Culture Documents
2 Position of door frames a) Ensure door frames are erected at the correct location SIB/ICL/BWDF
@ @ o
3 Position of brickwall a) Ensure brickwalls are erected correctly as per setting SIB/ICL/BWDF
out confirmed in item (1) @ @ o
5 Verticality of brickwall a) Brickwall are laid vertically and cornerings are vertical @ @ o SIB/ICL/BWDF
6 Brickwall reinforcement & other a) Exmet to be provided every forth course of brick starting @ @ o SIB/ICL/BWDF
accessories from the second course
7 Brick Joints a) Ensure all joints between bricks are properly filled with @ @ o SIB/ICL/BWDF
cement mortar.
SUN INTEGRATED BUILDERS SDN. BHD.
Document Ref. SIB/ITP/BWDF
INSPECTION AND TEST PLAN Revision No. 0
Effective Date 15-Sep-08
BRICKWORK & INSTALLATION OF DOOR FRAMES Page No. 2 of 2
8 Opening and services at a) Ensure all M&E services and openings are installed as per @ @ o SIB/ICL/BWDF
brickwall construction drawings.
9 Unwanted materials a) All loose and foreign material are to be removed from @ @ o SIB/ICL/BWDF
the erected brickwall.
@ - prepared / checked by
# - confirmed by
o - approved by Name Name
Date Date