T5HP-T5C-XXXX-MIN-EL-000022/ 00088 7 December 2022

Contract No, PK-AF Tarbela 4th-125546-CW-RFB

FAO: Mr. Hu Binhai


Contractor’s Representative
M/S HEI-HEC JV

Subject: Minutes of Meeting on Long Standing issues of EM Contract

References: Nil

Dear Sir,
With reference to the above subject, please find attached the “Minutes of Meeting on Long
Standing issues of EM Contract” for your further necessary action and information.

Yours faithfully,

Mark Gill
Project Manager - T5C
T: +44 1273 365174 M: 0311 437 9209
Mark.gill@mottmac.com

Enclosure: Minutes of Meeting

Tarbela 5 Consultants: Mott MacDonald Limited, in association with MM Pakistan (Pvt.) Limited (M.Rafi - CCC)
Site Office, Tarbela Dam Project, Ghazi, Haripur, KPK T: 92-938-281065 Design Office: 203-Upper Mall, Lahore T: +92-42-37534656-60
Mott MacDonald, Victory House, Trafalgar Place, Brighton BN1 4FY, UK T: 01273 365000 Branch Office: PTET Tele House, 6 Floor, Mauve Area, Islamabad G10/4
th

Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered Office: Mott MacDonald House, 8-10 Sydenham Rd, Croydon CR0 2EE, UK Page 1 of 5
T5HP-T5C-XXXX-MIN-EL-000022/ 00088 Minutes of Meeting on Long Standing issues of EM Contract

Employer: WAPDA

Minutes of Meeting Tarbela 5th Extension Project

Tarbela, Haripur, KPK

Contract: T5HPP EM Works

Subject: Long Outstanding issues of EM Contracts

Location: Employer Office Date:02- 12- 2022

Attendees: Name Party Name Party

Khair Muhammad PD T5HPP Mark Gill T5C

Aziz Ullah Soomro Employer Muhammad Rafi T5C

Abul Kalam Employer Imran Khan T5C

Faisal Hayat Employer Mushtaq Ahmed T5C (Online)

Iqrar Employer Ahmed Butt T5C (Online)

Taha Employer Ehsan Khokhar T5C (Online)

Asif Shah Employer Shahzad Shahid T5C (Online)

Recorded: Muhammad Rafi/Imran Khan

Item Topic Action / Notes

1 Meeting Agenda: Employer / Project


Manager
1. Constitution to DAAB
2. Standards
3. Transportation Documents
4. Staff CVs
5. Approval of Sub-Contractor
6. 11 kV Power Supply
7. Mobilization of T5C Design Team at Site
8. Change Order for Program
9. FATs and how to facilitate them
10. Change Order for 11 kV Power Supply
11. Change Order for interconnector switchgear
12. 11 kV line Powerhouse to Switchyard
13. Warehouse Handing over
14. MIV Crane Capacity
15. AOB

Tarbela 5 Consultants: Mott MacDonald Limited, in association with MM Pakistan (Pvt.) Limited (M.Rafi - CCC)
Site Office, Tarbela Dam Project, Ghazi, Haripur, KPK T: 92-938-281065 Design Office: 203-Upper Mall, Lahore T: +92-42-37534656-60
Mott MacDonald, Victory House, Trafalgar Place, Brighton BN1 4FY, UK T: 01273 365000 Branch Office: PTET Tele House, 6 Floor, Mauve Area, Islamabad G10/4
th

Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered Office: Mott MacDonald House, 8-10 Sydenham Rd, Croydon CR0 2EE, UK Page 2 of 5
T5HP-T5C-XXXX-MIN-EL-000022/ 00088 Minutes of Meeting on Long Standing issues of EM Contract

Item Topic Action / Notes

1. Constitution of DB Contractor

PM informed that HEI has been reminded for nomination of his DB


member. In response, HEI replied that they are still searching for suitable
candidates and will submit their CVs soon.
HEI are reminded again to expedite the process.

2. Standards Contractor

HEI are reminded again to submit the remaining standards used in


T5HPP.

3. Transportation Documents Contractor

PM informed that HEI submitted revised transportation documents on 19


October 2022. The revision was reviewed, and HEI was requested to fulfil
all the necessary requirements, to resolve this matter and conclude the
review of transportation documents.

4. Senior Staff CVs Contractor

PM informed that as there is not fix criterion provided for the Contractor’s
staff provided in Organization Chart in the Contract.
It was agreed that performance evaluation of Senior Staff will be carried
out and upon the performance of the staff, matter will be discussed with
their high-ups. Either to replace as per Contract, the personnel having
poor performance or to provide with the relevant assistant staff to them to
complete the job.

5. Approval of Sub-Contractors Contractor


The Client agreed with the minutes of meeting held on 24 October 2022 in
Engineer Office with HEI and agreed that the Project Manager evaluate and
act on behalf of the Employer regarding approval of Subcontractors.

It was also discussed and noted that the subcontracting limit in PQ


Document does not apply to the Contract.

6. 11 kV Power Supply Contractor

Layout of 11kV T4-T5 will be supplied by HEI for their construction part.
It is agreed that the constructed line may be handed over or dismantled
as desired by the Employer.

PCCCL D/C 11 kV Line will be used for backup for T5 Powerhouse.


Any upgrade of PCCCL Line will be rectified in accordance with the FYI
requirements of PESCO.

Proper access for 11 kV permanent supply will be provided by the civil


Contractor for future rectification. FYI

Tarbela 5 Consultants: Mott MacDonald Limited, in association with MM Pakistan (Pvt.) Limited (M.Rafi - CCC)
Site Office, Tarbela Dam Project, Ghazi, Haripur, KPK T: 92-938-281065 Design Office: 203-Upper Mall, Lahore T: +92-42-37534656-60
Mott MacDonald, Victory House, Trafalgar Place, Brighton BN1 4FY, UK T: 01273 365000 Branch Office: PTET Tele House, 6 Floor, Mauve Area, Islamabad G10/4
th

Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered Office: Mott MacDonald House, 8-10 Sydenham Rd, Croydon CR0 2EE, UK Page 3 of 5
T5HP-T5C-XXXX-MIN-EL-000022/ 00088 Minutes of Meeting on Long Standing issues of EM Contract

Item Topic Action / Notes

7. Mobilization of T5C Design Team at Site Contractor

Design team will have an intermittent input on site.

HEI team is expected to be mobilized by 2nd quarter of 2023.

In 2nd Quarter, CRE E&M, T5C, is expected to be mobilized with


associates.

8. Change Order for Program CO-3 Contractor

A request for Change Proposal has been sent to HEI to submit revised
program along with estimate by 16 December 2022 for Project Manager
review and Approval.

Within 7 days, the Project Manager will undergo 2nd round and further
finalization of Program.

After finalization, coordinated Construction schedule will be prepared for


both, PCCCL and HEI, and Change Order will be issued accordingly.

9. Factory Acceptance Tests (FATs) and how to facilitate them Contractor

The team mobilized for Model test has already been struck in China due
to quarantine protocols.

A local Subconsultant in China, Moody (Shanghai) Consulting Co Ltd (aka


Intertek), is being hired for future FATs and will be coordinated
accordingly.

Current experience in China reinforces to use Moody.

10.Change Order 11 kV Power Supply-01 Contractor

11kV Power Cables Overhead will be used instead of Underground from


Powerhouse to Switchyard.

The Employer agreed with the proposal of the Project Manager.

11.Change Order for Interconnector CO-02 Contractor

The WAPDA had sent signed “Request for Change Proposal” to the
Project Manager to formally forward it to the Contractor.

Tarbela 5 Consultants: Mott MacDonald Limited, in association with MM Pakistan (Pvt.) Limited (M.Rafi - CCC)
Site Office, Tarbela Dam Project, Ghazi, Haripur, KPK T: 92-938-281065 Design Office: 203-Upper Mall, Lahore T: +92-42-37534656-60
Mott MacDonald, Victory House, Trafalgar Place, Brighton BN1 4FY, UK T: 01273 365000 Branch Office: PTET Tele House, 6 Floor, Mauve Area, Islamabad G10/4
th

Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered Office: Mott MacDonald House, 8-10 Sydenham Rd, Croydon CR0 2EE, UK Page 4 of 5
T5HP-T5C-XXXX-MIN-EL-000022/ 00088 Minutes of Meeting on Long Standing issues of EM Contract

Item Topic Action / Notes

The Project Manager has forwarded the same to the Contractor and
request to submit estimate within 14 days of the request.

12. 11kV line Powerhouse to Switchyard Contractor

In continuation of item 10, For crossing the river crossing, two 132 kV
poles will be used. For remaining line,11 kV towers will be erected.

WAPDA agreed to the proposal and will submit response in one week.

As overhead line is proposed instead of Underground, HEI will be


requested to submit a net estimate (deleting the cost of underground
cable system and adding the overhead line in Price Schedule) for change
order.

13. Warehouse WAPDA/Contractor

A meeting will be convened in between WAPDA and HEI regarding


acquiring of warehouse.

HEI will request for the allocation of Warehouse

14. MIV crane Capacity WAPDA/Contractor

WAPDA agreed that HEI will propose the Crane capacity.


Project Manager supports this position.

Now, Mr Khurram Baig, Director Mechanical WAPDA, on his return from


China, will discuss the matter.

15. Any Other Business (AOB) Employer / T5C /


Contractor
A separate meeting will be held between Mr Taha (Employer) and Mr.
Shahzad (T5C) regarding construction of relay room.

HEI is requested to submit hard copies of each correspondence to the


Employer.

Next Meeting: As and when required

Distribution: Attendees plus T5C Design Team

Tarbela 5 Consultants: Mott MacDonald Limited, in association with MM Pakistan (Pvt.) Limited (M.Rafi - CCC)
Site Office, Tarbela Dam Project, Ghazi, Haripur, KPK T: 92-938-281065 Design Office: 203-Upper Mall, Lahore T: +92-42-37534656-60
Mott MacDonald, Victory House, Trafalgar Place, Brighton BN1 4FY, UK T: 01273 365000 Branch Office: PTET Tele House, 6 Floor, Mauve Area, Islamabad G10/4
th

Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered Office: Mott MacDonald House, 8-10 Sydenham Rd, Croydon CR0 2EE, UK Page 5 of 5