48x tie ø = 48(10) = 480mm


COLUMN 9a AT 2nd FLOOR
Beam Ext./Int LL DL span RLL RDL c. Least Dimension = 200mm
B1 Ext. 1.58 20 2.5 1.98 25 ∴ use 10mm ties @ 200 mm O.C.
B3 Int. 1.58 16 2.5 2.27 23
B9 Ext. 5.76 22.50 2.5 7.20 28.13

AXIAL CAPACITY

Pu2 = ϕ0.80[0.85f’c(Ag-Ast)+f’yAst]

109,680 = (0.70)(0.80)[(0.85)(27.6)( Ag-0.0.02 Ag)


+(414)(0.02 Ag)] MAXIMUM STEEL RATIO

109,680 =(0.56)[23.46(0.98 Ag+6.21 Ag)] π


Ast= ØN
109,680 =(0.56)(22.99 Ag+8.21 Ag) 4
109,680 = 17.51 Ag π 2
Ast= 16 (6)
Ag= 6,263.85 mm2 = t2
4
Ast= 1206.37mm2
√ 6,263.85 = t = 79.14mm 2

A st
∴ Use 200mm x 300mm section of Column Pg=
Ag
Ast= 60,000 (0.02) = 1,200mm2
1,206.37
Pg=
TOTAL REACTION
60,000
NUMBER OF BARS
Pg= 0.0201 >0.08>0.01 ∴ OK
RLL = RB1LL + RB3LL + RB9LL
π
øN=1200
RLL = 1.98 + 2.27 + 7.20 4
MAIN BAR SPACING
RLL = 11.45 kN/m 1200

( )
Spacing in b
N= π
(162 )
RDL = RB1DL + RB3DL + RB9DL 4 t−2 ( cover ) −2 ( n. of ties )−n . of main bars (ø bars )
S=
RDL = 25 + 23 + 28.13 N= 5.97 say 6 Bars 1

RDL = 76.13 kN/m 200−2 ( 40 )−2 ( 10 )−2(16)


S=
USE 200mm X 300mm Column w/ 6-16 mm Bars 1
S= 68mm>40mm ∴ OK
Pu2 = 1.2(DL) + 1.6(LL)

Pu2 = 1.2(76.13) + 1.6(11.45) SPACING OF TIES

a. 16xdb = 16(16) = 256 mm Spacing in d


Pu2 = 109.68kN or 109,680 N
t−2 ( cover ) −2 ( n. of ties )−n . of main bars ( ø barsRLL) = 22.9 kN/m 1200
S=
( )
Beam Ext./Int LL DL span RLL RDL
2 N= π
B1 Ext. 1.58 20 2.5 1.98 25 (162 )
B3 Int. 1.58 16 2.5 2.27 23 4
300−2 ( 40 )−2 ( 10 )−3 (16)
S= B9 Ext. 5.76 22.50 2.5 7.20 28.13
2 N= 5.97 say 6 Bars

S= 76mm > 40mm ∴ OK


RDL = 2(RTOTAL DL) + (w. of Column) USE 200mm X 300mm Column w/ 6-16 mm Bars
RDL = 2(76.13) + (23.6)(0.2)(0.3)(3)

RDL = 156.51 kN/m SPACING OF TIES

a. 16xdb = 16(16) = 256 mm


nd Pu2 = 1.2(DL) + 1.6(LL) b. 48x tie ø = 48(10) = 480mm
COLUMN 9b AT 2 FLOOR c. Least Dimension = 200mm
Pu1 = 1.2(156.51) + 1.6(22.9) ∴ use 10mm ties @ 200 mm O.C.

Pu1 = 224.45 kN or 224,450 N

AXIAL CAPACITY

Pu2 = ϕ0.80[0.85f’c(Ag-Ast)+f’yAst]

224,450 = (0.70)(0.80)[(0.85)(27.6)( Ag-0.0.02 Ag) MAXIMUM STEEL RATIO


+(414)(0.02 Ag)]
π
224,450 =(0.56)[23.46(0.98 Ag+6.21 Ag)] Ast= ØN
4
224,450 =(0.56)(22.99 Ag+8.21 Ag)
π 2
224,450 = 17.51 Ag
Ast= 16 (6)
4
Ag= 12,818.39 mm2 = t2 Ast= 1206.37mm2

√ 12,818.39 = t = 113.22 mm 2
A st
Pg=
∴ Use 200mm x 300mm section of Column Ag
Ast= 60,000 (0.02) = 1,200mm2 1,206.37
Pg=
60,000
REACTION
NUMBER OF BARS Pg= 0.0201 >0.08>0.01 ∴ OK
RLL= 2(RTOTAL LL)
π
RLL= 2(11.45) øN=1200
4
MAIN BAR SPACING TOTAL DEPTH= 150+16+75
Beam Ext./Int LL DL span RLL RDL
Spacing in b TOTAL DEPTH= 241 mm
B1 Ext. 1.58 20 2.5 1.98 25
B3 Int. 1.58 16 2.5 2.27 23
t−2 ( cover ) −2 ( n. of ties )−n . of main bars ( ø bars )
S= B9 Ext. 5.76 22.50 2.5 7.20 28.13
1 EFFECTIVE SOIL PRESSURE

200−2 ( 40 )−2 ( 10 )−2(16) qe= qa - ych c- yshs


S=
1 qe= 200 – (23.6)(0.25) – (18.70)(0.60)

S= 68mm>40mm ∴ OK qe= 182.88kN/m

Spacing in d AREA OF FOOTING


TOTAL REACTION
t−2 ( cover ) −2 ( n. of ties )−n . of main bars ( ø barsRLL) = 2(RTOTAL LL) T DL +T ¿
S= A=
2 qe
RLL= 2(22.9)
300−2 ( 40 )−2 ( 10 )−3 (16) RLL= 45.8 kN/m 322.93+ 45.8
S= A=
2 182.88
S= 76mm > 40mm ∴ OK 2
RDL = 2(RTOTAL DL) + (w. of Column9a) + (w. of Column9b) A=2.01m
RDL = 2(156.51)+ (23.6)(0.2)(0.3)(3) + (23.6)(0.2)(0.3) BASE, B = √ 2.01
(4)
BASE, B = 1.42m
RDL = 322.93 kN/m
∴ 1.50m

FOOTING AT COLUMN 9

TOTAL DEPTH, FOOTING

MIN. REQ’d DEPTH =150mm

Assume= 150mm STEEL BARS USING MINIMUM rho = 0.005

Assume Bar ø = 16mm Where:

MINIMUM CONCRETE COVER= 75mm b = 1.50m strip = 1500 mm

d = depth of footing above reinforcement + ½


of assumed bar ø
d = 150 + ½(16) = 158mm

As= ρbd

As= (0.005)(1500)(158)

As= 1,185mm2

SPACING

Using 16mm with As of bar used = 201.06mm2

(201.06)(15 00)
Spacing =
1185
Spacing = 254.51 say 200 mm < 450mm ∴ OK

∴ USE 16mm FOOTING BARS SPACED AT 300mm