydration unit based on the
following criteria
Inlet scrubber
5
Trayed type glycol contactor
Reboiler
b. What is the estimated total mass of water expected to be removed Wr, by the dehydration
𝑄𝑠 (𝐶𝑊𝑖 −𝐶𝑊𝑜 )
unit in lb of water per hour ? Use: 𝑊𝑟 =
24
where Wi in inlet water content and Wo is the outlet water content of the dry gas from the
contactor and Qs is the standard flow rate based on 0.7 specific gravity and 100 OF temperature
6
NATURAL GAS TRANSPORTATION
A low suction pressure Ps is expected from the dehydration unit which may not be sufficient for
gas transport via pipeline to the onshore site. Therefore, compressor station is proposed. Knowing
that the Maximum allowable compression ratio per compressor is 4.0 and an efficiency of 85% is
expected. The maximum operating temperature of the pipeline is 1200F. let k = 1.28
b. Based on the discharge temperature, justify if there are any requirements for inter and or
after stage cooling of the gas after compression. (3 marks)
c. Is stage compression required, given the MOP of the pipeline? (2 marks)
7
QUESTION 6: Natural gas Pipeline Transport (15 MARKS)
The dry gas recurved after compression is proposed to be transported via pipeline (neglecting all
forms of elevation) to the onshore facility 90 miles away for further processing.
Relevant information
Base temperature = 60 0F
b. Confirm if the computed internal diameter exceeds the erosional velocity requirement of
100
the pipeline? Knowing that the erosional velocity is computed as, 𝑣𝑚𝑎𝑥 = , where 𝑣𝑚𝑎𝑥
√𝜌
8
9
RELEVANT FIGURES AND EQUATIONS
10
11
GAS CAPACITY FOR VERTICAL HIGH PRESSURE SEPARATOR
12
LIQUID CAPCAITY OF A SEPARATOR
1440𝑉
𝑊=
𝑡𝑟
13
Settling volumes (V) for high pressure vertical separator
14
Settling volumes (V) for high pressure horizontal separator
15
16
17
INLET SCRUBBER SIZING OF A 7.5 FT HIEGHT VESSEL
18
19
GYLCOL CONTACTOR HEIGHT CHART
20
G
COMPRESSOR DESIGN
Theoretical horsepower
PIPELINE DESIGN
21
22