Professional Documents
Culture Documents
1 MANAGEMENT OF CHANGES
1.2 RESPONSIBILITY
The overall responsibility for managing the changes affecting various activities in office
and Vessels lie with the Head of Ship Management team.
The Head of CMS team is responsible for monitoring the changes affecting the office.
The Master is responsible for monitoring the changes affecting the vessel.
each employee of the company has the responsibility to become aware of the Management
of change process.
1.3 DEFINITION
Change:
Change means a temporary or permanent substitution, alteration, replacement (not in
kind), modification by addition or deletion of organization, personnel, critical equipment,
applicable codes, operating limits, procedures, emergency response equipment from the
present configuration whether they are planned or out of emergency.
Management of change:
Changes affecting the ships and offices can introduce new hazards, which if not identified
and managed in time, could result in incidents. A well-defined process for approving the
changes, prior to their implementation is called Management of change.
1.6 INITIATION:
All staff in ships or in office is responsible for identifying a need for change. Ship staff
shall inform either Master about the need for a change. Similarly, office staff shall inform
any Superintendent about the change identified. Whenever there is a change is identified,
the change initiator (Master / Marine & Tech Superintendent) shall fill up the relevant
section of the Change request form, including the reason & the source for the change
requirement; justification for the change and send to change coordinator for endorsement
(Organizational and Operational changes – to Marine Superintendent / Engineering
changes to Technical Supt) If there are any supporting documents that can also be attached
with the filled-up form.
The initiator shall provide sufficient details to enable the objectives of the proposal is fully
understood.
The filled-up Change Request form shall be submitted to Change Coordinator. One of the
Marine or Technical Superintendent will be the change coordinator. The Change Initiator
could also be Change Coordinator.
1.7 ENDORSEMENT
The Change Coordinator shall receive the Change request form and analyse the change
request based on the justification, other options, and budget requirements. If he considers
that the change proposed is likely to be implemented, then only he will endorse the change
proposal for further review. He will fill in the relevant sections of the Change request
form, informs the Master and will coordinate for registration of the change.
Any proposed change is approved at an appropriate level and not by the person directly
involved in the change. (Ref 16.5.5)
registers the request in Change Register and issues a unique number for the change
proposed.
Once the change is registered and given number, the Change Administrator shall fill in the
relevant section of the Change request form and inform the Change Coordinator and the
Master. He will start collecting all the records associated with the change proposed like
risk assessment, meeting minutes etc., till the change is closed out. Even if the change
proposal is rejected or not progressed, details must be collected and documented as to why
the change proposal is rejected.
He / She will maintain the status of all change requests in the data base whether they are
open or closed. The records (like the signed change request forms or risk assessments) will
also be stored in the data base for each change requested.
1.10 APPROVAL
The approving authority may:
approve the change plan
alter or send it back for revision, if he determines that certain aspects of the change
proposal are unacceptable or need more work
Reject it if the plan is not suitable.
If the change is approved under some conditions, then these conditions shall be clearly
described in the Change Request form. While approving temporary change, duration for
approval shall be highlighted. For permanent changes, proposed time scale for
implementation shall be highlighted.
After the change is approved, it may be implemented. Change coordinator shall send the
approved change request form along with other records such as risk assessments etc. to
change administrator for maintaining records.
Approving authority for changes are mentioned in the below table:
SL NO CHANGE CLASSIFICATION APPROVING AUTHORITY
VERY HIGH & HIGH BASED ON RISK ASSESSMENT Head of Ship Management
1 HIGH BASED ON COST (Above 100,000 USD) / Head of Technical / Head of
CMS
MEDIUM BASED ON RISK ASSESSMENT Marine Manager / CMS
2 MEDIUM BASED ON COST (50,000 ~ 100,000 USD) Manager / Technical
Manager
LOW & VERY LOW BASED ON RISK ASSESSMENT Marine Manager / CMS
3 LOW BASED ON COST (Below 50,000 USD) Manager / Technical
Manager
1.11 IMPLEMENTATION
Once the change proposal is approved, a step-by-step implementation plan shall be
developed to ensure that the implementation of change is carried out:
All identified hazards are mitigated or controlled by the identified risk reduction measures
With minimum interference to other routine activities
By maximizing the use of available resources
After the training is provided to relevant personnel
Complying with all relevant permit to work system
Within the planned time line
Change Coordinator is responsible forming a change implementation team and for
planning the implementation of the change in consultation with Master and other personnel
as required. Once the implementation plan is developed, it shall be circulated to all
concerned personnel including the Change Administrator for record keeping.
The implementation plan should describe how the change would be tested prior to
implementation, where it is possible. This will greatly reduce unwanted surprises and
delays.
The required material, equipment and contracted services shall be arranged as necessary.
All the implementation work should be in compliance with the Permit to Work system.
Regular updates on the progress of the change implementation should be reported to
office.
If the change cannot be implemented within the proposed time line, the change shall be
reviewed once again and revalidated.
1.12 COMMUNICATION
Successful change requires the engagement and participation of the people involved.
Communication before, during and after the change is one of the most important aspect of
the change management process.
The Change Coordinator has to ensure that all the end users of the changes are informed of
the change.
To achieve support of all personnel in a change management, proper communication shall
be established to ensure that:
Sufficient advance notice is given before implementing any change, especially if a
response is expected.
Affected staff knows to whom they should respond to, if they have comments or concerns.
The impacts, hazards associated with change and mitigation requirements are well
communicated across the organization
All employees are informed when the change is implemented
JNM - SHIP MANAGEMENT MANUAL
1.13 DOCUMENTATION
The change should be fully incorporated into the management system. The procedures
affected by the change should be amended by following the required document change
procedure as explained in Ch. 11 of this manual.
The changes to designs should be reflected in drawings and copies of design changes shall
be made available to operating personnel as well as to maintenance personnel.
Documents that may be affected may be as below, but not limited to;
Certification.
Manuals.
Plans and drawings.
Operational procedures.
Records checklists and forms.
Planned maintenance including spare parts inventories.
Masters and Chief Engineers, after joining a ship and taking over, should issue their own
set of standing orders, and have the pertinent officers sign them. After successful take
over, both Master and Chief Engineer should carry out a thorough inspection of their
respective departments, as per the takeover audit checklist, and forward the completed
report to the office within 14 days of takeover.
HAND OVER (OTHERS)
The Master must ensure that in advance of a crew change, all relevant hand-over notes
(including inventories) are prepared by each member of the shipboard management team
and other crewmembers as appropriate.
These notes should be concise while covering all key areas of activity. The members of the
shipboard management team are responsible for preparation. A copy should be retained on
board for the verification of the Superintendent (if required). The Chief Officer and the
2nd Engineer additionally complete the takeover audit checklist according to their
respective positions, and the report should be sent to office within 14 days of takeover.
The hand-over period for senior staff will be determined by the Technical Superintendent
in-charge of the concerned vessel.
HANDING OVER CALL
When the change of top four ranks on board is planned, the technical/marine
superintendent shall:
Obtain the handing over notes of outgoing officer one week before the planned sign off.
Go through the handing over notes and verify that outstanding defects on board are
mentioned and updated in ship-palm defect reporting module.
Conduct a telephonic ‘handing over call’ with the outgoing and the incoming officer as per
JNM - SHIP MANAGEMENT MANUAL
the handing over notes and discuss the outstanding defects on board.
Outline the corrective action plan for defects with the incoming officer.
The call shall be recorded in the respective handing over form in ‘additional information
section’.
OPERATIONAL CHANGES FROM DOCUMENTED PROCEDURES
All operational changes from the documented procedures shall be of temporary nature with
a definite time limit.
Should it become necessary to deviate from the documented procedures, the Master or the
office staff involved in the process shall send the required deviation from the procedure
along with the justification for the change and risk assessment done showing the impacts
of the changes proposed to the Marine Manager. The Marine Manager will coordinate for
a HSE and technical review of the proposed deviation from the procedure by relevant
department personnel. Based on the review result, the Head of Ship Management will
approve the temporary change from operating procedure.
TEMPORARY CHANGES TO ALARM SETTINGS / DEACTIVATION OF ALARMS
Temporary changes in settings of any equipment from the maker’s or statutory
recommendations and temporary deactivation of any critical system safety alarms shall be
carried out in accordance with the procedure explained in this section.
Any permanent changes to alarm settings shall go through the process explained in section
16.5 of this procedure.
Critical and safety systems include but not limited to:
Fire Alarms, Fire Pumps & Emergency fire pumps, Fixed Fire Fighting Systems, Overfill
Prevention or Warning Systems, Thermal/Pressure Relief Valves, ME alarms, UMS
alarms, AE alarms
Critical systems / equipment is reflected in the vessel specific computer-based PMS.
Temporary changes on critical system safety alarms / controls must be controlled
and authorized using the form “Temporary changes to critical system safety alarms”
Prior to planned deactivation of alarms or changing any settings of any safety alarms
/ controllers, the Chief Engineer or Chief Officer shall complete the Form. Steps will
involve identifying the risk involved, the action planned to mitigate the risks and the
personnel who will be informed of the intended changes. Master will confirm the steps and
send the form to Technical Superintendent for approval.
Technical Superintendent will go through the request, discuss with the Fleet Manager if
necessary.
He will send a mail to the vessel approving the changes and duration of approval if the
changes planned are safe. Master will attach the email copy with the form and send it to
the Chief engineer or Chief Officer who will carry out the changes to settings or the
deactivation of alarms. Upon completion of the job planned or after the expiry of the
approval duration, the alarm system shall be reinstated to original position and the
technical superintendent shall be informed.
If the job is not completed, for any extension, the process has to be repeated.
carefully managed to ensure restoring of system within time frame. Duration of temporary
MOC should be based on the expected time frame as well as any increase in risk.
The maximum life of a Temporary MOC shall be 60 days from the date of approval.
However, to evaluate the risk during change, risk assessments shall be validated every 15
days.
In addition, the management of change procedures for temporary changes shall ensure that
the equipment and procedures are returned to their original or designed conditions at the
end of the time limit for the temporary change. If any extension is required for a temporary
change, it should go through the complete management of change process again.
1.19 Records:
Engineering and Organization Change Request Form: TE-19
“Temporary changes to critical system safety alarms” (Form No TE 28)
APPENDIX 1
JNM - SHIP MANAGEMENT MANUAL
(This section is specific to PT Jala Nusantara Mardika)
Rev No: 0.0
APPENDIX I Rev Date: 25 April 2023
Page: 1 0f 1