VIJAYAWADA BYPASS PROJECT

Internal Review Meeting


Date 03.04.2023
Venue ARTL Office, Mandadam

ARTL
Sr. No. Name Department

1 Mr. Ramesh Singooru Head-Projects, ARTL(RMRW)

2 Mr. P. Sreeramamurthy Project Head, VBPPL


3 Mr. Sinivasachary Project Coordinator

3 Mr. E. Srinivasa Rao Highway Head, VBPPL

4 Mr. I S Ramesh Structure Head, VBPPL

5 Mr. E Raja Ramesh QA/QC Head, VBPPL


Sr. Manager-Planning,
6 Mr. Karteeka Kumar G.
VBPPL

Sr. Manager-Safety,
7 Mr. Nachiappan.
VBPPL
Sr. Manager-Contracts,
8 Mr. S V H Kamesh
VBPPL
9 Mr. Padma Rao ARTL, HR Head

S.No. Point of Discussion Responsibility Target Date Discussions 03.04.2023 Remarks

Head-Projects, ARTL, Mr. Ramesh Singooru


1 Info
chaired the meeting
Head-Projects, ARTL has discussed in detailed
about the Audit Reports dated 11.11.2022 and
thereby advised the team to strictly ensure
2 Internal Audit Points VBPPL
implementation of QAP/Safety Plan/SOP's etc and
also to ensure there will be no observations/remidial
actions required in future.

Head-Projects, ARTL has instructed PM, VBPPL to


issue letter to NECL regarding Flyover-01 status,
quantity required for completion, rate of progress
3 Progress of Flyover-01 VBPPL
required/day, augmentation of resources required
for completion and submission of catch-up
program.

Head-Projects, ARTL enquired about the likely


completion of balance structures of the project.
Structures-Head, VBPPL informed that, all the
Target for completion of balance
4 VBPPL structure s will be completed by April'2024. Head-
structures
Projects, ARTL, informed VBPPL tean to ensure
completion of all structures before February'2023,
accordly works need to be monitored.

Head-Projects, ARTL enquired about progress of


Highway works in 3.4 km atgrade portion. Highway-
Head, VBPPL informed that, out of 3.4 km, in 3.3 km
5 Progress of Highway works VBPPL works were taken-up and Embankment works
completed for 2 km. Highway-Head informed that,
there is issue in obtaining Sub-Grade material which
needs to be taken-up with NECL.

Head-Projects, ARTL enquired about progress of RE


Wall locations. Highway-Head, VBPPL informed that,
out of 99000 Sq.m RE wall quantity, as on date
6 Progress of RE Wall works VBPPL
20000 sq.m Re Wall has been completed. Labour
needs to be increased for enhancing current
progress of 50 sq.m/ day to target of 300 sq.m/day.

Head-Projects, ARTL advised project co-ordinator to


prepare list of brought out items such as
bearings/expansion joints etc required for
7 Status of brought out items for structures VBPPL
structures along with detailed procurement
program assuming completion of structures by
28.02.2024.

Meeting Concluded with vote of thanks to all participants

Page 1 of 1