This report has been compiled in good faith to the best of our knowledge and ability in accordance with the information supplied
to us by representatives of the Insured. However, we, PT Asuransi TRI PAKARTA, our shareholders, directors and employees,
hereby disclaim any responsibility whatsoever, for any errors or omissions contained herein or for any loss, damage,
consequential loss or liability howsoever caused, arising from the use of this report, or the information it contains, by any party
whosoever. This report is for internal underwriting use only. The recommendations for risk improvement contained in the report
are purely advisory and the decision and responsibility for implementation rest with the site’s management.
(Risk Point Scale : 4 (Good) … 1 (Poor) – High point indicates good risk)
TOTAL 86
NOTE:
The higher this score, the better the risk quality. Scores or points are calculated using safety aspect and good risk
management indicators. The assessment is based on the available information at the time of this evaluation including tracks
of loss history data. Thus, locations with lower scores are more likely to have large losses.
1. GENERAL
1.1. PURPOSE
Risk Assessment conducted at Apartement Gardenia @Bogor on 07 May 2019 on Jl. K S Tubun
No.102, Cibuluh, North Bogor, Bogor, West Java. Within the framework of insurance coverage and
to know the latest conditions on the subject of coverage and risks that are in the object.
And look at aspects of general construction and protection facilities against fire, blasting and other
risks.
This information is used to evaluate existing prevention and control measures, and also suggests
improving and reducing overall hazards.
During conducting a location survey, we met with several people representing the Insured, as
follows:
Mr. Dian – Technical Head
Mrs. Titi Mumpuni – Technical Staff
And some of the people involved were very cooperative during our survey.
1.2. DISTRIBUTION
The report is used by the Insurer, the relevant Branch Office and Some Reinsurance Companies
and or Reinsurance Brokers.
Recommendations for Rising Risks are submitted to the Insured by the relevant Branch Office.
2. OCCUPANCY
PT. Duta Senawijaya Mandiri is part of the Takke Group engaged in property business. Takke Group built
a Gardenia Bogor apartment on an area of 1.3 ha and there are two towers. Each tower has a height of
25 floors which summarizes 1,539 units of various types. The number of units is divided into 465 units of
Raflesia tower and 1,074 units of Bougenvile tower.
Various facilities are provided at the Gardenia Bogor apartment, including a swimming pool, jogging
track, playground, fitness center, sky garden, 24-hour security, and commercial area. Here also will be
built a 1,000 m2 commercial area and lifestyle center to meet the needs of residents.
The project area is 88,683 M2. This apartement has 2 towers building. They are Bougenville (U shape)
and Raflesia (L shape).
There is 3-meter-high zinc fence that surrounds the project area as a barrier to the outside area
and the entrance door on the site is guarded by security.
From the basis of the boundary factors and the properties located around the location, the
exposure of the surrounding property can be considered Low to Medium.
Based on the existing layout, the building can be included in the category as 1 Fire Zone because
the distance between buildings is unadequate.
between the towers there is an area that is one, namely the commercial area and the basement
area which is the parking area of the vehicle. in that area there is no separate firewall to prevent
the fire from spreading to other buildings
4. PROCESS DESCRIPTION
4.1. OPERATION PRODUCT FLOW
PT Duta Senawijaya Mandiri appoints PT. Pembangunan Perumahan (Persero) Tbk as the main
contractor to build this apartment. This project began in 2014 where the installation of the
foundation using piles was carried out by PT. Sunway Yasa Mandiri. After the installation of the
pile was completed in 2015, the handover of the project was carried out to PT. Pembangunan
Perumahan (Persero) in the same year. This project will be completed in October 2019.
The development of this apartment development has now reached 50% - 60%. in 2017 the
apartment building has been carried out "Topping Off". meanwhile the current stage is the
finishing stage, namely ME (Mechanical Electrical). In finishing work there are also welding
activities
5. HAZARDS ANALYSIS
Layout design This apartment project will have as many as 24 floors of buildings
with additional 2 floors of basement. There are 1527 units of
apartment rooms with studio types and 2 bedrooms types. And there
is also a swimming pool and commercial area that complements the
supporting facilities in the apartment. While the basement will be
used as a vehicle parking lot (193 cars) and a transfomator room,
generator room and hydrant pump room.
Control of process The power cord uses PVC sheathed cables and most of the lighting for
the project using uncovered fluorescent lights.
Material Handling The stock materials that will be used in the construction of apartments
are stored in the project location with a bounding tape. The material
stock is arranged neatly and does not obstruct the evacuation route that
is in the project
6. PROTECTION Point : 3
• Sprinkler System,
Not Installed
• Detection System,
Not Installed
• CCTV,
There are 16 CCTV units and and a CCTV monitor in a contractor room
• Hydrant System,
Currently the contractor is installing a hydrant system. Most of the hydrant pipes have been
installed and the hydrant box has been installed in the tower apartment. However, the hydrant
pump has not been installed by the contractor yet.
• WaterSupply,
A ground tank with a capacity of 400 m3 equipped by a jockey pump has been prepared by the
contractor but there is no water supply in the ground tank.
• Siamese Connection
Not Available
• Safety Nets
There is safety net installed by the contractor to keep the objects falling and the contractor also
places a barrier in front of the elevator column
6.3. MAINTENANCE
In general, the fire protection system provided at the site is rated medium average compared to
the inherent operational hazards given.
8. SPECIAL PERILS
Burglary and Theft Low All activities are monitored and supervised by
3
security forces
Vandalisme Low The area monitored and supervised by security
3
forces
Riot, Strike, Malicious Low The wages have been adjusted to the provisions of
Damage, Civil the local government 3
Commotion
Sabotage and Terrorism Low Site is not a target of terrorism. There are no
4
recorded losses.
Vehicle Damage Low Roads inside premesis areas are considered
adequate for vehicle movements. The area is
equipped with route markers, speed limit signs and 4
directions. Vehicles that are entered are supervised
by security personnel
Water Damage Medium - The possibility of damage due to water can occur
High because there are holes that are not closed crane
foundations so that the water entering the project
moistens the stock material and floods the area in
the building.
Smoke Damage Low There is no effect on the stock of goods in the project
3
area.
Aircraft Impact Low Far from commercial airports. The nearest
commercial airport is Halim Perdana Kusuma 4
Airport, about 32,51 km (straight linear distance)
9. NATURAL PERILS
Total N/A
NO. 05.2019.01
Protection
Fire Protection system is installed and maintained fully appropriate to the hazards present 4
Fire Protection System is installed and maintained sufficiently appropriate to the hazards present as to be acceptable
3
without the need for improvement
Fire Protection System is installed and maintained below the standard appropriate to the hazards present 2
Fire Protection System installed and maintained significantly below the standard appropriate to the hazards present 1
Construction
No combustibility 4
Limited combustibility 3
Combustible materials but slow burning 2
Combustible Materials, Contribute to fire spreading 1
Time Schedule