You are on page 1of 64

DAFTAR HARGA SATUAN BAHAN DAN UPAH

SEMESTER I 2015
DINAS PEKERJAAN UMUM KAB MURUNG RAYA

A. BAHAN LOKAL DOMINAN YANG SANGAT DIPENGARUHI BIAYA ANGKUT


HARGA HARGA DASAR HARGA DESAIN =
ONGKOS ANGKUT KE LOKASI
NO. BAHAN KODE SAT SUMBER BAHAN SETEMPAT REGIONAL REGIONAL HARGA DASAR +
REGIONAL I REGIONAL II PEKERJAAN
(RP.) III IV ONGKOS ANGKUT
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)

1 Batu Gunung/batu belah M 010 m3 Puruk Cahu 224,532 280,665 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 623,700 779,625 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 548,856 686,070 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 561,330 701,663 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 449,064 561,330 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

2 Batu Pecah 10 - 15 cm M 026 m3 Puruk Cahu 319,788 399,735 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Manual) Saripoi 755,244 944,055 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 619,164 773,955 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 673,596 841,995 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 694,008 867,510 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 489,888 612,360 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 625,968 782,460 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 571,536 714,420 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 489,888 612,360 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 639,576 799,470 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

3 Batu Pecah 5 - 7 cm M 022 m3 Puruk Cahu 427,518 534,398 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Manual) Saripoi 899,262 1,124,078 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 751,842 939,803 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 810,810 1,013,513 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 840,294 1,050,368 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 619,164 773,955 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 766,584 958,230 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 707,616 884,520 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 619,164 773,955 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 796,068 995,085 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
4 Batu Pecah 3 - 5 cm M 023 m3 Puruk Cahu 592,515 740,644 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 854,469 1,068,086 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 754,677 943,346 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

5 Batu Pecah 2 - 3 cm M 024 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

6 Batu Pecah 1 - 2 cm M 025 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

7 Batu Pecah 0,5 - 1 cm M 026 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
8 Batu Pecah Tersaring M 018 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

9 Debu Batu m3 Puruk Cahu 674,730 843,413 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 912,870 1,141,088 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 822,150 1,027,688 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 958,230 1,197,788 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

10 Kerikil Galian Bukit M 011 m3 Puruk Cahu 187,110 233,888 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Awcas) Saripoi 461,538 576,923 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 424,116 530,145 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 424,116 530,145 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 486,486 608,108 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 424,116 530,145 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 361,746 452,183 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 486,486 608,108 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

11 Kerikil Sungai M 012 m3 Puruk Cahu 228,690 285,863 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 598,752 748,440 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 449,064 561,330 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 598,752 748,440 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 453,600 567,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
12 Kerikil Sungai Ayak M 013 m3 Puruk Cahu 253,260 316,575 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Tanpa Pasir Saripoi 589,680 737,100 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 453,600 567,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 589,680 737,100 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 442,260 552,825 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 442,260 552,825 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 442,260 552,825 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 385,560 481,950 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

13 Pasir Urug / Timbunan M 040 m3 Puruk Cahu 111,132 138,915 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 170,667 213,334 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 178,605 223,256 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 267,908 334,884 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 250,047 312,559 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 309,582 386,978 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 202,419 253,024 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 190,512 238,140 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 190,512 238,140 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 250,047 312,559 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

14 Pasir Ayak Untuk M 041 m3 Puruk Cahu 166,320 207,900 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Beton / Pasir Barito. Saripoi 449,064 561,330 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 349,272 436,590 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 311,850 389,813 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

15 Sirtu (tidak diayak, dari M 042 m3 Puruk Cahu 187,110 233,888 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
sungai) Saripoi 548,856 686,070 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 399,168 498,960 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 548,856 686,070 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
16 Tanah Timbunan M 050 m3 Puruk Cahu 99,225 124,031 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 158,760 198,450 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 166,698 208,373 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 238,140 297,675 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 238,140 297,675 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 297,675 372,094 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 190,512 238,140 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 178,605 223,256 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 178,605 223,256 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 238,140 297,675 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

17 Semen Portland M080 zak Puruk Cahu 124,200 155,250 = [(150.000 + (15.000 x jarak)] / 80 (7) + (11)
(1 zak = 50 kg) Saripoi 142,997 178,747 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Dirung Lingkin 142,997 178,747 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Muara Laung 136,080 170,100 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Makunjung 125,442 156,803 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Tbg Lahung 158,760 198,450 = [(150.000 + (15.000 x jarak)] / 80 (9) + (11)
Tbg Kunyi 201,960 252,450 = [(150.000 + (15.000 x jarak)] / 80 (10) + (11)
Tbg Bantian 190,080 237,600 = [(150.000 + (15.000 x jarak)] / 80 (9) + (11)
Tbg Olong 207,900 259,875 = [(150.000 + (15.000 x jarak)] / 80 (10) + (11)
Muara Joloi 219,780 274,725 = [(150.000 + (15.000 x jarak)] / 80 (10) + (11)

18 Besi Beton Polos (top) M167 Kg Puruk Cahu 13,662 17,078 = [(150.000 + (15.000 x jarak)] / 4.000 (7) + (11)
Saripoi 13,900 17,375 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Dirung Lingkin 13,900 17,375 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Muara Laung 13,900 17,375 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Makunjung 13,662 17,078 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Tbg Lahung 14,137 17,672 = [(150.000 + (15.000 x jarak)] / 4.000 (9) + (11)
Tbg Kunyi 14,494 18,117 = [(150.000 + (15.000 x jarak)] / 4.000 (10) + (11)
Tbg Bantian 14,434 18,043 = [(150.000 + (15.000 x jarak)] / 4.000 (9) + (11)
Tbg Olong 14,672 18,340 = [(150.000 + (15.000 x jarak)] / 4.000 (10) + (11)
Muara Joloi 16,276 20,345 = [(150.000 + (15.000 x jarak)] / 4.000 (10) + (11)

19 Kayu Ulin Balok Besar M 181 m3 Puruk Cahu 5,278,500 6,598,125 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 2,328,750 2,910,938 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 5,278,500 6,598,125 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 6,831,000 8,538,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 5,589,000 6,986,250 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 4,471,200 5,589,000 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 6,210,000 7,762,500 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 6,210,000 7,762,500 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 2,484,000 3,105,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 4,657,500 5,821,875 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
20 Kayu Ulin Balok Kecil M 181 m3 Puruk Cahu 5,643,000 7,053,750 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 4,455,000 5,568,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 5,346,000 6,682,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 6,534,000 8,167,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 5,346,000 6,682,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 5,049,000 6,311,250 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 4,455,000 5,568,750 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

21 Papan Ulin M 181 m3 Puruk Cahu 6,997,320 8,746,650 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 8,167,500 10,209,375 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 8,167,500 10,209,375 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 6,311,250 7,889,063 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 2,970,000 3,712,500 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 5,568,750 6,960,938 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

22 Kayu Lanan Balok Kecil m3 Puruk Cahu 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,782,000 2,227,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 1,782,000 2,227,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 2,524,500 3,155,625 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 2,257,200 2,821,500 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 1,485,000 1,856,250 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

23 Papan Lanan m3 Puruk Cahu 2,577,960 3,222,450 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 2,227,500 2,784,375 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 2,598,750 3,248,438 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 2,524,500 3,155,625 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 2,301,750 2,877,188 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 1,856,250 2,320,313 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 2,227,500 2,784,375 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Keterangan :
Regional I : Kecamatan Murung

Regional II : Kecamatan Tanah Siang Puruk Cahu, Juni 2008


Kecamatan Tanah Siang Selatan
Kecamatan Laung Tuhup KEPALA DINAS PEKERJAAN UMUM
Kecamatan Barito Tuhup Raya KAB. MURUNG RAYA

Regional III : Kecamatan Permata Intan


Kecamatan Sei Babuat

Regional IV : Kecamatan Sumber Barito Ir. ADRIAN WT, MM


Kecamatan Uut Murung NIP. 530 007 565
Kecamatan Seribu Riam
B. BAHAN UMUM
REGIONAL
REGION I REGION II REGION III REGION IV
Kec. Tanah Siang Kec. Sumber Barito
Harga Dasar Kec. Laung Tuhup Kec. Permata Intan Kec. U'ut Murung
No. NAMA BAHAN SAT. KODE Kec. Murung KET.
(Rp.) Kec. Barito Tuhup Raya Kec. Sei Babuat Kec. Seribu Riam
Kec. Tanah Siang Selatan
Total Total Total Total
(Rp.) (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10

1 Alat Bantu Set M.170 89,100.00 111,375.00 115,830.00 120,285.00 124,740.00


2 Ampelas Lbr 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
3 Angker Bh 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
4 Arde Tanah Bh 178,200.00 222,750.00 231,660.00 240,570.00 249,480.00
5 Armatur Lampu Set 403,920.00 504,900.00 525,096.00 545,292.00 565,488.00
6 Aspal Pen 60/70 Kg M.061 12,474.00 15,592.50 16,216.20 16,839.90 17,463.60
7 Astelin Btl 534,600.00 668,250.00 694,980.00 721,710.00 748,440.00
8 Atap Genteng Metal merk Sakura Color (77 x 80 cm) Tipe Classic (2 Susun) Lbr 47,520.00 59,400.00 61,776.00 64,152.00 66,528.00
9 Atap Polycarbonate + Rangka Besi Biasa (Set) M2 594,000.00 742,500.00 772,200.00 801,900.00 831,600.00
10 Atap Polycarbonate + Rangka Steinless (Set) M2 831,600.00 1,039,500.00 1,081,080.00 1,122,660.00 1,164,240.00
11 Atap Sirap Ulin Lbr 1,425.60 1,782.00 1,853.28 1,924.56 1,995.84 Lokal
12 Baja Profil WF Kg M.165 29,106.00 36,382.50 37,837.80 39,293.10 40,748.40
13 Baja Ulir 1" / Profil Kg 20,124.72 25,155.90 26,162.14 27,168.37 28,174.61
14 Bak Mandi Fibreglass (70 cm x 70 cm Segi Empat Besar) Unit 475,200.00 594,000.00 617,760.00 641,520.00 665,280.00
15 Batako Bh 5,464.80 6,831.00 7,104.24 7,377.48 7,650.72 Lokal
16 Batu - Bata Merah (5 x 11 x 22 cm) Bh 1,128.60 1,410.75 1,467.18 1,523.61 1,580.04 Lokal
17 Baut dan Beugel 10 cm Biji 2,376.00 2,970.00 3,088.80 3,207.60 3,326.40
18 Baut dan Beugel 20 cm Biji 9,504.00 11,880.00 12,355.20 12,830.40 13,305.60
19 Besi Plat 5 mm Lbr 1,550,340.00 1,937,925.00 2,015,442.00 2,092,959.00 2,170,476.00
20 Besi Siku 4 cm panajang 6 cm Bh 81,972.00 102,465.00 106,563.60 110,662.20 114,760.80
21 Besi U, 10 x 10 x 6 m Btg 106,920.00 133,650.00 138,996.00 144,342.00 149,688.00
22 Besi Strip Bh 35,877.60 44,847.00 46,640.88 48,434.76 50,228.64
23 Besi Ulir (U - 39) 12 m Kg 16,038.00 20,047.50 20,849.40 21,651.30 22,453.20
24 Box Zekering Kas 2 Group Bh 149,688.00 187,110.00 194,594.40 202,078.80 209,563.20
25 Bubungan Atap Sakura Color 15 cm Lbr 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
26 Cat Dasar Kayu merk Kembang Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
27 Cat Kilap Kayu setara merk Jotun Kg 95,040.00 118,800.00 123,552.00 128,304.00 133,056.00
28 Cat Kilap Kayu setara merk Glotex Kg 45,144.00 56,430.00 58,687.20 60,944.40 63,201.60
29 Cat Kilap Kayu setara merk Platone Kg 45,144.00 56,430.00 58,687.20 60,944.40 63,201.60
30 Cat Kilap Kayu setara setara Avia Paint Kg 46,332.00 57,915.00 60,231.60 62,548.20 64,864.80
31 Cat Menie Kg 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
32 Cat Tembok merk setara Kimex Kg 16,632.00 20,790.00 21,621.60 22,453.20 23,284.80
33 Cat Tembok setara merk Matek Kg 16,632.00 20,790.00 21,621.60 22,453.20 23,284.80
34 Closed Duduk setaramerk American Standard Set 2,316,600.00 2,895,750.00 3,011,580.00 3,127,410.00 3,243,240.00
35 Closed Jongkok setara merk American Standard Bh 237,600.00 297,000.00 308,880.00 320,760.00 332,640.00
36 Elbow 2" PVC (AW) 90˚ Bh 10,692.00 13,365.00 13,899.60 14,434.20 14,968.80
37 Elbow 4" PVC (AW) 90˚ Bh 59,400.00 74,250.00 77,220.00 80,190.00 83,160.00
38 Engsel Lokal 3" setara merk Picaso Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
39 Engsel Lokal 4" setara merk Picaso Bh 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
40 Engsel Lokal 4" setara merk Iron Bh 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
41 Espanyolet Tanam setara merk SES Bh 149,688.00 187,110.00 194,594.40 202,078.80 209,563.20
42 Fiting Lampu Gantung Biasa Bh 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
43 Fiting Lampu Gantung Tipe E 40 Bh 89,100.00 111,375.00 115,830.00 120,285.00 124,740.00
44 Fiting Lampu Gipsum Bh 101,574.00 126,967.50 132,046.20 137,124.90 142,203.60
45 Flange Adaptor Ø 2" merk Maspion Bh 104,544.00 130,680.00 135,907.20 141,134.40 146,361.60
46 Flange Adaptor Ø 3" merk Maspion Bh 142,560.00 178,200.00 185,328.00 192,456.00 199,584.00
47 Flange Adaptor Ø 4" merk Maspion Bh 181,170.00 226,462.50 235,521.00 244,579.50 253,638.00
48 Flange Adaptor Ø 6" merk Maspion Bh 356,518.80 445,648.50 463,474.44 481,300.38 499,126.32
49 Flange Adaptor Ø 2" merk Vinilon Bh 153,608.40 192,010.50 199,690.92 207,371.34 215,051.76
50 Flange Adaptor Ø 3" merk Vinilon Bh 211,464.00 264,330.00 274,903.20 285,476.40 296,049.60
51 Flange Adaptor Ø 4" merk Vinilon Bh 278,942.40 348,678.00 362,625.12 376,572.24 390,519.36
52 Flange Adaptor Ø 6" merk Vinilon Bh 514,522.80 643,153.50 668,879.64 694,605.78 720,331.92
53 Flange Adaptor Ø 8" merk Vinilon Bh 829,105.20 1,036,381.50 1,077,836.76 1,119,292.02 1,160,747.28
54 Flange Adaptor Ø 10" merk Vinilon Bh 850,370.40 1,062,963.00 1,105,481.52 1,148,000.04 1,190,518.56
55 Flange Adaptor Ø 12" merk Vinilon Bh 1,294,563.60 1,618,204.50 1,682,932.68 1,747,660.86 1,812,389.04
56 Floor Strainer Bh 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
57 Kunci Gembok + Plat (Besar) Set 53,460.00 66,825.00 69,498.00 72,171.00 74,844.00
58 Glassbeads Kg 38,016.00 47,520.00 49,420.80 51,321.60 53,222.40
59 Glassblock Bh 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
60 Grendel 2" setara merk Omco Bh 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
61 Grendel 3" setara merk Omco Bh 9,504.00 11,880.00 12,355.20 12,830.40 13,305.60
62 Handle Listrik 30 Ampere Bh 59,400.00 74,250.00 77,220.00 80,190.00 83,160.00
63 Handle / Tarikan Kuning setara merk Top Bh 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
64 Isolasi Listrik Buah 7,128.00 8,910.00 9,266.40 9,622.80 9,979.20
65 Kabel NYA 2,5" M' 1,663.20 2,079.00 2,162.16 2,245.32 2,328.48
66 Kabel Power tipe NYM 3 x 2,5 mm setara merk Spring M' 6,534.00 8,167.50 8,494.20 8,820.90 9,147.60
67 Kabel Tanam 2 x 2,5" setara merk Spring M' 4,752.00 5,940.00 6,177.60 6,415.20 6,652.80
68 Kabel tipe NYFGBY 4 x 10 mm M' 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
69 Kaca Bening ≠ 3 mm M2 118,800.00 148,500.00 154,440.00 160,380.00 166,320.00
70 Kaca Bening ≠ 5 mm M2 130,680.00 163,350.00 169,884.00 176,418.00 182,952.00
71 Kaca Hitam / Ryben ≠ 5 mm M2 148,500.00 185,625.00 193,050.00 200,475.00 207,900.00
72 Kait Angin Kuning Pasang 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
73 Kait Talang Air merk Maspion Bh 9,504.00 11,880.00 12,355.20 12,830.40 13,305.60
74 Kapur Pasang / Kapur Padam Kg M.081 1,960.20 2,450.25 2,548.26 2,646.27 2,744.28
75 Kawat Berduri M' 7,128.00 8,910.00 9,266.40 9,622.80 9,979.20
76 Kawat Beton (Bindrat) Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
77 Kawat Bronjong Kg M.162 41,164.20 51,455.25 53,513.46 55,571.67 57,629.88
78 Kawat Harmonika M2 15,444.00 19,305.00 20,077.20 20,849.40 21,621.60
79 Kawat Las Dos 160,380.00 200,475.00 208,494.00 216,513.00 224,532.00
80 Kawat Nyamuk (Besi) M2 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
81 Kayu Bakar M3 M.070 118,800.00 148,500.00 154,440.00 160,380.00 166,320.00 Lokal
82 Kayu Bekisting M3 M.180 772,200.00 965,250.00 1,003,860.00 1,042,470.00 1,081,080.00 Lokal
83 Kayu Bulat Ø 6 - 10 cm panjang 4 m Btg 9,355.50 11,694.38 12,162.15 12,629.93 13,097.70 Lokal
84 Kayu Log Ø 50 - 70 cm panjang 4 m Btg 810,810.00 1,013,512.50 1,054,053.00 1,094,593.50 1,135,134.00 Lokal
85 Keramik 20 x 20 cm merk Roman Bh 3,088.80 3,861.00 4,015.44 4,169.88 4,324.32
86 Keramik 20 x 20 cm merk Mulia Bh 3,088.80 3,861.00 4,015.44 4,169.88 4,324.32
87 Keramik 20 x 25 cm merk Mulia Bh 3,861.00 4,826.25 5,019.30 5,212.35 5,405.40
88 Keramik 30 x 30 cm merk Roman Bh 8,672.40 10,840.50 11,274.12 11,707.74 12,141.36
89 Keramik 40 x 40 cm merk Roman Bh 17,938.80 22,423.50 23,320.44 24,217.38 25,114.32
90 Keramik 30 x 30 cm Putih merk Mulia Bh 7,484.40 9,355.50 9,729.72 10,103.94 10,478.16
91 Klam Pipa Listrik Bungkus 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
92 Knee PVC Ø 2" merk Maspion (DV) Bh 7,722.00 9,652.50 10,038.60 10,424.70 10,810.80
93 Knee PVC Ø 3" merk Maspion (DV) Bh 23,878.80 29,848.50 31,042.44 32,236.38 33,430.32
94 Knee PVC Ø 4" merk Maspion (DV) Bh 45,738.00 57,172.50 59,459.40 61,746.30 64,033.20
95 Knee PVC Ø 6" merk Maspion (DV) Bh 196,020.00 245,025.00 254,826.00 264,627.00 274,428.00
96 Knee PVC Ø 8" merk Maspion (DV) Bh 281,556.00 351,945.00 366,022.80 380,100.60 394,178.40
97 Knee PVC Ø 10" merk Maspion (DV) Bh 403,920.00 504,900.00 525,096.00 545,292.00 565,488.00
98 Knee PVC Ø 12" merk Maspion (DV) Bh 659,340.00 824,175.00 857,142.00 890,109.00 923,076.00
99 Knee PVC Ø 2" merk Vinilon Bh 27,918.00 34,897.50 36,293.40 37,689.30 39,085.20
100 Knee PVC RRJ Ø 3" merk Vinilon Bh 445,500.00 556,875.00 579,150.00 601,425.00 623,700.00
102 Kran Air Ø 1/2" setara merk Amico Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
103 Kran Air Ø 3/4" setara merk Amico Bh 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
104 Kunci Tanam setara merk Kodai Bh 148,500.00 185,625.00 193,050.00 200,475.00 207,900.00
105 Kunci Tanam setara merk SES Bh 415,800.00 519,750.00 540,540.00 561,330.00 582,120.00
106 Lem Isarplast (700 gr) Kg 154,440.00 193,050.00 200,772.00 208,494.00 216,216.00
107 Lem Kayu merk Fox Kg 41,580.00 51,975.00 54,054.00 56,133.00 58,212.00
108 List Profil Kayu 4 Cm M' 3,861.00 4,826.25 5,019.30 5,212.35 5,405.40 Lokal
109 List Profil Gipsum M' 53,460.00 66,825.00 69,498.00 72,171.00 74,844.00
110 MCB merk Elitech Buah 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
111 Minyak Bakar / Minyak Tanah Ltr M.065 10,692.00 13,365.00 13,899.60 14,434.20 14,968.80
112 Minyak Cat / Thinner A Ltr 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
113 Minyak Cat / Thinner B Ltr 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
114 Minyak Cat Biasa (600 ml) Btl 6,534.00 8,167.50 8,494.20 8,820.90 9,147.60
115 Minyak Cat merk Super Ltr 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
116 Minyak Pelumas (SAE 30) Ltr M.185 35,046.00 43,807.50 45,559.80 47,312.10 49,064.40
117 Moulding Lanan (Lebar 10 Cm) Keping 19,008.00 23,760.00 24,710.40 25,660.80 26,611.20 Lokal
118 Moulding Lanan M3 2,356,992.00 2,946,240.00 3,064,089.60 3,181,939.20 3,299,788.80 Lokal
119 Paking Pipa Karet (3 mm) Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
120 Paku Atap Genteng Metal Kg 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
121 Paku Jembatan Kg M.166 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
122 Paku Kayu (≤ 1") Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
123 Paku Kayu ( 1 1/4" - 1,5") Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
124 Paku Kayu (2") Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
125 Paku Kayu (2,5" - 5") Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
126 Paku Plywood Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
127 Paku Seng Kg 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
128 Paku Sirap Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
129 Paku Ulin (2,5" - 5") Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
130 Paku Ulin (≤ 2") Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
131 Papan Bekisting M3 1,620,432.00 2,025,540.00 2,106,561.60 2,187,583.20 2,268,604.80 Lokal
132 Papan Kayu Bouwplank M3 1,915,056.00 2,393,820.00 2,489,572.80 2,585,325.60 2,681,078.40 Lokal
133 Lampu TL 20 watt merk Phillips Lengkap Set 100,980.00 126,225.00 131,274.00 136,323.00 141,372.00
134 Lampu SL 18 watt merk Philips Bh 41,580.00 51,975.00 54,054.00 56,133.00 58,212.00
135 Lampu Pijar 25 watt merk Philips Bh 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
136 Pasangan Instalasi Listrik (Rumah Beton) Bh 95,040.00 118,800.00 123,552.00 128,304.00 133,056.00
137 Pasangan Instalasi Listrik (Rumah Kayu) Bh 71,280.00 89,100.00 92,664.00 96,228.00 99,792.00
138 Tangki Air 1.200 ltr setara merk Grand Bh 1,603,800.00 2,004,750.00 2,084,940.00 2,165,130.00 2,245,320.00
139 Tangki Air 2.200 ltr setara merk Grand Bh 3,267,000.00 4,083,750.00 4,247,100.00 4,410,450.00 4,573,800.00
140 Paving Block Bh 3,920.40 4,900.50 5,096.52 5,292.54 5,488.56 Lokal
141 Pipa Galvanis Ø 2" panjang 4 m Btg 363,528.00 454,410.00 472,586.40 490,762.80 508,939.20
142 Pipa Galvanis Ø 3" panjang 6 m Btg 557,172.00 696,465.00 724,323.60 752,182.20 780,040.80
143 Pipa Galvanis Ø 4" panjang 6 m Btg 1,016,928.00 1,271,160.00 1,322,006.40 1,372,852.80 1,423,699.20
144 Pipa Galvanis Ø 6" panjang 6 m Btg 1,647,162.00 2,058,952.50 2,141,310.60 2,223,668.70 2,306,026.80
145 Pipa Paralon PVC Ø 1/2" AW, panjang 4 m merk Super Intilon Btg 18,414.00 23,017.50 23,938.20 24,858.90 25,779.60
146 Pipa Paralon PVC Ø 3/4" AW, panjang 4 m merk Super Intilon Btg 24,948.00 31,185.00 32,432.40 33,679.80 34,927.20
147 Pipa Paralon PVC Ø 1" AW, panjang 4 m merk Super Intilon Btg 31,482.00 39,352.50 40,926.60 42,500.70 44,074.80
148 Pipa Paralon PVC Ø 1,5" AW, panjang 4 m merk Super Intilon Btg 54,648.00 68,310.00 71,042.40 73,774.80 76,507.20
149 Pipa Paralon PVC Ø 2" AW, panjang 4 m merk Super Intilon Btg 59,400.00 74,250.00 77,220.00 80,190.00 83,160.00
150 Pipa Paralon PVC Ø 3" AW, panjang 4 m merk Super Intilon Btg 142,560.00 178,200.00 185,328.00 192,456.00 199,584.00
151 Pipa Paralon PVC Ø 4" AW, panjang 4 m merk Super Intilon Btg 190,080.00 237,600.00 247,104.00 256,608.00 266,112.00
152 Pipa Paralon PVC Ø 2", panjang 6 m merk Maspion Btg 122,958.00 153,697.50 159,845.40 165,993.30 172,141.20
153 Pipa Paralon PVC Ø 3", panjang 6 m merk Maspion Btg 239,668.31 299,585.39 311,568.80 323,552.22 335,535.63
154 Pipa Paralon PVC Ø 4", panjang 6 m merk Maspion Btg 348,410.70 435,513.38 452,933.91 470,354.45 487,774.98
155 Pipa Paralon PVC Ø 6", panjang 6 m merk Maspion Btg 721,116.00 901,395.00 937,450.80 973,506.60 1,009,562.40
156 Pipa Paralon PVC Ø 8", panjang 6 m merk Maspion Btg 1,095,930.00 1,369,912.50 1,424,709.00 1,479,505.50 1,534,302.00
157 Pipa Paralon PVC Ø 10", panjang 6 m merk Maspion Btg 1,703,295.00 2,129,118.75 2,214,283.50 2,299,448.25 2,384,613.00
158 Pipa Paralon PVC Ø 12", panjang 6 m merk Maspion Btg 2,806,650.00 3,508,312.50 3,648,645.00 3,788,977.50 3,929,310.00
159 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø1/2", panjang 4 m merk Vinilon Btg 12,952.76 16,190.96 16,838.59 17,486.23 18,133.87
160 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø 3/4", panjang 4 m merk Vinilon Btg 19,111.36 23,889.20 24,844.76 25,800.33 26,755.90
161 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø 1", panjang 4 m merk Vinilon Btg 32,658.12 40,822.65 42,455.56 44,088.46 45,721.37
162 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø 1,5", panjang 4 m merk Vinilon Btg 94,029.01 117,536.27 122,237.72 126,939.17 131,640.62
163 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 2", panjang 6 m merk Vinilon Btg 182,045.56 227,556.95 236,659.22 245,761.50 254,863.78
164 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 3", panjang 6 m merk Vinilon Btg 310,473.11 388,091.39 403,615.04 419,138.70 434,662.35
165 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 4", panjang 6 m merk Vinilon Btg 451,529.10 564,411.38 586,987.83 609,564.29 632,140.74
166 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 6", panjang 6 m merk Vinilon Btg 981,050.40 1,226,313.00 1,275,365.52 1,324,418.04 1,373,470.56
167 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 8", panjang 6 m merk Vinilon Btg 1,484,168.40 1,855,210.50 1,929,418.92 2,003,627.34 2,077,835.76
168 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 10", panjang 6 m merk Vinilon Btg 2,266,407.00 2,833,008.75 2,946,329.10 3,059,649.45 3,172,969.80
169 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 12", panjang 6 m merk Vinilon Btg 3,805,282.80 4,756,603.50 4,946,867.64 5,137,131.78 5,327,395.92
170 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 14", panjang 6 m merk Vinilon Btg 5,826,189.60 7,282,737.00 7,574,046.48 7,865,355.96 8,156,665.44
171 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 16", panjang 6 m merk Vinilon Btg 7,103,170.80 8,878,963.50 9,234,122.04 9,589,280.58 9,944,439.12
172 Plafond Gipsum (1,20 m x 2,40 m) Lbr 98,010.00 122,512.50 127,413.00 132,313.50 137,214.00
173 Plafond Kalsiboard (1,20 m x 2,40 m) Lbr 80,190.00 100,237.50 104,247.00 108,256.50 112,266.00
174 Plamur Tembok setara merk Boyo Kg 10,692.00 13,365.00 13,899.60 14,434.20 14,968.80
175 Plastik Cor M3 65,340.00 81,675.00 84,942.00 88,209.00 91,476.00
176 Plywood / Triplek (3 mm) Lbr 53,460.00 66,825.00 69,498.00 72,171.00 74,844.00
177 Pompa Air Jet Pump setara merk Panasonic 125 w Unit 415,800.00 519,750.00 540,540.00 561,330.00 582,120.00
178 Pompa Air Jet Pump setara merk Panasonic 200 w Unit 653,400.00 816,750.00 849,420.00 882,090.00 914,760.00
179 Premium (Bensin) Ltr M.184 9,682.20 12,102.75 12,586.86 13,070.97 13,555.08
180 Rangka Plafond Gipsum M2 130,977.00 163,721.25 170,270.10 176,818.95 183,367.80
181 Reducer Socket RR 4" x 3" merk Maspion (DV) Bh 10,098.00 12,622.50 13,127.40 13,632.30 14,137.20
182 Reducer Socket RR 6" x 4" merk Maspion (DV) Bh 38,610.00 48,262.50 50,193.00 52,123.50 54,054.00
183 Reducer Socket RR 3" x 2" Merk Vinilon Bh 297,000.00 371,250.00 386,100.00 400,950.00 415,800.00
184 Reducer Socket RR 4" x 3" merk Vinilon Bh 297,000.00 371,250.00 386,100.00 400,950.00 415,800.00
185 Reducer Socket RR 6" x 4" merk Vinilon Bh 831,600.00 1,039,500.00 1,081,080.00 1,122,660.00 1,164,240.00
186 Reducer Socket RR 4" x 2" merk Vinilon Bh 475,200.00 594,000.00 617,760.00 641,520.00 665,280.00
186 Saklar Ganda setara merk Broco Bh 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
187 Reducer Socket RR 8" x 6" merk Vinilon Bh 1,069,200.00 1,336,500.00 1,389,960.00 1,443,420.00 1,496,880.00
187 Saklar Tunggal setara merk Broco Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
188 Stop Kontak setara merk Broco Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
189 Selang Fleksibel (Karet) Ø 4" M' 891,000.00 1,113,750.00 1,158,300.00 1,202,850.00 1,247,400.00
190 Selotif Pipa merk Onda Buah 3,564.00 4,455.00 4,633.20 4,811.40 4,989.60
191 Semen Putih 50 kg Kg 2,970.00 3,712.50 3,861.00 4,009.50 4,158.00
192 Seng Bubungan Plat BJLS 30, Lebar 40 cm M' 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
193 Seng Bubungan Plat BJLS 30, Lebar 30 cm M' 14,256.00 17,820.00 18,532.80 19,245.60 19,958.40
194 Seng Gelombang Kecil BJLS 30 Lbr 42,768.00 53,460.00 55,598.40 57,736.80 59,875.20
195 Seng Plat Besar Biasa BJLS 30 Lbr 59,400.00 74,250.00 77,220.00 80,190.00 83,160.00
196 Solar Ltr M.183 10,632.60 13,290.75 13,822.38 14,354.01 14,885.64
197 Stop Kran Ø 2" PVC Bh 89,100.00 111,375.00 115,830.00 120,285.00 124,740.00
198 Stop Kran Ø 1/2" PVC Bh 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
199 Stop Kran Ø 3/4" PVC Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
200 Spring Knife setara merk Subur Bh 8,316.00 10,395.00 10,810.80 11,226.60 11,642.40
201 Talang Air PVC merk Maspion @ 4 m M' 26,730.00 33,412.50 34,749.00 36,085.50 37,422.00
202 Talang Air PVC merk Champion @ 4 m M' 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
203 Tee All RR Ø 2" merk Maspion Bh 108,108.00 135,135.00 140,540.40 145,945.80 151,351.20
204 Tee All RR Ø 3" merk Maspion Bh 178,200.00 222,750.00 231,660.00 240,570.00 249,480.00
205 Tee All RR Ø 4" merk Maspion Bh 294,030.00 367,537.50 382,239.00 396,940.50 411,642.00
206 Tee All RR Ø 6" merk Maspion Bh 545,292.00 681,615.00 708,879.60 736,144.20 763,408.80
207 Tee All RR Ø 2" merk Vinilon Bh 150,876.00 188,595.00 196,138.80 203,682.60 211,226.40
208 Tee All RR Ø 3" merk Vinilon Bh 205,048.80 256,311.00 266,563.44 276,815.88 287,068.32
209 Tee All RR Ø 4" merk Vinilon Bh 359,251.20 449,064.00 467,026.56 484,989.12 502,951.68
210 Tee All RR Ø 6" merk Vinilon Bh 956,458.80 1,195,573.50 1,243,396.44 1,291,219.38 1,339,042.32
211 Tee All RR Ø 8" merk Vinilon Bh 1,972,555.20 2,465,694.00 2,564,321.76 2,662,949.52 2,761,577.28
212 Tee All RR Ø 10" merk Vinilon Bh 2,688,800.40 3,361,000.50 3,495,440.52 3,629,880.54 3,764,320.56
213 Teer / Residu Ltr 8,316.00 10,395.00 10,810.80 11,226.60 11,642.40
214 Teralis Besi M2 415,800.00 519,750.00 540,540.00 561,330.00 582,120.00
215 Terminal Kabel dan MCB 6 A Bh 77,220.00 96,525.00 100,386.00 104,247.00 108,108.00
216 Thermoplastic Kg 35,640.00 44,550.00 46,332.00 48,114.00 49,896.00
217 Knee PVC RRJ Ø 4" merk Vinilon Bh 534,600.00 668,250.00 694,980.00 721,710.00 748,440.00
218 Knee PVC RRJ Ø 6" merk Vinilon Bh 772,200.00 965,250.00 1,003,860.00 1,042,470.00 1,081,080.00
219 Knee PVC RRJ Ø 8" merk Vinilon Bh 891,000.00 1,113,750.00 1,158,300.00 1,202,850.00 1,247,400.00
220 Get Valve RR Ø 8" Bh 7,128,000.00 8,910,000.00 9,266,400.00 9,622,800.00 9,979,200.00
221 Get Valve RR Ø 6" Bh 4,158,000.00 5,197,500.00 5,405,400.00 5,613,300.00 5,821,200.00
222 Get Valve RR Ø 4" Bh 3,088,800.00 3,861,000.00 4,015,440.00 4,169,880.00 4,324,320.00
223 Bend RR Ø 8" Bh 1,039,500.00 1,299,375.00 1,351,350.00 1,403,325.00 1,455,300.00
224 Bend RR Ø 6" Bh 772,200.00 965,250.00 1,003,860.00 1,042,470.00 1,081,080.00
225 Bend RR Ø 4" Bh 653,400.00 816,750.00 849,420.00 882,090.00 914,760.00
226 Bend RR Ø 3" Bh 415,800.00 519,750.00 540,540.00 561,330.00 582,120.00

Catatan :
- Harga Setempat sudah termasuk Pungutan Resmi Lainnya (sesuai daerah ybs).
- Harga Total sudah termasuk Pajak PPn dan Keuntungan Pelaksana.
- Untuk Lokasi yang sulit ditempuh lewat jalan darat dan jauh dari pinggir sungai perlu ditambah dengan
Ongkos Angkut sesuai jauh lokasi atau jarak tempuh angkutan (darat/sungai).
- Harga Bahan Pabrikasi dihitung Harga Pabrik + Ongkos Kirim + Pajak PPN dan Keuntungan Pelaksana.
C. UPAH
REGIONAL
REGION I REGION II REGION III REGION IV
Kec. Tanah Siang Kec. Sumber Barito
Harga Dasar Kec. Barito Tuhup Raya Kec. Sei Babuat Kec. U'ut Murung
No. JENIS KEAHLIAN SAT. KODE Kec. Murung KET.
(Rp.) Kec. Laung Tuhup Kec. Permata Intan Kec. Seribu Riam
Kec. Tanah Siang Selatan
Total Total Total Total
(Rp.) (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10

1 Mandor /Hari L.061 115,500.00 144,375.00 150,150.00 155,925.00 161,700.00


2 Mekanik /Hari L.071 111,100.00 138,875.00 144,430.00 149,985.00 155,540.00
3 Kepala Tukang (Batu, Besi, Kayu, Cat, Gali ) /Hari L.073 112,750.00 140,937.50 146,575.00 152,212.50 157,850.00
4 Tukang (Batu, Besi, Kayu, Cat, Gali ) /Hari L.079 107,625.00 134,531.25 139,912.50 145,293.75 150,675.00
5 Pekerja / Buruh Semi Terlatih /Hari L.103 105,575.00 131,968.75 137,247.50 142,526.25 147,805.00
6 Operator Terlatih /Hari L.081 300,000.00 375,000.00 390,000.00 405,000.00 420,000.00
7 Operator Kurang Terlatih / Pembantu Operator /Hari L.082 120,000.00 150,000.00 156,000.00 162,000.00 168,000.00
8 Sopir Terlatih /Hari L.091 150,000.00 187,500.00 195,000.00 202,500.00 210,000.00
9 Pembantu Sopir /Hari L.099 107,625.00 134,531.25 139,912.50 145,293.75 150,675.00

Keterangan :
Regional I : Kecamatan Murung

Regional II : Kecamatan Tanah Siang


Kecamatan Tanah Siang Selatan
Kecamatan Laung Tuhup
Kecamatan Barito Tuhup Raya

Regional III : Kecamatan Permata Intan


Kecamatan Sei Babuat

Regional IV : Kecamatan Sumber Barito


Kecamatan U'ut Murung
Kecamatan Seribu Riam
RENCANA ANGGARAN BIAYA
(RAB)

NILAI FISIK:
Rp 561,000,000.00

### LIMA RATUS ENAM PULUH SATU JUTA RUPIAH ###

PROGRAM :
Program Pembangunan Prasarana Sanitasi

KEGIATAN :
Pembuatan Prasarana Sanitasi (DAK)

PEKERJAAN :
Pembangunan Baru Tangki Septik Skala Komunal Desa Karalai 8 Unit (DAK)

LOKASI :
Kecamatan Tanah Siang

TAHUN :
2018
RENCANA ANGGARAN BIAYA (RAB)
Program : Program Pembangunan Prasarana Sanitasi
Kegiatan : Pembuatan Prasarana Sanitasi (DAK)
Pekerjaan : Pembangunan Baru Tangki Septik Skala Komunal Desa Karalai 8 Unit (DAK)
Lokasi : Kecamatan Tanah Siang
Tahun : 2018

Harga satuan Total Harga


No Uraian Pekerjaan Analisa Volume
(Rp.) (Rp.)
1 2 3 4 5 6

I PEKERJAAN PENDAHULUAN
1 Pekerjaan Pengukuran dan Pembersihan Lokasi - 8.00 Keg 522,500.00 4,180,000.00
2 Biaya Operasional KSM - 1.00 Unit 2,000,000.00 2,000,000.00
3 Pemasangan Bowplank - 8.00 Unit 525,000.00 4,200,000.00
4 Pembuatan Papan Nama Kegiatan - 1.00 Bh 400,000.00 400,000.00
Jumlah I 10,780,000.00

II PEKERJAAN TANAH DAN URUGAN


1 Galian Tanah Septictank A.2.3.1.2. 118.56 M3 104,223.60 12,356,750.02
2 Galian Tanah Pipa, Bak Kontrol dan Manhole A.2.3.1.1. 104.46 M3 85,351.50 8,915,646.99
3 Urugan Tanah Kembali A.2.3.1.9. 67.29 M3 60,905.00 4,098,384.46
4 Urugan Pasir A.2.3.1.11. 12.97 M3 239,340.60 3,103,589.40
Jumlah II 28,474,370.86

III PEKERJAAN BETON, DAN PASANGAN


1 Pek . Beton (f'c = 14,5 Mpa)
a. Beton Sloof,Penyangga Media Bakteri, Kolom, Ring Balok dan Dinding Septictank (f'c = 14,5 Mpa) A.A.4.1.1.5. 20.42 M3 1,346,700.69 27,504,476.21
b. Beton Lantai Septictank T. 10 cm (f'c = 14,5 Mpa) A.A.4.1.1.5. 3.58 M3 1,346,700.69 4,826,575.27
c. Beton Dak Tutup Septictank T. 10 cm (f'c = 14,5 Mpa) A.A.4.1.1.5. 3.58 M3 1,346,700.69 4,826,575.27
d. Beton Bak Kontrol T. 10 cm (f'c = 14,5 Mpa) A.A.4.1.1.5. 2.74 M3 1,346,700.69 3,684,573.09
e. Beton Lantai T. 10 cm dan Plat Tutup Bak Kontrol T. 5 cm (f'c = 14,5 Mpa) A.A.4.1.1.5. 1.08 M3 1,346,700.69 1,458,476.85
f. Beton Manhole T. 10 cm (f'c = 14,5 Mpa) A.A.4.1.1.5. 4.21 M3 1,346,700.69 5,672,303.31
g. Beton Lantai T. 10 cm dan Plat Tutup Manhole T. 5 cm (f'c = 14,5 Mpa) A.A.4.1.1.5. 1.63 M3 1,346,700.69 2,199,835.58
h. Beton Manhole Resapan T. 10 cm (f'c = 14,5 Mpa) A.A.4.1.1.5. 1.92 M3 1,346,700.69 2,585,665.32
i. Beton Plat Tutup Manhole Resapan T. 5 cm (f'c = 14,5 Mpa) A.A.4.1.1.5. 0.20 M3 1,346,700.69 263,953.34
2 Pek. Pembesian
a. Pembesian Sloof Septictank Ø 10 dan 8 mm Jarak 15 Cm A.4.1.1.17. 438.05 Kg 16,772.23 7,347,093.73
b. Pembesian Lantai Septictank Ø 10 mm Jarak 15 Cm A.4.1.1.17. 302.08 Kg 16,772.23 5,066,607.70
c. Pembesian Kolom Septictank Ø 10 mm Jarak 15 Cm A.4.1.1.17. 470.35 Kg 16,772.23 7,888,737.33
d. Pembesian Dinding Septictank Ø 10 mm Jarak 15 Cm A.4.1.1.17. 1,857.91 Kg 16,772.23 31,161,293.12
e. Pembesian Ring Balok Septictank Ø 10 dan 8 mm Jarak 15 Cm A.4.1.1.17. 382.66 Kg 16,772.23 6,418,019.75
f. Pembesian Penutup Septictank Ø 10 mm Jarak 15 Cm A.4.1.1.17. 361.32 Kg 16,772.23 6,060,060.19
g. Pembesian Bak Kontrol Ø 10 mm Jarak 15 Cm A.4.1.1.17. 239.15 Kg 16,772.23 4,011,064.43
h. Pembesian Lantai dan Penutup Bak Kontrol Ø 10 mm Jarak 15 Cm A.4.1.1.17. 84.41 Kg 16,772.23 1,415,669.80
i. Pembesian Manhole Ø 10 mm Jarak 15 Cm A.4.1.1.17. 383.16 Kg 16,772.23 6,426,395.80
j. Pembesian Lantai dan Penutup Manhole Ø 10 mm Jarak 15 Cm A.4.1.1.17. 108.28 Kg 16,772.23 1,816,155.33
k. Pembesian Manhole Resapan Ø 10 mm Jarak 15 Cm A.4.1.1.17. 176.71 Kg 16,772.23 2,963,799.93
l. Pembesian Penutup Manhole Resapan Ø 10 mm Jarak 15 Cm A.4.1.1.17. 32.08 Kg 16,772.23 538,120.10
3 Pek. Bekisting
a. Bekisting Bawah Sloof Septictank A.4.1.1.21.a 9.04 M2 131,732.64 1,190,863.07
b. Bekisting Kolom, Dinding dan Ring Balok Septictank A.4.1.1.25.a. 378.91 M2 221,698.88 84,004,366.02
c. Bekisting Penutup Septictank A.4.1.1.24.a. 35.84 M2 233,803.44 8,379,515.29
d. Bekisting Bak Kontrol A.4.1.1.25.b. 54.72 M2 192,058.88 10,509,461.91
e. Bekisting Bak Manhole A.4.1.1.25.b. 84.24 M2 192,058.88 16,179,040.05
f. Bekisting Bak Manhole Resapan A.4.1.1.25.b. 38.40 M2 192,058.88 7,375,060.99
4 Pek. Plesteran A.4.4.2.4. 279.42 M2 75,777.60 21,174,080.10
5 Pek. Acian A.4.4.2.27. 360.52 M2 41,051.40 14,799,686.52
6 Pek. Pas. Ulin 5/7 Cm Penyangga Media Bakteri Ls 0.72 M3 6,500,000.00 4,659,200.00
7 Plastik Cor - 62.17 M2 6,240.00 387,940.80
8 Pek. Pas. Pipa PVC Ø 4" AW A.5.1.1.32.a 1,104.00 M' 181,125.18 199,962,196.51
9 Pemasangan / Pegadaan Media Bakteri Botol Plastik (Tersusun Sarang Tawon ) - 8.00 Unit 1,500,000.00 12,000,000.00
10 Pek. Pas. Aksesoris Pipa
a. Elbow PVC Ø 4" - 32.00 Bh 94,750.00 3,032,000.00
b. Tee PVC Ø 4" - 24.00 Bh 165,000.00 3,960,000.00
Jumlah III 521,748,862.71

REKAPITULASI RENCANA ANGGARAN BIAYA

No URAIAN PEKERJAAN JUMLAH


I PEKERJAAN PENDAHULUAN 10,780,000.00
II PEKERJAAN TANAH DAN URUGAN 28,474,370.86
III PEKERJAAN BETON, DAN PASANGAN 521,748,862.71
JUMLAH TOTAL I + II + III 561,003,233.57
DIBULATKAN 561,000,000.00

Terbilang : ### LIMA RATUS ENAM PULUH SATU JUTA RUPIAH ###
PERHITUNGAN VOLUME
Program : Program Pembangunan Prasarana Sanitasi
Kegiatan : Pembuatan Prasarana Sanitasi (DAK)
Pekerjaan : Pembangunan Baru Tangki Septik Skala Komunal Desa Karalai 8 Unit (DAK)
Lokasi : Kecamatan Tanah Siang
Tahun : 2018

No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4
I PEKERJAAN PENDAHULUAN
1 Pekerjaan Pengukuran dan Pembersihan Lokasi
= 1.00 x 8.00 = 8.000
2 Biaya Operasional KSM
= 1.00 x 1.00 = 1.000
3 Pemasangan Bowplank
= 1.00 x 8.00 = 8.000
4 Pembuatan Papan Nama Kegiatan
= 1.00 = 1.00
II PEKERJAAN TANAH DAN URUGAN
1 Galian Tanah Septictank
Galian Septictank = 3.00 x 1.90 x 2.60 x 8.00 = 118.56
118.56 Jumlah = 118.560
2 Galian Tanah Pipa, Bak Kontrol dan Manhole
Galian Pipa (80% Panjang Pipa) = 819.20 x 0.20 x 0.50 = 81.92
Galian Bak Kontrol = 0.50 x 0.55 x 0.60 x 38.00 = 6.27
Galian Manhole = 0.70 x 0.80 x 0.75 x 27.00 = 11.34
Galian Manhole Resapan = 0.70 x 0.80 x 1.10 x 8.00 = 4.93
104.46 Jumlah = 104.458
3 Urugan Tanah Kembali
Urugan Galian Pipa = 81.92 - 8.19 - 6.44 = 67.29
67.29 Jumlah = 67.291

4 Urugan Pasir
Urugan Bawah Lantai Septicktank = 3.00 x 1.90 x 0.08 x 8.00 = 3.65
Urugan Pipa = 819.20 x 0.20 x 0.05 = 8.19
Urugan Bak Kontrol = 0.50 x 0.55 x 0.05 x 27.00 = 0.37
Urugan Galian Manhole = 0.70 x 0.80 x 0.05 x 27.00 = 0.76
12.97 Jumlah = 12.967
III PEKERJAAN BETON, DAN PASANGAN
1 Pek . Beton (f'c = 14,5 Mpa)
a Beton Sloof,Penyangga Media Bakteri, Kolom, Ring Balok dan Dinding Septictank (f'c = 14,5 Mpa)
Dinding Sisi Luar P = 2.70 x 1.95 x 0.10 x 2.00 = 1.05
Dinding Sisi Luar L = 1.50 x 2.07 x 0.10 x 2.00 = 0.62
Dinding Sisi Dalam P = 1.70 x 1.53 x 0.10 x 2.00 = 0.52
Dinding Sisi Dalam L = 0.50 x 1.53 x 0.10 x 2.00 = 0.15
Kaki Kolom Dalam = 0.35 x 0.15 x 0.15 x 2.00 = 0.02
Sloof Sisi Dalam P = 1.75 x 0.15 x 0.20 x 2.00 = 0.11
Sloof Sisi Dalam L = 0.55 x 0.15 x 0.20 x 2.00 = 0.03
Penyangga = 2.60 x 0.10 0.10 x 2.00 = 0.05
8.00 x 2.55 Jumlah = 20.424

b Beton Lantai Septictank T. 10 cm (f'c = 14,5 Mpa)


= 2.80 x 1.60 x 0.10 x 8.00 = 3.58
3.58 Jumlah = 3.584
c Beton Dak Tutup Septictank T. 10 cm (f'c = 14,5 Mpa)
= 2.80 x 1.60 x 0.10 x 8.00 = 3.58
3.58 Jumlah = 3.584
d Beton Bak Kontrol T. 10 cm (f'c = 14,5 Mpa)
= 0.40 x 0.45 x 0.10 x 4.00 x 38.00 = 2.74
2.74 Jumlah = 2.736
e Beton Lantai T. 10 cm dan Plat Tutup Bak Kontrol T. 5 cm (f'c = 14,5 Mpa)
Beton Lantai = 0.40 x 0.40 x 0.10 x 38.00 = 0.61
Beton Penutup = 0.50 x 0.50 x 0.05 x 38.00 = 0.48
1.08 Jumlah = 1.083
f Beton Manhole T. 10 cm (f'c = 14,5 Mpa)
Manhole = 0.60 x 0.65 x 0.10 x 4.00 x 27.00 = 4.21
4.21 Jumlah = 4.212
g Beton Lantai T. 10 cm dan Plat Tutup Manhole T. 5 cm (f'c = 14,5 Mpa)
Beton Lantai = 0.60 x 0.60 x 0.10 x 27.00 = 0.97
Beton Penutup = 0.70 x 0.70 x 0.05 x 27.00 = 0.66
1.63 Jumlah = 1.634
h Beton Manhole Resapan T. 10 cm (f'c = 14,5 Mpa)
Manhole Resapan = 0.60 x 1.00 x 0.10 x 4.00 x 8.00 = 1.92
1.92 Jumlah = 1.920
i Beton Plat Tutup Manhole Resapan T. 5 cm (f'c = 14,5 Mpa)
Beton Penutup = 0.70 x 0.70 x 0.05 x 8.00 = 0.20
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4
0.20 Jumlah = 0.196
2 Pek. Pembesian
a Pembesian Sloof Septictank Ø 10 dan 8 mm Jarak 15 Cm
Pembesian Horizontal :
Sloof Sisi Luar P = 2.80 x 4.00 x 0.62 x 2.00 = 13.82
Sloof Sisi Luar L = 1.60 x 4.00 x 0.62 x 2.00 = 7.90
Sloof Sisi Dalam P = 1.85 x 4.00 x 0.62 x 2.00 = 9.13
Sloof Sisi Dalam L = 0.65 x 4.00 x 0.62 x 2.00 = 3.21
8.00 x 34.06
Pembesian Vertikal :
Sloof Sisi Luar P = 2.70 : 0.15 x 0.50 x 0.40 x 2.00 = 7.51
Sloof Sisi Luar L = 1.60 : 0.15 x 0.50 x 0.40 x 2.00 = 4.35
Sloof Sisi Dalam P = 1.75 : 0.15 x 0.70 x 0.40 x 2.00 = 6.64
Sloof Sisi Dalam L = 0.55 : 0.15 x 0.70 x 0.40 x 2.00 = 2.21
8.00 x 20.70 Jumlah = 438.051
b Pembesian Lantai Septictank Ø 10 mm Jarak 15 Cm
Pembesian A = 2.80 : 0.15 x 1.60 x 0.62 x 8.00 = 150.05
150.05
Pembesian B = 1.60 : 0.15 x 2.80 x 0.62 x 8.00 = 152.03
152.03 Jumlah = 302.083
c Pembesian Kolom Septictank Ø 10 mm Jarak 15 Cm
Pembesian Vertikal :
Kolom Sisi Luar = 2.15 x 4.00 x 0.62 x 4.00 = 21.22
Kolom Sisi Dalam = 1.73 x 4.00 x 0.62 x 4.00 = 17.08
Kaki Kolom Dalam = 0.55 x 4.00 x 0.62 x 2.00 = 2.71
8.00 x 41.02
Pembesian Horizontal :
Kolom Sisi Luar = 1.95 : 0.15 x 0.42 x 0.40 x 4.00 = 9.29
Kolom Sisi Dalam = 1.53 : 0.15 x 0.42 x 0.40 x 4.00 = 7.30
Kaki Kolom Dalam = 0.35 : 0.15 x 0.50 x 0.40 x 2.00 = 1.19
8.00 x 17.78 Jumlah = 470.345
d Pembesian Dinding Septictank Ø 10 mm Jarak 15 Cm
Pembesian Vertikal :
Dinding Sisi Luar P = 2.70 : 0.15 x 2.15 x 0.62 x 2.00 = 50.41
Dinding Sisi Luar L = 1.50 : 0.15 x 2.27 x 0.62 x 2.00 = 30.81
Dinding Sisi Dalam P = 1.70 : 0.15 x 1.73 x 0.62 x 2.00 = 25.62
Dinding Sisi Dalam L = 0.50 : 0.15 x 1.73 x 0.62 x 2.00 = 8.54
8.00 x 115.38
Pembesian Horizontal :
Dinding Sisi Luar P = 2.05 : 0.15 x 2.90 x 0.62 x 2.00 = 50.10
Dinding Sisi Luar L = 2.17 : 0.15 x 1.70 x 0.62 x 2.00 = 31.47
Dinding Sisi Dalam P = 1.63 : 0.15 x 1.90 x 0.62 x 2.00 = 25.79
Dinding Sisi Dalam L = 1.63 : 0.15 x 0.70 x 0.62 x 2.00 = 9.50
8.00 x 116.86 Jumlah = 1,857.910
e Pembesian Ring Balok Septictank Ø 10 dan 8 mm Jarak 15 Cm
Pembesian Horizontal :
Balok Sisi Luar P = 2.80 x 4.00 x 0.62 x 2.00 = 13.82
Balok Sisi Luar L = 1.60 x 4.00 x 0.62 x 2.00 = 7.90
Balok Sisi Dalam P = 1.80 x 4.00 x 0.62 x 2.00 = 8.88
Balok Sisi Dalam L = 0.60 x 4.00 x 0.62 x 2.00 = 2.96
8.00 x 33.56
Pembesian Vertikal :
Balok Sisi Luar P = 2.70 : 0.15 x 0.42 x 0.40 x 2.00 = 6.30
Balok Sisi Luar L = 1.30 : 0.15 x 0.42 x 0.40 x 2.00 = 2.99
Balok Sisi Dalam P = 1.70 : 0.15 x 0.42 x 0.40 x 2.00 = 3.98
Balok Sisi Dalam L = 0.30 : 0.15 x 0.42 x 0.40 x 2.00 = 1.00
8.00 x 14.27 Jumlah = 382.658
f Pembesian Penutup Septictank Ø 10 mm Jarak 15 Cm
Pembesian A = 2.80 : 0.15 x 2.00 x 0.62 x 2.00 = 23.45
8.00 x 23.45
Pembesian B = 1.60 : 0.15 x 3.20 x 0.62 x 2.00 = 21.72
8.00 x 21.72 Jumlah = 361.315
g Pembesian Bak Kontrol Ø 10 mm Jarak 15 Cm 45.164
Pembesian Vertikal
Manhole = 0.40 : 0.15 x 0.45 x 0.62 x 4.00 = 3.33
Pembesian Horizontal
Manhole = 0.35 : 0.15 x 0.40 x 0.62 x 4.00 = 2.96
38.00 6.29 Jumlah = 239.149
h Pembesian Lantai dan Penutup Bak Kontrol Ø 10 mm Jarak 15 Cm
Pembesian Lantai = 0.40 : 0.15 x 0.40 x 0.62 x 2.00 = 1.48
1.48
Pembesian Penutup = 0.50 : 0.15 x 0.45 x 0.62 x 2.00 = 2.22
38.00 x 2.22 Jumlah = 84.406
i Pembesian Manhole Ø 10 mm Jarak 15 Cm
Pembesian Vertikal
Manhole = 0.60 : 0.15 x 0.55 x 0.62 x 4.00 = 6.79
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4
Pembesian Horizontal
Manhole = 0.60 : 0.15 x 0.60 x 0.62 x 4.00 = 7.40
27.00 x 14.19 Jumlah = 383.157
j Pembesian Lantai dan Penutup Manhole Ø 10 mm Jarak 15 Cm
Pembesian Lantai = 0.60 : 0.15 x 0.60 x 0.62 x 2.00 = 3.70
3.70
Pembesian Penutup = 0.70 : 0.15 x 0.65 x 0.62 x 2.00 = 4.01
27.00 x 4.01 Jumlah = 108.284
k Pembesian Manhole Resapan Ø 10 mm Jarak 15 Cm
Pembesian Vertikal
Manhole Resapan = 0.60 : 0.15 x 0.95 x 0.62 x 4.00 = 11.72
Pembesian Horizontal
Manhole Resapan = 1.00 : 0.15 x 0.60 x 0.62 x 4.00 = 10.37
8.00 x 22.09 Jumlah = 176.709
l Pembesian Penutup Manhole Resapan Ø 10 mm Jarak 15 Cm
Pembesian Penutup = 0.70 : 0.15 x 0.65 x 0.62 x 2.00 = 4.01
8.00 x 4.01 Jumlah = 32.084
3 Pek. Bekisting
a Bekisting Bawah Sloof Septictank
Sloof Sisi Luar P = 2.80 x 0.10 x 8.00 = 2.24
Sloof Sisi Luar L = 1.60 x 0.10 x 8.00 = 1.28
Sloof Sisi Dalam P = 1.75 x 0.10 x 3.00 x 8.00 = 4.20
Sloof Sisi Dalam L = 0.55 x 0.10 x 3.00 x 8.00 = 1.32
9.04 Jumlah = 9.040
b Bekisting Kolom, Dinding dan Ring Balok Septictank
Dinding Sisi Luar P = 2.70 x 1.95 x 2.00 x 2.00 = 21.06
Dinding Sisi Luar L = 1.50 x 2.07 x 2.00 x 2.00 = 12.42
Dinding Sisi Dalam P = 1.70 x 1.53 x 2.00 x 2.00 = 10.40
Dinding Sisi Dalam L = 0.50 x 1.53 x 2.00 x 2.00 = 3.06
Kaki Kolom Dalam = 0.35 x 0.15 x 4.00 x 2.00 = 0.42
x 8.00 x 47.36 Jumlah = 378.912
c Bekisting Penutup Septictank
= 2.80 x 1.60 x 8.00 = 35.84
35.84 Jumlah = 35.840
d Bekisting Bak Kontrol
= 0.40 x 0.45 4.00 x 2.00 x 38.00 = 54.72
54.72 Jumlah = 54.720
e Bekisting Bak Manhole
= 0.60 x 0.65 4.00 x 2.00 x 27.00 = 84.24
84.24 Jumlah = 84.240
f Bekisting Bak Manhole Resapan
= 0.60 x 1.00 4.00 x 2.00 x 8.00 = 38.40
38.40 Jumlah = 38.400
4 Pek. Plesteran
Plesteran Dinding Sisi Dalam P = 2.60 x 1.93 x x 2.00 = 10.04
Plesteran Dinding Sisi Dalam L = 1.40 x 2.06 x x 2.00 = 5.77
Plesteran Dinding Sisi Dalam Luar P = 1.70 x 1.73 x 2.00 x 2.00 = 11.76
Plesteran Dinding Sisi Dalam Luar L = 0.50 x 1.73 x 2.00 x 2.00 = 3.46
Plesteran Lantai 2.60 x 1.50 x 3.90
8.00 x 279.42 Jumlah = 279.424
5 Pek. Acian
Acian Dinding Sisi Dalam P = 2.50 x 1.93 x x 2.00 = 9.65
Acian Dinding Sisi Dalam L = 1.40 x 2.06 x x 2.00 = 5.77
Acian Dinding Sisi Dalam Luar P = 1.70 x 1.73 x 2.00 x 2.00 = 11.76
Acian Dinding Sisi Dalam Luar L = 0.50 x 1.73 x 2.00 x 2.00 = 3.46
Acian Kaki Kolom = 0.35 x 0.15 x 4.00 x 4.00 = 0.84
AcianLantai 2.60 x 1.50 x = 3.90
8.00 x 283.06
Acian Dinding Bak Kontrol = 0.30 x 0.35 x 4.00 x 38.00 = 15.96
Acian Lantai Bak Kontrol = 0.40 x 0.40 x 38.00 = 6.08
22.04
Acian Dinding Manhole = 0.50 x 0.55 x 4.00 x 27.00 = 29.70
Acian Dinding Manhole Resapan = 0.50 x 1.00 x 4.00 x 8.00 = 16.00
Acian Lantai Manhole = 0.60 x 0.60 x 27.00 = 9.72
55.42 Jumlah = 360.516
6 Pek. Pas. Ulin 5/7 Cm Penyangga Media Bakteri
Sisi Panjang = 1.40 x 0.07 x 0.05 x 8.00 = 0.04
Sisi Pendek = 0.40 x 0.07 x 0.05 x 36.00 = 0.05
8.00 x 0.09 Jumlah = 0.717
7 Plastik Cor
Lantai Septictank = 2.90 x 1.70 x 8.00 = 39.44
Lantai Bak Kontrol = 0.50 x 0.50 x 38.00 = 9.50
Lantai Manhole = 0.70 x 0.70 x 27.00 = 13.23
62.17 Jumlah = 62.170
8 Pek. Pas. Pipa PVC Ø 4" AW
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4
Pipa Septictank = 1.00 + 2.00 x 2.00 x 8.00 = 48.00
Pipa Outlet = 4.00 x 8.00 = 32.00
Pipa Jaringan dan SR = 1,024.00 = 1,024.00
1,104.00 Jumlah = 1,104.000
9 Pemasangan / Pegadaan Media Bakteri Botol Plastik (Tersusun Sarang Tawon )
= 1.00 x 8.00 = 8.00
8.00 Jumlah = 8.000
10 Pek. Pas. Aksesoris Pipa
a Elbow PVC Ø 4"
Septictank = 4.00 x 8.00 = 32.00
32.00 Jumlah = 32.000
b Tee PVC Ø 4"
Septictank = 3.00 x 8.00 = 24.00
24.00 Jumlah = 24.000
PERHITUNGAN VOLUME

Jumlah

Keg

Unit

Unit

Bh

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3
Jumlah

4
M3

Kg

Kg

Kg

Kg

Kg

Kg

Kg

Kg
Jumlah

Kg

Kg

Kg

Kg

M2

M2

M2

M2

M2

M2

M2

M2

M3

M2
Jumlah

M'

Unit

Bh

Bh
ANALISA
A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.75 109,798.00 82,348.50
Mandor L.04 OH 0.025 120,120.00 3,003.00
JUMLAH TENAGA KERJA 85,351.50
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 85,351.50


E Overhead & Profit (Contoh 15 %) 15% x D
F Harga Satuan Pekerjaan (D+E) 85,351.50

A.2.3.1.2. Penggalian 1 m3 tanah biasa sedalam 2 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.9 109,798.00 98,818.20
Mandor L.04 OH 0.045 120,120.00 5,405.40
JUMLAH TENAGA KERJA 104,223.60
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 104,223.60


E Overhead & Profit (Contoh 15 %) 15% x D
F Harga Satuan Pekerjaan (D+E) 104,223.60

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah

Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.5 109,798.00 54,899.00
Mandor L.04 OH 0.05 120,120.00 6,006.00
JUMLAH TENAGA KERJA 60,905.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 60,905.00
E Overhead & Profit (Contoh 15 %) 15% x D
F Harga Satuan Pekerjaan (D+E) 60,905.00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3 109,798.00 32,939.40
Mandor L.04 OH 0.01 120,120.00 1,201.20
JUMLAH TENAGA KERJA 34,140.60
B BAHAN
Pasir urug 1.200 171,000.00 205,200.00
JUMLAH HARGA BAHAN 205,200.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 239,340.60
E Overhead & Profit (Contoh 15 %) 15% x D
F Harga Satuan Pekerjaan (D+E) 239,340.60
A.4.1.1 HARGA SATUAN PEKERJAAN BETON

CATATAN
Bobot isi pasir = 1.400 kg/m3. Bobot isi kerikil = 1.350 kg/m3. Buckling factor pasir = 20 %

A.4.1.1.2. Membuat 1 m3 beton mutu f’ = 9.8 MPa (K 125). slump (12 ± 2) cm. w/c = 0.78
w/c = 0.87

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 109,798.00 181,166.70
Tukang Batu L.02 OH 0.275 111,930.00 30,780.75
Kepala Tukang L.03 OH 0.028 117,260.00 3,283.28
Mandor L.04 OH 0.083 120,120.00 9,969.96
JUMLAH TENAGA KERJA 225,200.69
B BAHAN
Semen Portland kg 276 1,700.00 469,200.00
Pasir Beton kg 828 250.00 207,000.00
Kerikil (Maks 30mm) kg 1012 366.67 371,066.67
Air Liter 215
JUMLAH HARGA BAHAN 1,047,266.67
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,272,467.36


E Overhead & Profit (Contoh 15 %) 15% x D
F Harga Satuan Pekerjaan (D+E) 1,272,467.36

A. A.4.1.1.5. Membuat 1 m3 beton mutu f’ = 14.5 MPa. slump (12 ± 2) cm. w/c = 0.66

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 109,798.00 181,166.70
Tukang Batu L.02 OH 0.275 111,930.00 30,780.75
Kepala Tukang L.03 OH 0.028 117,260.00 3,283.28
Mandor L.04 OH 0.083 120,120.00 9,969.96
JUMLAH TENAGA KERJA 225,200.69
B BAHAN
Semen Portland kg 326 1,700.00 554,200.00
Pasir Beton kg 760 250.00 190,000.00
Kerikil (Maks 30mm) kg 1029 366.67 377,300.00
Air Liter 215
JUMLAH HARGA BAHAN 1,121,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,346,700.69


E Overhead & Profit (Contoh 15 %) 15% x D
F Harga Satuan Pekerjaan (D+E) 1,346,700.69

A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.07 109,798.00 7,685.86
Tukang Besi L.02 OH 0.07 111,930.00 7,835.10
Kepala Tukang L.03 OH 0.007 117,260.00 820.82
Mandor L.04 OH 0.004 120,120.00 480.48
JUMLAH TENAGA KERJA 16,822.26
B BAHAN
Besi beton (polos/ulir) kg 10.500 14,000.00 147,000.00
Kawat beton kg 0.15 26,000.00 3,900.00
JUMLAH HARGA BAHAN 150,900.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 167,722.26


E Overhead & Profit (Contoh 15 %) 15% x D
F Harga Satuan Pekerjaan (D+E) 167,722.26
A.4.1.1.21.a Pemasangan 1 m 2 Sloof

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.52 109,798.00 57,094.96
Tukang Kayu L.02 OH 0.26 111,930.00 29,101.80
Kepala Tukang L.03 OH 0.026 117,260.00 3,048.76
Mandor L.04 OH 0.026 120,120.00 3,123.12
JUMLAH TENAGA KERJA 92,368.64
B BAHAN
Kayu kelas III m3 0.022 1,612,000.00 35,464.00
Paku 5 cm – 10 cm kg 0.15 26,000.00 3,900.00
Minyak bekisting Liter 0 36,400.00 -
JUMLAH HARGA BAHAN 39,364.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 131,732.64


E Overhead & Profit (Contoh 15 %) 15% x D
F Harga Satuan Pekerjaan (D+E) 131,732.64

A.4.1.1.24.a. Pemasangan 1 m2 bekisting untuk lantai

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 109,798.00 72,466.68
Tukang Kayu L.02 OH 0.33 111,930.00 36,936.90
Kepala Tukang L.03 OH 0.033 117,260.00 3,869.58
Mandor L.04 OH 0.033 120,120.00 3,963.96
JUMLAH TENAGA KERJA 117,237.12
B BAHAN
Kayu kelas III m3 0.040 1,612,000.00 64,480.00
Paku 5 cm – 12 cm kg 0.400 26,000.00 10,400.00
Minyak bekisting Liter 0.000 36,400.00 -
Balok kayu Bekisting m3 0.015 803,088.00 12,046.32
Dolken kayu galam. 8–10 cm
Batang 3.000 9,880.00 29,640.00
panjang 4 m
JUMLAH HARGA BAHAN 116,566.32
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 233,803.44
E Overhead & Profit (Contoh 15 %) 15% x D
F Harga Satuan Pekerjaan (D+E) 233,803.44

A.4.1.1.25.a. Pemasangan 1 m 2 bekisting untuk dinding

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 109,798.00 72,466.68
Tukang Kayu L.02 OH 0.33 111,930.00 36,936.90
Kepala Tukang L.03 OH 0.033 117,260.00 3,869.58
Mandor L.04 OH 0.033 120,120.00 3,963.96
JUMLAH TENAGA KERJA 117,237.12
B BAHAN
Kayu kelas III m3 0.030 1,612,000.00 48,360.00
Paku 5 cm – 12 cm kg 0.400 26,000.00 10,400.00
Minyak bekisting Liter 0.000 36,400.00 -
Balok kayu Bekisting m3 0.020 803,088.00 16,061.76
Dolken kayu , 8–10 cm, panj. 4 m
Batang 3.000 9,880.00 29,640.00
JUMLAH HARGA BAHAN 104,461.76
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 221,698.88
E Harga Satuan Pekerjaan 221,698.88
A.4.1.1.25.b. Pemasangan 1 m2 Bekisting untuk manhole dan bak kontrol

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 109,798.00 72,466.68
Tukang Kayu L.02 OH 0.33 111,930.00 36,936.90
Kepala Tukang L.03 OH 0.033 117,260.00 3,869.58
Mandor L.04 OH 0.033 120,120.00 3,963.96
JUMLAH TENAGA KERJA 117,237.12
B BAHAN
Kayu kelas III m3 0.030 1,612,000.00 48,360.00
Paku 5 cm – 12 cm kg 0.400 26,000.00 10,400.00
Minyak bekisting Liter 0.000 36,400.00 -
Balok kayu Bekisting m3 0.020 803,088.00 16,061.76
Dolken kayu , 8–10 cm, panj. 4 m
Batang 0.000 9,880.00 -
JUMLAH HARGA BAHAN 74,821.76
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 192,058.88
E Harga Satuan Pekerjaan 192,058.88

A.4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 109,798.00 32,939.40
Tukang Batu L.03 OH 0.150 111,930.00 16,789.50
Kepala Tukang L.03 OH 0.015 117,260.00 1,758.90
Mandor L.04 OH 0.015 120,120.00 1,801.80
JUMLAH TENAGA KERJA 53,289.60
B BAHAN
Semen PC Kg 6.240 1,700.00 10,608.00
Pasir m3 0.024 495,000.00 11,880.00
JUMLAH HARGA BAHAN 22,488.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 75,777.60


E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E) 75,777.60
A.4.4.2.27. Pemasangan 1 m2 acian.

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 109,798.00 21,959.60
Tukang Batu L.03 OH 0.100 111,930.00 11,193.00
Kepala Tukang L.03 OH 0.010 117,260.00 1,172.60
Mandor L.04 OH 0.010 120,120.00 1,201.20
JUMLAH TENAGA KERJA 35,526.40
B BAHAN
Semen PC Kg 3.250 1,700.00 5,525.00
JUMLAH HARGA BAHAN 5,525.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 41,051.40


E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E) 41,051.40
A.5.1.1 32.a Pemasangan 1 m’ pipa PVC tipe AW diameter 4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 109,798.00 8,893.64
Tukang batu L.02 0.135 111,930.00 15,110.55
Kepala tukang L.03 0.0135 117,260.00 1,583.01
Mandor L.04 OH 0.004 120,120.00 480.48
JUMLAH TENAGA KERJA 26,067.68
B BAHAN
Pipa PVC 4” M 1.2 119,275.00 143,130.00
Perlengkapan % 10 119,275.00 11,927.50
JUMLAH HARGA BAHAN 155,057.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 181,125.18


E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E) 181,125.18
ANALISA HARGA SATUAN PEKERJAAN

Analisa Uraian Pekerjaan Harga Satuan Upah Bahan Jumlah


( Rp ) ( Rp ) ( Rp ) ( Rp )

BOW. Anl. F.1.a 1 M3 Mengerjakan Rangka Bawah Ulin

15.0000 Tukang Kayu 111,930.00 1,678,950.00 1,678,950.00


1.5000 Kepala Tukang 117,260.00 175,890.00 175,890.00
5.0000 Pekerja 109,798.00 548,990.00 548,990.00
0.2500 Mandor 120,120.00 30,030.00 30,030.00
1.2000 M3 Balok Kayu Ulin 6,000,000.00 7,200,000.00 7,200,000.00
Jumlah 2,433,860.00 7,200,000.00 9,633,860.00
HARGA SATUAN UPAH DAN BAHAN

Program : Program Pembangunan Prasarana Sanitasi


Kegiatan : Pembuatan Prasarana Sanitasi (DAK)
Pekerjaan : Pembangunan Baru Tangki Septik Skala Komunal Desa Karalai 8 Unit (DAK)
Lokasi : Kecamatan Tanah Siang
Tahun : 2018

A. BAHAN

No. Nama Bahan Satuan Kode Harga

1 Kerikil Sungai M3 M 012 470,000.00


2 Kerikil Sungai Ayak Tanpa Pasir M3 M 013 495,000.00
3 Pasir Urug / Timbunan M3 M 040 171,000.00
4 Pasir Ayak Untuk Beton M3 M 041 350,000.00
5 Semen Portland (PC) Lokal Kalimantan Setara merk Conch (1 zak = 50 kg) Zak M 080 85,000.00
6 Besi Beton Polos (top) Kg M 167 14,000.00
7 Kawat Beton (Bindrat) Kg 26,000.00
8 Kayu Bekisting M3 M.180 803,088.00
9 Kayu Bulat Ø 6 - 10 cm panjang 4 m Btg 9,880.00
10 Minyak Pelumas (SAE 30) / Minyak Bekisting Ltr M.185 36,400.00
11 Paku Kayu (2") Kg 26,000.00
12 Paku Kayu (2,5" - 5") Kg 26,000.00
13 Papan Bekisting M3 1,612,000.00
14 Plastik Cor M2 6,240.00
15 Pipa Paralon PVC Ø 3" DV, panjang 4 m Btg 172,900.00
16 Pipa PVC AW Ø 4", panjang 4 m setara merk Power Btg 477,100.00
17 Elbow 4" PVC (AW) 90˚ Panjang Bh 79,750.00
18 Tee 4" PVC (AW) Bh 150,000.00
19 Kayu Ulin Balok Kecil M3 6,000,000.00

B. UPAH TENAGA KERJA

No. Jenis Keahlian Satuan Kode Harga

1 Mandor Oh L.061 120,120.00


2 Kepala Tukang (Batu, Besi, Kayu, Cat, Gali ) Oh L.073 117,260.00
3 Tukang (Batu, Besi, Kayu, Cat, Gali ) Oh L.079 111,930.00
4 Pekerja / Buruh Semi Terlatih Oh L.106 109,798.00
DAFTAR HARGA SATUAN B
SEMESTER II
DINAS PEKERJAAN UMUM DAN PENATAA

A. BAHAN LOKAL DOMINAN YANG SANGAT DIPENGARUHI BIAYA ANGKUT


HARGA
DASAR
NO. BAHAN KODE SAT SUMBER BAHAN
SETEMPAT
(1) (2) (3) (4) (5) (RP.)
(6)

1 Batu Gunung/Batu Belah M 010 m3 Puruk Cahu 204,545


Saripoi 390,000
Dirung Lingkin 350,000
Muara Laung 390,000
Makunjung 450,000
Tbg Lahung 374,000
Tbg Kunyi 650,000
Tbg Bantian 475,000
Tbg Olong 374,000
Muara Joloi 500,000

2 Batu Pecah 10 - 15 cm M 026 m3 Puruk Cahu 379,545


(Manual) Saripoi 565,000
Dirung Lingkin 525,000
Muara Laung 565,000
Makunjung 694,000
Tbg Lahung 550,000
Tbg Kunyi 626,000
Tbg Bantian 572,000
Tbg Olong 490,000
Muara Joloi 640,000

3 Batu Pecah 5 - 7 cm M 022 m3 Puruk Cahu 429,545


(Manual) Saripoi 615,000
Dirung Lingkin 575,000
Muara Laung 615,000
Makunjung 840,000
Tbg Lahung 619,000
Tbg Kunyi 767,000
Tbg Bantian 708,000
Tbg Olong 619,000
Muara Joloi 796,000

4 Batu Pecah 3 - 5 cm M 023 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

5 Batu Pecah 2 - 3 cm M 024 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

6 Batu Pecah 1 - 2 cm M 025 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

7 Batu Pecah 0,5 - 1 cm M 026 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

8 Batu Pecah Tersaring M 018 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

9 Debu Batu m3 Puruk Cahu 454,545


Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

10 Kerikil Galian Bukit M 011 m3 Puruk Cahu 181,818


(Awcas) Saripoi 370,000
Dirung Lingkin 330,000
Muara Laung 370,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

11 Kerikil Sungai M 012 m3 Puruk Cahu 281,818


Saripoi 470,000
Dirung Lingkin 430,000
Muara Laung 470,000
Makunjung 437,000
Tbg Lahung 450,000
Tbg Kunyi 499,000
Tbg Bantian 437,000
Tbg Olong 374,000
Muara Joloi 454,000

12 Kerikil Sungai Ayak M 013 m3 Puruk Cahu 306,818


Tanpa Pasir Saripoi 495,000
Dirung Lingkin 455,000
Muara Laung 495,000
Makunjung 400,000
Tbg Lahung 600,000
Tbg Kunyi 522,000
Tbg Bantian 460,000
Tbg Olong 397,000
Muara Joloi 477,000

13 Pasir Urug / Timbunan M 040 m3 Puruk Cahu 112,000


Saripoi 171,000
Dirung Lingkin 179,000
Muara Laung 268,000
Makunjung 300,000
Tbg Lahung 310,000
Tbg Kunyi 202,000
Tbg Bantian 191,000
Tbg Olong 191,000
Muara Joloi 250,000

14 Pasir Ayak Untuk M 041 m3 Puruk Cahu 231,818


Beton / Pasir Barito. Saripoi -
Dirung Lingkin 380,000
Muara Laung 420,000
Makunjung 374,000
Tbg Lahung 400,000
Tbg Kunyi 600,000
Tbg Bantian 500,000
Tbg Olong 400,000
Muara Joloi 500,000

15 Sirtu (tidak diayak, dari M 042 m3 Puruk Cahu 166,818


sungai) Saripoi -
Dirung Lingkin 315,000
Muara Laung 355,000
Makunjung 437,000
Tbg Lahung 437,000
Tbg Kunyi 534,000
Tbg Bantian 400,000
Tbg Olong 400,000
Muara Joloi 500,000

16 Tanah Timbunan M 050 m3 Puruk Cahu 80,000


Saripoi 150,000
Dirung Lingkin 150,000
Muara Laung 150,000
Makunjung 238,000
Tbg Lahung 250,000
Tbg Kunyi 200,000
Tbg Bantian 179,000
Tbg Olong 179,000
Muara Joloi 238,000

17.a Semen Portland M 080 zak Puruk Cahu 70,000


Lokal Kalimantan Saripoi 85,000
Setara merk Conch Dirung Lingkin 85,000
(1 zak = 50 kg) Muara Laung 80,000
Makunjung 70,000
Tbg Lahung 88,000
Tbg Kunyi 170,000
Tbg Bantian 133,000
Tbg Olong 143,000
Muara Joloi 220,000

17.b Semen Portland M 080 zak Puruk Cahu 85,000


Non Lokal Kalimantan Saripoi 100,000
Setara merk Semen Gresik Dirung Lingkin 100,000
(1 zak = 50 kg) Muara Laung 95,000
Makunjung 80,000
Tbg Lahung 103,000
Tbg Kunyi 185,000
Tbg Bantian 148,000
Tbg Olong 158,000
Muara Joloi 235,000
18 Besi Beton Polos (top) M 167 Kg Puruk Cahu 12,500
Saripoi 14,000
Dirung Lingkin 14,000
Muara Laung 14,000
Makunjung 14,500
Tbg Lahung 15,000
Tbg Kunyi 15,500
Tbg Bantian 15,400
Tbg Olong 15,600
Muara Joloi 16,500

19 Kayu Ulin Balok Besar M 181 m3 Puruk Cahu 6,000,000


Saripoi 5,800,000
Dirung Lingkin 6,000,000
Muara Laung 6,800,000
Makunjung 6,300,000
Tbg Lahung 6,200,000
Tbg Kunyi 6,200,000
Tbg Bantian 6,200,000
Tbg Olong 5,000,000
Muara Joloi 4,700,000

20 Kayu Ulin Balok Kecil M 181 m3 Puruk Cahu 6,000,000


Saripoi 5,800,000
Dirung Lingkin 6,000,000
Muara Laung 6,800,000
Makunjung 6,300,000
Tbg Lahung 6,200,000
Tbg Kunyi 6,200,000
Tbg Bantian 6,200,000
Tbg Olong 5,000,000
Muara Joloi 4,700,000

21 Papan Ulin M 181 m3 Puruk Cahu 6,000,000


Saripoi 5,900,000
Dirung Lingkin 5,900,000
Muara Laung 8,100,000
Makunjung 8,100,000
Tbg Lahung 6,300,000
Tbg Kunyi 6,000,000
Tbg Bantian 6,000,000
Tbg Olong 5,300,000
Muara Joloi 5,500,000

22 Kayu Lanan Balok Kecil m3 Puruk Cahu 2,600,000


Saripoi 2,500,000
Dirung Lingkin 2,400,000
Muara Laung 1,800,000
Makunjung 1,800,000
Tbg Lahung 2,500,000
Tbg Kunyi 2,400,000
Tbg Bantian 2,300,000
Tbg Olong 2,300,000
Muara Joloi 2,100,000

23 Papan Lanan m3 Puruk Cahu 2,600,000


Saripoi 2,500,000
Dirung Lingkin 2,600,000
Muara Laung 2,100,000
Makunjung 2,100,000
Tbg Lahung 2,500,000
Tbg Kunyi 2,400,000
Tbg Bantian 2,300,000
Tbg Olong 2,300,000
Muara Joloi 2,200,000

Keterangan :
Regional I : Kecamatan Murung

Regional II : Kecamatan Tanah Siang


Kecamatan Tanah Siang Selatan
Kecamatan Laung Tuhup
Kecamatan Barito Tuhup Raya

Regional III : Kecamatan Permata Intan


Kecamatan Sei Babuat

Regional IV : Kecamatan Sumber Barito


Kecamatan Uut Murung
Kecamatan Seribu Riam
AR HARGA SATUAN BAHAN DAN UPAH
SEMESTER II 2017
UMUM DAN PENATAAN RUANG KAB. MURUNG RAYA

HARGA REGIONAL ONGKOS ANGKUT KE LOKASI


REGIONAL I REGIONAL II REGIONAL III REGIONAL IV PEKERJAAN
(7) (8) (9) (10) (11)

255,682 = [(150.000 + (15.000 x jarak)] / 3


487,500 = [(150.000 + (15.000 x jarak)] / 3
437,500 = [(150.000 + (15.000 x jarak)] / 3
487,500 = [(150.000 + (15.000 x jarak)] / 3
562,500 = [(150.000 + (15.000 x jarak)] / 3
467,500 = [(150.000 + (15.000 x jarak)] / 3
812,500 = [(150.000 + (15.000 x jarak)] / 3
593,750 = [(150.000 + (15.000 x jarak)] / 3
467,500 = [(150.000 + (15.000 x jarak)] / 3
625,000 = [(150.000 + (15.000 x jarak)] / 3

474,432 = [(150.000 + (15.000 x jarak)] / 3


706,250 = [(150.000 + (15.000 x jarak)] / 3
656,250 = [(150.000 + (15.000 x jarak)] / 3
706,250 = [(150.000 + (15.000 x jarak)] / 3
867,500 = [(150.000 + (15.000 x jarak)] / 3
687,500 = [(150.000 + (15.000 x jarak)] / 3
782,500 = [(150.000 + (15.000 x jarak)] / 3
715,000 = [(150.000 + (15.000 x jarak)] / 3
612,500 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3

536,932 = [(150.000 + (15.000 x jarak)] / 3


768,750 = [(150.000 + (15.000 x jarak)] / 3
718,750 = [(150.000 + (15.000 x jarak)] / 3
768,750 = [(150.000 + (15.000 x jarak)] / 3
1,050,000 = [(150.000 + (15.000 x jarak)] / 3
773,750 = [(150.000 + (15.000 x jarak)] / 3
958,750 = [(150.000 + (15.000 x jarak)] / 3
885,000 = [(150.000 + (15.000 x jarak)] / 3
773,750 = [(150.000 + (15.000 x jarak)] / 3
995,000 = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

227,273 = [(150.000 + (15.000 x jarak)] / 3


462,500 = [(150.000 + (15.000 x jarak)] / 3
412,500 = [(150.000 + (15.000 x jarak)] / 3
462,500 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

352,273 = [(150.000 + (15.000 x jarak)] / 3


587,500 = [(150.000 + (15.000 x jarak)] / 3
537,500 = [(150.000 + (15.000 x jarak)] / 3
587,500 = [(150.000 + (15.000 x jarak)] / 3
546,250 = [(150.000 + (15.000 x jarak)] / 3
562,500 = [(150.000 + (15.000 x jarak)] / 3
623,750 = [(150.000 + (15.000 x jarak)] / 3
546,250 = [(150.000 + (15.000 x jarak)] / 3
467,500 = [(150.000 + (15.000 x jarak)] / 3
567,500 = [(150.000 + (15.000 x jarak)] / 3

383,523 = [(150.000 + (15.000 x jarak)] / 3


618,750 = [(150.000 + (15.000 x jarak)] / 3
568,750 = [(150.000 + (15.000 x jarak)] / 3
618,750 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
652,500 = [(150.000 + (15.000 x jarak)] / 3
575,000 = [(150.000 + (15.000 x jarak)] / 3
496,250 = [(150.000 + (15.000 x jarak)] / 3
596,250 = [(150.000 + (15.000 x jarak)] / 3

140,000 = [(150.000 + (15.000 x jarak)] / 3


213,750 = [(150.000 + (15.000 x jarak)] / 3
223,750 = [(150.000 + (15.000 x jarak)] / 3
335,000 = [(150.000 + (15.000 x jarak)] / 3
375,000 = [(150.000 + (15.000 x jarak)] / 3
387,500 = [(150.000 + (15.000 x jarak)] / 3
252,500 = [(150.000 + (15.000 x jarak)] / 3
238,750 = [(150.000 + (15.000 x jarak)] / 3
238,750 = [(150.000 + (15.000 x jarak)] / 3
312,500 = [(150.000 + (15.000 x jarak)] / 3

289,773 = [(150.000 + (15.000 x jarak)] / 3


= [(150.000 + (15.000 x jarak)] / 3
475,000 = [(150.000 + (15.000 x jarak)] / 3
525,000 = [(150.000 + (15.000 x jarak)] / 3
467,500 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
625,000 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
625,000 = [(150.000 + (15.000 x jarak)] / 3

208,523 = [(150.000 + (15.000 x jarak)] / 3


= [(150.000 + (15.000 x jarak)] / 3
393,750 = [(150.000 + (15.000 x jarak)] / 3
443,750 = [(150.000 + (15.000 x jarak)] / 3
546,250 = [(150.000 + (15.000 x jarak)] / 3
546,250 = [(150.000 + (15.000 x jarak)] / 3
667,500 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
625,000 = [(150.000 + (15.000 x jarak)] / 3

100,000 = [(150.000 + (15.000 x jarak)] / 3


187,500 = [(150.000 + (15.000 x jarak)] / 3
187,500 = [(150.000 + (15.000 x jarak)] / 3
187,500 = [(150.000 + (15.000 x jarak)] / 3
297,500 = [(150.000 + (15.000 x jarak)] / 3
312,500 = [(150.000 + (15.000 x jarak)] / 3
250,000 = [(150.000 + (15.000 x jarak)] / 3
223,750 = [(150.000 + (15.000 x jarak)] / 3
223,750 = [(150.000 + (15.000 x jarak)] / 3
297,500 = [(150.000 + (15.000 x jarak)] / 3

87,500 = [(150.000 + (15.000 x jarak)] / 80


106,250 = [(150.000 + (15.000 x jarak)] / 80
106,250 = [(150.000 + (15.000 x jarak)] / 80
100,000 = [(150.000 + (15.000 x jarak)] / 80
87,500 = [(150.000 + (15.000 x jarak)] / 80
110,000 = [(150.000 + (15.000 x jarak)] / 80
212,500 = [(150.000 + (15.000 x jarak)] / 80
166,250 = [(150.000 + (15.000 x jarak)] / 80
178,750 = [(150.000 + (15.000 x jarak)] / 80
275,000 = [(150.000 + (15.000 x jarak)] / 80

106,250 = [(150.000 + (15.000 x jarak)] / 80


125,000 = [(150.000 + (15.000 x jarak)] / 80
125,000 = [(150.000 + (15.000 x jarak)] / 80
118,750 = [(150.000 + (15.000 x jarak)] / 80
100,000 = [(150.000 + (15.000 x jarak)] / 80
128,750 = [(150.000 + (15.000 x jarak)] / 80
231,250 = [(150.000 + (15.000 x jarak)] / 80
185,000 = [(150.000 + (15.000 x jarak)] / 80
197,500 = [(150.000 + (15.000 x jarak)] / 80
293,750 = [(150.000 + (15.000 x jarak)] / 80
15,625 = [(150.000 + (15.000 x jarak)] / 4.000
17,500 = [(150.000 + (15.000 x jarak)] / 4.000
17,500 = [(150.000 + (15.000 x jarak)] / 4.000
17,500 = [(150.000 + (15.000 x jarak)] / 4.000
18,125 = [(150.000 + (15.000 x jarak)] / 4.000
18,750 = [(150.000 + (15.000 x jarak)] / 4.000
19,375 = [(150.000 + (15.000 x jarak)] / 4.000
19,250 = [(150.000 + (15.000 x jarak)] / 4.000
19,500 = [(150.000 + (15.000 x jarak)] / 4.000
20,625 = [(150.000 + (15.000 x jarak)] / 4.000

7,500,000 = [(150.000 + (15.000 x jarak)] / 3


7,250,000 = [(150.000 + (15.000 x jarak)] / 3
7,500,000 = [(150.000 + (15.000 x jarak)] / 3
8,500,000 = [(150.000 + (15.000 x jarak)] / 3
7,875,000 = [(150.000 + (15.000 x jarak)] / 3
7,750,000 = [(150.000 + (15.000 x jarak)] / 3
7,750,000 = [(150.000 + (15.000 x jarak)] / 3
7,750,000 = [(150.000 + (15.000 x jarak)] / 3
6,250,000 = [(150.000 + (15.000 x jarak)] / 3
5,875,000 = [(150.000 + (15.000 x jarak)] / 3

7,500,000 = [(150.000 + (15.000 x jarak)] / 3


7,250,000 = [(150.000 + (15.000 x jarak)] / 3
7,500,000 = [(150.000 + (15.000 x jarak)] / 3
8,500,000 = [(150.000 + (15.000 x jarak)] / 3
7,875,000 = [(150.000 + (15.000 x jarak)] / 3
7,750,000 = [(150.000 + (15.000 x jarak)] / 3
7,750,000 = [(150.000 + (15.000 x jarak)] / 3
7,750,000 = [(150.000 + (15.000 x jarak)] / 3
6,250,000 = [(150.000 + (15.000 x jarak)] / 3
5,875,000 = [(150.000 + (15.000 x jarak)] / 3

7,500,000 = [(150.000 + (15.000 x jarak)] / 3


7,375,000 = [(150.000 + (15.000 x jarak)] / 3
7,375,000 = [(150.000 + (15.000 x jarak)] / 3
10,125,000 = [(150.000 + (15.000 x jarak)] / 3
10,125,000 = [(150.000 + (15.000 x jarak)] / 3
7,875,000 = [(150.000 + (15.000 x jarak)] / 3
7,500,000 = [(150.000 + (15.000 x jarak)] / 3
7,500,000 = [(150.000 + (15.000 x jarak)] / 3
6,625,000 = [(150.000 + (15.000 x jarak)] / 3
6,875,000 = [(150.000 + (15.000 x jarak)] / 3

3,250,000 = [(150.000 + (15.000 x jarak)] / 3


3,125,000 = [(150.000 + (15.000 x jarak)] / 3
3,000,000 = [(150.000 + (15.000 x jarak)] / 3
2,250,000 = [(150.000 + (15.000 x jarak)] / 3
2,250,000 = [(150.000 + (15.000 x jarak)] / 3
3,125,000 = [(150.000 + (15.000 x jarak)] / 3
3,000,000 = [(150.000 + (15.000 x jarak)] / 3
2,875,000 = [(150.000 + (15.000 x jarak)] / 3
2,875,000 = [(150.000 + (15.000 x jarak)] / 3
2,625,000 = [(150.000 + (15.000 x jarak)] / 3

3,250,000 = [(150.000 + (15.000 x jarak)] / 3


3,125,000 = [(150.000 + (15.000 x jarak)] / 3
3,250,000 = [(150.000 + (15.000 x jarak)] / 3
2,625,000 = [(150.000 + (15.000 x jarak)] / 3
2,625,000 = [(150.000 + (15.000 x jarak)] / 3
3,125,000 = [(150.000 + (15.000 x jarak)] / 3
3,000,000 = [(150.000 + (15.000 x jarak)] / 3
2,875,000 = [(150.000 + (15.000 x jarak)] / 3
2,875,000 = [(150.000 + (15.000 x jarak)] / 3
2,750,000 = [(150.000 + (15.000 x jarak)] / 3

Puruk Cahu, Juni 2008

KEPALA DINAS PEKERJAAN UMUM


KAB. MURUNG RAYA

Ir. ADRIAN WT, MM


NIP. 530 007 565
HARGA DESAIN =
HARGA DASAR +
ONGKOS ANGKUT
(12)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11) 562,500


(8) + (11) 358333.33
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

AN UMUM
B. BAHAN UMUM

No. NAMA BAHAN SAT. KODE

(1) (2) (3) (4)

1 Alat Bantu Set M.170


2 Ampelas Lbr
3 Angker Bh
4 Arde Tanah Bh
5 Armatur Lampu Set
6 Aspal Pen 60/70 Kg M.061
7 Astelin Btl
8 Atap Genteng Metal merk Sakura Elang (77 x 80 cm) Tipe Classic (2 Susun) Lbr
9 Atap Polycarbonate + Rangka Besi Biasa (Set) M2
10 Atap Polycarbonate + Rangka Steinless (Set) M2
11 Atap Sirap Ulin Lbr
12 Baja Profil WF Kg M.165
13 Baja Ulir 1" / Profil Kg
14 Bak Mandi Fibreglass (70 cm x 70 cm Segi Empat Besar) Unit
15 Batako Bh
16 Batu - Bata Merah (5 x 11 x 22 cm) Bh
17 Baut dan Beugel 10 cm Biji
18 Baut dan Beugel 20 cm Biji
19 Besi Plat 5 mm Lbr
20 Besi Siku 4 cm panjang 6 cm Bh
21 Besi Strip Bh
22 Besi U, 10 x 10 x 6 m Btg
23 Besi Ulir (U - 39) 12 m Kg
24 Box Zekering Kas 2 Group Bh
25 Bubungan Atap Sakura Color 15 cm Lbr
26 Cat Dasar Kayu setara merk Kembang Kg
27 Cat Kilap Kayu setara merk Glotex Kg
28 Cat Kilap Kayu setara merk Jotun Kg
29 Cat Kilap Kayu setara merk Platone Kg
30 Cat Kilap Kayu setara setara Avia Paint Kg
31 Cat Menie Kg
32 Cat Tembok setara merk Jotun Kg
33 Cat Tembok setara merk Kimex Kg
34 Cat Tembok setara merk Matek Kg
35 Closed Duduk setara merk Toto Set
36 Closed Jongkok setara merk American Standart Bh
37 Engsel Lokal 3" setara merk 777 Bh
38 Engsel Lokal 3" setara merk Imperial Bh
39 Engsel Lokal 4" setara merk 777 Bh
40 Engsel Lokal 4" setara merk Imperial Bh
41 Espanyolet Tanam setara merk SES Bh
42 Fiting Lampu Gantung Biasa Bh
43 Fiting Lampu Gantung Tipe E 40 Bh
44 Fiting Lampu Gipsum Bh
45 Floor Strainer Bh
46 Glassbeads Kg
47 Glassblock Bh
48 Grendel 2" setara merk Omco Bh
49 Grendel 3" setara merk Omco Bh
50 Handle / Tarikan Kuning setara merk Top Bh
51 Handle Listrik 30 Ampere Bh
52 Isolasi Listrik Buah
53 Kabel NYA 2,5" M'
54 Kabel Power tipe NYM 3 x 2,5 mm setara merk Spring M'
55 Kabel Tanam 2 x 2,5" setara merk Spring M'
56 Kabel tipe NYFGBY 4 x 10 mm M'
57 Kaca Bening ≠ 3 mm M2
58 Kaca Bening ≠ 5 mm M2
59 Kaca Hitam / Ryben ≠ 5 mm M2
60 Kait Angin Kuning Pasang
61 Kait Talang Air merk Maspion Bh
62 Kapur Pasang / Kapur Padam Kg M.081
63 Kawat Berduri M'
64 Kawat Beton (Bindrat) Kg
65 Kawat Bronjong Roll
66 Kawat Harmonika M2
67 Kawat Las Dos
68 Kawat Nyamuk (Besi) M2
69 Kayu Bakar M3 M.070
70 Kayu Bekisting M3 M.180
71 Kayu Bulat Ø 6 - 10 cm panjang 4 m Btg
72 Keramik 20 x 20 cm setara merk Mulia Bh
73 Keramik 20 x 20 cm setara merk Roman Bh
74 Keramik 20 x 25 cm setara merk Mulia Bh
75 Keramik 30 x 30 cm Putih setara merk Mulia Bh
76 Keramik 30 x 30 cm setara merk Roman Bh
77 Keramik 40 x 40 cm setara merk Roman Bh
78 Klam Pipa Listrik Bungkus
79 Kunci Gembok + Plat (Besar) Set
80 Kunci Tanam setara merk Kodai Bh
81 Kunci Tanam setara merk SES Bh
82 Lampu Pijar 25 watt merk Philips Bh
83 Lampu SL 18 watt merk Philips Bh
84 Lampu TL 20 watt merk Phillips Lengkap Set
85 Lem Isarplast Kg
86 Lem Kayu merk Fox Kg
87 List Profil Gipsum M'
88 List Profil Kayu 4 Cm M'
89 MCB merk Elitech Buah
90 Minyak Bakar / Minyak Tanah Ltr M.065
91 Minyak Cat / Thinner A Ltr
92 Minyak Cat / Thinner B Ltr
93 Minyak Cat Biasa (600 ml) Btl
94 Minyak Cat merk Super Ltr
95 Minyak Pelumas (SAE 30) Ltr M.185
96 Moulding Lanan M3
97 Moulding Lanan (Lebar 10 Cm) Keping
98 Neoloy based Neoweb Geocell 330-150 Type C M2
99 Paking Pipa Karet (3 mm) Bh
100 Paku Atap Genteng Metal Kg
101 Paku Jembatan Kg M.166
102 Paku Kayu ( 1 1/4" - 1,5") Kg
103 Paku Kayu (≤ 1") Kg
104 Paku Kayu (2") Kg
105 Paku Kayu (2,5" - 5") Kg
106 Paku Plywood Kg
107 Paku Seng Kg
108 Paku Sirap Kg
109 Paku Ulin (2,5" - 5") Kg
110 Paku Ulin (≤ 2") Kg
111 Papan Bekisting M3
112 Papan Kayu Bouwplank M3
113 Pasangan Instalasi Listrik (Rumah Beton) Bh
114 Pasangan Instalasi Listrik (Rumah Kayu) Bh
115 Paving Block Bh
116 Pipa Galvanis Ø 2" panjang 4 m Btg
117 Pipa Galvanis Ø 3" panjang 6 m Btg
118 Pipa Galvanis Ø 4" panjang 6 m Btg
119 Pipa Galvanis Ø 6" panjang 6 m Btg
120 Plafond Gipsum (1,20 m x 2,40 m) Lbr
121 Plafond Kalsiboard (1,20 m x 2,40 m) Lbr
122 Plamur Tembok setara merk RJ Kg
123 Plastik Cor M2
124 Plywood / Triplek (12 mm) Lbr
125 Plywood / Triplek (3 mm) Lbr
126 Plywood / Triplek (5 mm) Lbr
127 Plywood / Triplek (9 mm) Lbr
128 Pompa Air Jet Pump setara merk Panasonic 125 w Unit
129 Pompa Air Jet Pump setara merk Panasonic 200 w Unit
130 Premium (Bensin) Ltr M.184
131 Rangka Plafond Gipsum M2
132 Saklar Ganda setara merk Broco Bh
133 Saklar Tunggal setara merk Broco Bh
134 Selang Fleksibel (Karet) Ø 4" M'
135 Selotif Pipa merk Onda Buah
136 Semen Putih 50 kg Kg
137 Seng Bubungan Plat BJLS 30, Lebar 30 cm M'
138 Seng Bubungan Plat BJLS 30, Lebar 40 cm M'
139 Seng Gelombang Kecil BJLS 30 Lbr
140 Seng Plat Besar Biasa BJLS 30 Lbr
141 Solar Ltr M.183
142 Spring Knife setara merk Subur Bh
143 Stop Kontak setara merk Broco Bh
144 Tangki Air 1.200 ltr setara merk Grand Bh
145 Tangki Air 2.200 ltr setara merk Grand Bh
146 Teer / Residu Ltr
147 Teralis Besi M2
148 Terminal Kabel dan MCB 6 A Bh
149 Thermoplastic Kg
150 Wiremesh M 8 Kg

Catatan :
- Harga Setempat sudah termasuk Pungutan Resmi Lainnya (sesuai daerah ybs);
- Harga Total sudah termasuk Pajak dan Keuntungan Pelaksana;
- Harga Satuan ini bukan Harga Mutlak yang dijadikan pedoman pengadaan barang dan jasa pemerintah sesuai
ketentuan peraturan perundang-undangan;
- Untuk Lokasi yang sulit ditempuh lewat jalan darat dan jauh dari pinggir sungai perlu ditambah dengan
Ongkos Angkut sesuai jauh lokasi atau jarak tempuh angkutan (darat/sungai).

Keterangan :
Regional I : Kecamatan Murung

Regional II : Kecamatan Tanah Siang


Kecamatan Tanah Siang Selatan
Kecamatan Laung Tuhup
Kecamatan Barito Tuhup Raya

Regional III : Kecamatan Permata Intan


Kecamatan Sei Babuat

Regional IV : Kecamatan Sumber Barito


Kecamatan U'ut Murung
Kecamatan Seribu Riam

- Harga Bahan Pabrikasi dihitung Harga Pabrik + Ongkos Kirim + Pajak PPN dan Keuntungan Pelaksana.

EKERJAAN UMUM KAB. MURUNG RAYA TA. 2010

D. UPAH

No. JENIS KEAHLIAN SAT. KODE

1 2 3 4

1 Mandor /Hari L.061


2 Mekanik /Hari L.071
3 Kepala Tukang (Batu, Besi, Kayu, Cat, Gali ) /Hari L.073
4 Tukang (Batu, Besi, Kayu, Cat, Gali ) /Hari L.079
5 Pekerja / Buruh Semi Terlatih /Hari L.103
6 Operator Terlatih /Hari L.081
7 Operator Kurang Terlatih / Pembantu Operator /Hari L.082
8 Sopir Terlatih /Hari L.091
9 Pembantu Sopir /Hari L.099

Keterangan :
Regional I : Kecamatan Murung

Regional II : Kecamatan Tanah Siang


Kecamatan Tanah Siang Selatan
Kecamatan Laung Tuhup
Kecamatan Barito Tuhup Raya
Regional III : Kecamatan Permata Intan
Kecamatan Sei Babuat

Regional IV : Kecamatan Sumber Barito


Kecamatan U'ut Murung
Kecamatan Seribu Riam
REGIONAL
REGION I REGION II REGION III REGION IV
Kec. Tanah Siang Kec. Sumber Barito
Harga Dasar Kec. Laung Tuhup Kec. Permata Intan Kec. U'ut Murung
Kec. Murung KET.
(Rp.) Kec. Barito Tuhup Raya Kec. Sei Babuat Kec. Seribu Riam
Kec. Tanah Siang Selatan
Total Total Total Total
(Rp.) (Rp.) (Rp.) (Rp.)
(5) (6) (7) (8) (9) (10)

90,000.00 112,500.00 117,000.00 121,500.00 126,000.00


10,000.00 12,500.00 13,000.00 13,500.00 14,000.00
6,000.00 7,500.00 7,800.00 8,100.00 8,400.00
178,000.00 222,500.00 231,400.00 240,300.00 249,200.00
400,000.00 500,000.00 520,000.00 540,000.00 560,000.00
12,500.00 15,625.00 16,250.00 16,875.00 17,500.00
510,000.00 637,500.00 663,000.00 688,500.00 714,000.00
47,500.00 59,375.00 61,750.00 64,125.00 66,500.00
594,000.00 742,500.00 772,200.00 801,900.00 831,600.00
831,600.00 1,039,500.00 1,081,080.00 1,122,660.00 1,164,240.00
1,500.00 1,875.00 1,950.00 2,025.00 2,100.00 Lokal
- - - -
20,150.00 25,187.50 26,195.00 27,202.50 28,210.00
450,000.00 562,500.00 585,000.00 607,500.00 630,000.00
5,500.00 6,875.00 7,150.00 7,425.00 7,700.00 Lokal
1,100.00 1,375.00 1,430.00 1,485.00 1,540.00 Lokal
5,000.00 6,250.00 6,500.00 6,750.00 7,000.00
8,000.00 10,000.00 10,400.00 10,800.00 11,200.00
1,600,000.00 2,000,000.00 2,080,000.00 2,160,000.00 2,240,000.00
82,000.00 102,500.00 106,600.00 110,700.00 114,800.00
36,000.00 45,000.00 46,800.00 48,600.00 50,400.00
110,000.00 137,500.00 143,000.00 148,500.00 154,000.00
16,000.00 20,000.00 20,800.00 21,600.00 22,400.00
150,000.00 187,500.00 195,000.00 202,500.00 210,000.00
25,000.00 31,250.00 32,500.00 33,750.00 35,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
55,000.00 68,750.00 71,500.00 74,250.00 77,000.00
200,000.00 250,000.00 260,000.00 270,000.00 280,000.00
55,000.00 68,750.00 71,500.00 74,250.00 77,000.00
60,000.00 75,000.00 78,000.00 81,000.00 84,000.00
35,000.00 43,750.00 45,500.00 47,250.00 49,000.00
160,000.00 200,000.00 208,000.00 216,000.00 224,000.00
80,000.00 100,000.00 104,000.00 108,000.00 112,000.00
85,000.00 106,250.00 110,500.00 114,750.00 119,000.00
3,000,000.00 3,750,000.00 3,900,000.00 4,050,000.00 4,200,000.00
300,000.00 375,000.00 390,000.00 405,000.00 420,000.00
10,000.00 12,500.00 13,000.00 13,500.00 14,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
15,000.00 18,750.00 19,500.00 20,250.00 21,000.00
40,000.00 50,000.00 52,000.00 54,000.00 56,000.00
275,000.00 343,750.00 357,500.00 371,250.00 385,000.00
15,000.00 18,750.00 19,500.00 20,250.00 21,000.00
25,000.00 31,250.00 32,500.00 33,750.00 35,000.00
45,000.00 56,250.00 58,500.00 60,750.00 63,000.00
23,750.00 29,687.50 30,875.00 32,062.50 33,250.00
38,000.00 47,500.00 49,400.00 51,300.00 53,200.00
35,000.00 43,750.00 45,500.00 47,250.00 49,000.00
15,000.00 18,750.00 19,500.00 20,250.00 21,000.00
20,000.00 25,000.00 26,000.00 27,000.00 28,000.00
10,000.00 12,500.00 13,000.00 13,500.00 14,000.00
60,000.00 75,000.00 78,000.00 81,000.00 84,000.00
15,000.00 18,750.00 19,500.00 20,250.00 21,000.00
10,000.00 12,500.00 13,000.00 13,500.00 14,000.00
15,000.00 18,750.00 19,500.00 20,250.00 21,000.00
10,000.00 12,500.00 13,000.00 13,500.00 14,000.00
17,850.00 22,312.50 23,205.00 24,097.50 24,990.00
119,000.00 148,750.00 154,700.00 160,650.00 166,600.00
135,000.00 168,750.00 175,500.00 182,250.00 189,000.00
150,000.00 187,500.00 195,000.00 202,500.00 210,000.00
50,000.00 62,500.00 65,000.00 67,500.00 70,000.00
15,000.00 18,750.00 19,500.00 20,250.00 21,000.00
2,000.00 2,500.00 2,600.00 2,700.00 2,800.00
2,500.00 3,125.00 3,250.00 3,375.00 3,500.00
25,000.00 31,250.00 32,500.00 33,750.00 35,000.00
45,000.00 56,250.00 58,500.00 60,750.00 63,000.00
17,500.00 21,875.00 22,750.00 23,625.00 24,500.00
125,000.00 156,250.00 162,500.00 168,750.00 175,000.00
25,000.00 31,250.00 32,500.00 33,750.00 35,000.00
118,800.00 148,500.00 154,440.00 160,380.00 166,320.00 Lokal
772,200.00 965,250.00 1,003,860.00 1,042,470.00 1,081,080.00 Lokal
9,500.00 11,875.00 12,350.00 12,825.00 13,300.00 Lokal
3,000.00 3,750.00 3,900.00 4,050.00 4,200.00
3,000.00 3,750.00 3,900.00 4,050.00 4,200.00
3,700.00 4,625.00 4,810.00 4,995.00 5,180.00
7,000.00 8,750.00 9,100.00 9,450.00 9,800.00
7,700.00 9,625.00 10,010.00 10,395.00 10,780.00
18,000.00 22,500.00 23,400.00 24,300.00 25,200.00
17,000.00 21,250.00 22,100.00 22,950.00 23,800.00
50,000.00 62,500.00 65,000.00 67,500.00 70,000.00
149,000.00 186,250.00 193,700.00 201,150.00 208,600.00
335,000.00 418,750.00 435,500.00 452,250.00 469,000.00
7,000.00 8,750.00 9,100.00 9,450.00 9,800.00
42,000.00 52,500.00 54,600.00 56,700.00 58,800.00
110,000.00 137,500.00 143,000.00 148,500.00 154,000.00
80,000.00 100,000.00 104,000.00 108,000.00 112,000.00
45,000.00 56,250.00 58,500.00 60,750.00 63,000.00
60,000.00 75,000.00 78,000.00 81,000.00 84,000.00
5,000.00 6,250.00 6,500.00 6,750.00 7,000.00 Lokal
25,000.00 31,250.00 32,500.00 33,750.00 35,000.00
21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
35,000.00 43,750.00 45,500.00 47,250.00 49,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
20,000.00 25,000.00 26,000.00 27,000.00 28,000.00
60,000.00 75,000.00 78,000.00 81,000.00 84,000.00
35,000.00 43,750.00 45,500.00 47,250.00 49,000.00
2,357,000.00 2,946,250.00 3,064,100.00 3,181,950.00 3,299,800.00 Lokal
19,000.00 23,750.00 24,700.00 25,650.00 26,600.00 Lokal
241,000.00 301,250.00 313,300.00 325,350.00 337,400.00
18,000.00 22,500.00 23,400.00 24,300.00 25,200.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
25,000.00 31,250.00 32,500.00 33,750.00 35,000.00
25,000.00 31,250.00 32,500.00 33,750.00 35,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
30,000.00 37,500.00 39,000.00 40,500.00 42,000.00
1,550,000.00 1,937,500.00 2,015,000.00 2,092,500.00 2,170,000.00 Lokal
1,550,000.00 1,937,500.00 2,015,000.00 2,092,500.00 2,170,000.00 Lokal
95,000.00 118,750.00 123,500.00 128,250.00 133,000.00
75,000.00 93,750.00 97,500.00 101,250.00 105,000.00
4,000.00 5,000.00 5,200.00 5,400.00 5,600.00 Lokal
365,000.00 456,250.00 474,500.00 492,750.00 511,000.00
558,000.00 697,500.00 725,400.00 753,300.00 781,200.00
1,020,000.00 1,275,000.00 1,326,000.00 1,377,000.00 1,428,000.00
1,650,000.00 2,062,500.00 2,145,000.00 2,227,500.00 2,310,000.00
98,000.00 122,500.00 127,400.00 132,300.00 137,200.00
85,000.00 106,250.00 110,500.00 114,750.00 119,000.00
25,000.00 31,250.00 32,500.00 33,750.00 35,000.00
6,000.00 7,500.00 7,800.00 8,100.00 8,400.00
194,000.00 242,500.00 252,200.00 261,900.00 271,600.00
75,000.00 93,750.00 97,500.00 101,250.00 105,000.00
125,000.00 156,250.00 162,500.00 168,750.00 175,000.00
175,000.00 218,750.00 227,500.00 236,250.00 245,000.00
475,000.00 593,750.00 617,500.00 641,250.00 665,000.00
800,000.00 1,000,000.00 1,040,000.00 1,080,000.00 1,120,000.00
23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
131,000.00 163,750.00 170,300.00 176,850.00 183,400.00
20,000.00 25,000.00 26,000.00 27,000.00 28,000.00
20,000.00 25,000.00 26,000.00 27,000.00 28,000.00
891,000.00 1,113,750.00 1,158,300.00 1,202,850.00 1,247,400.00
10,000.00 12,500.00 13,000.00 13,500.00 14,000.00
5,000.00 6,250.00 6,500.00 6,750.00 7,000.00
15,000.00 18,750.00 19,500.00 20,250.00 21,000.00
20,000.00 25,000.00 26,000.00 27,000.00 28,000.00
45,000.00 56,250.00 58,500.00 60,750.00 63,000.00
45,000.00 56,250.00 58,500.00 60,750.00 63,000.00
108,108.00 135,135.00 140,540.40 145,945.80 151,351.20
5,000.00 6,250.00 6,500.00 6,750.00 7,000.00
20,000.00 25,000.00 26,000.00 27,000.00 28,000.00
1,450,000.00 1,812,500.00 1,885,000.00 1,957,500.00 2,030,000.00
2,850,000.00 3,562,500.00 3,705,000.00 3,847,500.00 3,990,000.00
8,500.00 10,625.00 11,050.00 11,475.00 11,900.00
450,000.00 562,500.00 585,000.00 607,500.00 630,000.00
77,200.00 96,500.00 100,360.00 104,220.00 108,080.00
35,000.00 43,750.00 45,500.00 47,250.00 49,000.00
12,650.00 15,812.50 16,445.00 17,077.50 17,710.00

pemerintah sesuai
REGIONAL
REGION I REGION II REGION III REGION IV
Kec. Tanah Siang Kec. Sumber Barito
Harga Dasar Kec. Barito Tuhup Raya Kec. Sei Babuat Kec. U'ut Murung
Kec. Murung KET.
(Rp.) Kec. Laung Tuhup Kec. Permata Intan Kec. Seribu Riam
Kec. Tanah Siang Selatan
Total Total Total Total
(Rp.) (Rp.) (Rp.) (Rp.)
5 6 7 8 9 10

115,500.00 144,375.00 150,150.00 155,925.00 161,700.00


111,100.00 138,875.00 144,430.00 149,985.00 155,540.00
112,750.00 140,937.50 146,575.00 152,212.50 157,850.00
107,625.00 134,531.25 139,912.50 145,293.75 150,675.00
105,575.00 131,968.75 137,247.50 142,526.25 147,805.00
300,000.00 375,000.00 390,000.00 405,000.00 420,000.00
120,000.00 150,000.00 156,000.00 162,000.00 168,000.00
150,000.00 187,500.00 195,000.00 202,500.00 210,000.00
107,625.00 134,531.25 139,912.50 145,293.75 150,675.00

You might also like