Professional Documents
Culture Documents
D.W. Buntine
Aurizon, Australia
daniel.buntine@aurizon.com.au
Who am I?
4
Fifty mines Five export ports
Where is the Aurizon Network? Darwin
Port of Townsville
Port Walcott Port Hedland Port of Abbot Point
Dampier Port Mt Isa
Port of Hay Point
Port of Gladstone
Brisbane
Perth
Port of Newcastle
Sydney
Adelaide
Melbourne
Hobart
5
CWR History in Aurizon
• First introduced with major upgrades
in 1980’s
– Track upgraded to 53-60kg/m on
concrete e-clip sleepers
• Rolling upgrades were completed
over multiple years
– Processes were refined and optimised
by trained crews
– Practice was largely taught from
generation to generation
• Many of the wise experts retired in
the last decade
• Shortcuts began to be taken
6
7
The catalyst for change
Level crossing upgrades General Track Track lifting to new design alignment General Track
Rail break repair Long Rail Turnout Rail/Component Replacement Short Rail
Rail crack repair Short Rail No action
Turnout Repairs – up to three bearers, no rail cut
required
Rail installation/repair – <15 metres Short Rail
Weld Replacement Short Rail
Rail installation/repair – ≥15 metres Long Rail
10
Mandatory requirements
MANDATORY REQUIREMENTS Tem porary only
Rail Stress Control Rail Stress Risk
Category Ballast Control Method Definitions
Method Mitigation
Clip-up Temperature Covers most types of track w orks,
General Track Works Track Consolidation Rail Adjustment Control -or- unless categorised differently
Stress Testing below
Covers most rail replacement
Clip-up Temperature
Long Rail Works w orks. Consideration for track
Maintain ballast profile Rail Adjustment Control -or-
No disturbance to sleepers or ballast consolidation is not required, as
Stress Testing
ballast is untouched.
Short Rail Works Covers small rail defect
Treat as Hazard
No disturbance to sleepers or ballast, and rail stress affected for Maintain ballast profile Steel In/Out replacement, such as w eld
Location replacement, plug rail installations
<15 metres
Where rail (and therefore rail
Maintain existing stress) remains unaffected, but
Ballast Disturbing Works Track Consolidation ballast has been affected, e.g. by
alignment
tamping.
Designated Mechanised Works
Mechanised ballast cleaning Stress Testing -or- Treat as Hazard
Maintenance resurfacing not considered Minor Track Consolidation
Resurfacing
Rail Adjustment Location
Refer General Track Works if new alignment.
Minor Resurfacing Mostly covers corrective
Resurfacing of defects or small changes w here: resurfacing where rail stress is not
lateral track realignment less than in Table 4-1, or Maintain existing
significantly changed, and w here
lifts of less than 100mm, or
Maintain ballast profile
alignment the track geometry is likely to be
w here both lift and lateral realignment is required, subject
improved.
to the discretion of District Civil Engineer 11
Key process improvements
13
Measuring success
50
45
40
35
30
22
20 18 17
18
10 8
6 5 6
0
FY 14 FY 15 FY 16 FY 17 Target
Track Misalignments/Kinks Buckle
14
Testing the limits
• We developed a baseline
of good CWR practice
• Many efficiencies to be
gained in production
• Key areas investigated:
– Roller usage
– Leg length limits
15
The challenge
• Works programme
dominated by rail
renewal
– Primary cause of rail
stressing
• Rail is wearing most on
tight 300m radius curves
• 300m radius curves
require many rollers, and
many pulls to complete
16
Roller usage reduction - analysis
• Key assumption 4
3
1 in 5
1 in 10
– ΔT = 35°C 2
1
0
0 500 1000 1500 2000 2500 3000
Radius (m) 17
Roller usage reduction - results
• Maintain the same factor of safety
– 5kN maximum working load
• Re-running the calculations for ΔT = 20°C
– Most rail stressing is undertaken at or above
rail temperature of 18°C Curve Vortok Roller spacing Roller spacing
20
Leg length extension – trials
• Trials conducted on
300m radius curves
• Most trials in the 200m
range
• Most ambitious trial was
up to 317m leg length
(up from 120m)
21
Leg length extension - result
• What happened?
23
Black Mountain – what we know
24
Rails get hot, very hot
• Wheels rub against the brakes for 3,000 revolutions and reach
temperatures as high as 160°C
• This heat is transferred through 500 wheels to the rail
• Rail observed to heat up ~7°C under loaded train
row? 01:00
02:00
• 26 minutes not enough time for 03:00
04:00
rail to cool 05:00
+16°C
27
Black Mountain solutions
28
Conclusions/Recommendations
• Got CWR Practice under
control
• Reduced stressing roller
usage rate
• Improved stressing leg
length
• Discovered train brakes
are governing rail
temperature down the hill
29