JOB PROGRAM
APPROVED SHEET
PREPARED BY:
Karrar Ali 2023/01/01
(Anton)
REVIEWED BY:
Zhang Bin 2023/01/01
(Anton)
VERIFIED BY:
Hu Zihui
(WSD Deputy Manager)
2023.01.02
10:00:58 +03'00'
APPROVED BY:
Cai Wenxin
(WSD Manager)
Issue Rev V1.0
WELL STIMULATION JOB PROGRAM
CLIENT: PETROCHINA
WELL NO: HF0888-M0888H1 Date 2023.01.01
Contents
1. Objectives ................................................................................................................... 1
1. Objectives
Eliminate the damaged pay zone.
Enhance oil productivity.
2. Well information
Basic data
TD (m) G. L RKB-G.L
Location Well Well Type
(Driller depth) (m) (m)
Halfaya Iraq HF0888-M0888H1 Horizontal Well 3910.0 MD/ 2936.12 TVD 4.67 9.60
Reservoirs
Oil Density
Formation Pressure Formation Temp H2S
Reservoirs (At Surface)
(psi) (℃) (ppm)
API
3107.3- 3125.13
3125.13- 3333.55
3333.55- 3462.97
3462.97- 3891.5
Note: Well completion schematic is taken from<HF0888-M0888H1 Final Completion Report July 2019>.
Wellhead schematic
Note: Wellhead schematic is taken from<HF0888-M0888H1 Final Completion Report July 2019>.
Well history
HF0888-M0888H1 has been drilled as a development horizontal well to final total
depth of 3910 m MD/ 2936.12 TVD from Apr 13, 2019 to June 29, 2019 using
DQ1205 drilling rig. Cased and cemented with 7” production casing (7” Casing
Shoe depth @ 3102m MD) to the surface. 6” horizontal hole section drilled to
3910 m MD.
3. Design principle
Horizontal interval length is 808.0m (3102.0- 3910.0m). Due to long interval
length a low permeability, coiled tubing acidizing is recommended to be
performed.
According to formation properties, Acid strength is recommended around
0.25m3/m which will penetrate around 0.59m deep into formation. Permeability
(average 5.27mD) for this well is less than the average value (20mD) in Halfaya
oilfield. Porosity (average 18.87%) for this well is better than the average value
(15%) in Halfaya oilfield.
In order to treat more formation damaged and /or less permeable areas and achieve
better stimulation result, 15% main acid and 15% diverting acid will be used to
treat the Mishrif perforation intervals. Selected Main Acid: Diverting Acid =2:1.
No. Formation interval Length 15% main acid(m3) 15% diverting acid(m3) Post flush(m3)
4. Pre-job stimulation
CT Specifications
OD L Thickness W.P Weight Inner volume Total inside volume L.C
(mm) (m) (mm) (MPa) (Kg/m) (m3/1000m) (m3) (T)
Hydra calculation
Coiled tubing friction pressure was simulated by CTES. According to simulation,
0.25-0.35m3/min can be chosen as theoretical pumping rate for main acid and
Safety formation calculation: PF≥Pp+ Ph- Pf, Pp≤PF - Ph + Pf; considering the limiting
condition, if pumping rate = 0, Pf = 0, which means the wellhead pressure that does not
exceed 17.4MPa will not frac the formation.
5. Operation program
Collect related equipment and tools and assemble.
Mobilize equipment required to location.
Hold Pre-job safety meeting with supervisor and related teams on location.
Functional test BOP and R/U CTU and all related equipment.
Pressure test as per procedure and below table.
Low Pressure Time Minutes High Pressure Time Minutes
Acceptance criteria
(MPa) (min) (MPa) (min)
Coil Tubing
check the actual CT depth. If CT met obstruction, immediately perform pull test and
try to pass without pumping; If cannot pass, try to pass it by circulating water until
remove the obstruction.
Note: If cannot pass for 30 minutes when met obstruction, report to PCH supervisor and execute acidizing pumping schedule as plan
(pls refer to everyday job plan and Appendix 5).
Start performing acidizing job. Pumping 5.35m3 main acid to displace water inside of
CT, as soon as main acid arrives at nozzle, zero the pumping volume, perform as per
below pumping schedule.
Pumping schedule
CT depth CT speed Stage Total
Stage Total
Pump rate
Step m m/min Fluid on nozzle Volume Volume time time Choke
0 3910.00 3910.00 - - 15% Main acid 5.35 0.25-0.35 Displace 17.8 17.8 open
Section 1: 3910-3775.55m
3910.00 3842.78 - 5-8
1 15% Main acid 6.5 0.25-0.35 6.5 21.7 39.5 close
3842.78 3842.78 - -
3842.78 3775.55 - 5-8
2 15% Main acid 5.0 0.25-0.35 11.5 16.7 56.2 close
3775.55 3775.55 - -
3775.55 3842.78 5-8 - 15%Diverting
3 6.0 0.25-0.35 17.5 20.0 76.2 Close
3842.78 3842.78 - - acid
8 3294.91 3333.55 5-8 - 15%Diverting 3.0 0.25-0.35 182.0 10.0 624.5 close
Shut-in the well 1 hour for soaking after finish all the pumping. Meanwhile, POOH
coiled tubing to 1000m at the speed of 15-20m/min.
Open the well, monitor wellhead pressure.
If well flow constantly. Confirmed with PCH supervisor, POOH CT to surface. Rig
down all equipment and recover the operation area, hand over the well to BH Rig and
demobilization.
If well confirmed no flow. Confirmed with PCH supervisor, shut in the well and
activate the well with N2 lifting.
Start pumping N2 as below procedure while monitoring WHP. RIH CT per 500m with
pumping N2 till 2500m. Monitor well status and adjust choke size accordingly. CT
depth not exceeds 2500m finally. Check flowback from testing choke manifold.
No. Depth, m Length, m POO/RIH Speed, m/min POO/RIH Time, hr N2 Lifting Time, hr
1 RIH: 0~1000 1000 15-25 0.85 /
2 Keep @ 1000 / / / 0.30
3 RIH: 1000~1500 500 8-12 0.85 0.85
4 Keep @ 1500 / / / 0.30
5 RIH: 1500~2000 500 8-12 0.85 0.85
6 Keep @ 2000 / / / 0.30
7 RIH: 2000~2500 500 8-12 0.85 0.85
8 Keep @ 2500 / / / 0.40
9 POOH: 2500~300 2200 8-12 3.67 3.67
10 POOH: 300~0 300 5-10 0.63 /
Total 7.70 9.00
When the well is self-flowing with stable parameters (WHP, FLT), confirmed with
PCH supervisor, stop pumping nitrogen. POOH CT to surface, rig down all equipment
and recover the operation area, hand over the well and demobilization.
0 Obstruction Obstruction - - 15% Main acid 5.4 0.25-0.35 Displace 17.8 17.8 open
Section 1: Obstruction-3775.55m
Obstruction 3775.55 - 5-8
1 15% Main acid 11.5 0.25-0.35 11.5 38.3 56.2 close
3775.55 3775.55 - -
Section 2: 3775.55-3672.05m
3775.55 3740.35 - 5-8
1 15% Main acid 3.5 0.25-0.35 42.0 11.7 157.8 close
3740.35 3740.35 - -
Section 3: 3672.05-3563.55m
1 3672.05 3617.50 - 5-8 15% Main acid 4.5 0.25-0.35 72.0 15.0 257.8 close
3617.50 3617.50 - -
Section 4: 3563.55-3453.55m
Section 5: 3453.55-3333.55m
3 3373.00 3333.55 - 3-5 15% Main acid 3.0 0.25-0.35 139.0 10.0 481.2 close
3333.55 3333.55 - -
3333.55 3373.00 5-8 - 15%Diverting
6 3.5 0.25-0.35 142.5 11.7 492.8 close
3373.00 3373.00 - acid
-
3373.00 3413.00 5-8 - 15%Diverting
7 3.5 0.25-0.35 146.0 11.7 504.5 close
3413.00 3413.00 - - acid
Section 6: 3333.55-3218.65m
Section 7: 3218.65-3102.0m
2 3179.97 3141.00 - 3-5 15% Main acid 3.5 0.25-0.35 202.0 11.7 691.2 close
3141.00 3141.00 - -
If obstruction depth is between 3810.0 and 3710.0m (100~200m), abandon section 1 and perform
below pumping schedule:
Pumping schedule
CT depth CT speed Stage Total Stage Total
Pump rate
Step m m/min Fluid on nozzle Volume Volume time time Choke
From To RIH POOH m3 m3/min m3 Min Min
0 Obstruction Obstruction - - 15% Main acid 5.35 0.25-0.35 Displace 17.8 17.8 open
Section 2: Obstruction-3672.05m
Obstruction 3705.25 - 5-8
1 15% Main acid 5.0 0.25-0.35 5.0 16.7 34.5 close
3705.25 3705.25 - -
3705.25 3672.05 - 5-8
2 15% Main acid 4.0 0.25-0.35 9.0 13.3 47.8 close
3672.05 3672.05 - -
3672.05 3705.25 5-8 - 15%Diverting
5 4.5 0.25-0.35 13.5 15.0 62.8 close
3705.25 3705.25 - - acid
If obstruction depth is between 3710.0 and 3610.0m (200~300m), abandon section 1&2 and
perform the below pumping schedule.
Pumping schedule
0 Obstruction Obstruction - - 15% Main acid 5.35 0.25-0.35 Displace 17.8 17.8 open
Section 3: Obstruction-3563.55m
Section 4: 3563.55-3453.55m
12 3527.55 3491.05 - 3-5 15% Main acid 3.0 0.25-0.35 55.0 10.0 171.2 close
3491.05 3491.05 - -
Section 5: 3453.55-3333.55m
Section 6: 3333.55-3218.65m
11 3333.55 3294.91 - 3-5 15% Main acid 3.5 0.25-0.35 118.0 11.7 381.2 close
3294.91 3294.91 - -
Section 7: 3218.65-3102.0m
If obstruction depth is between 3610.0 and 3510.0m (300~400m), abandon section 1&2&3 and
perform the below pumping schedule.
Pumping schedule
0 Obstruction Obstruction - - 15% Main acid 5.35 0.25-0.35 Displace 17.8 17.8 open
Section 4: Obstruction-3453.55m
Section 5: 3453.55-3333.55m
Section 6: 3333.55-3218.65m
Section 7: 3218.65-3102.0m
6 3102.00 3141.00 5-8 - 15%Diverting 3.5 0.25-0.35 110.5 11.7 386.2 close