Professional Documents
Culture Documents
Change Description:
To activate bypass switch LSLL 3021 for T-302 in Equipment Rack Room and HS9020 Group Maintenance Enable Key Switch
in TCR to lower down inventory in T-302 as much as possible by ITT from T-302 into T-301 via shipment pump P301 A/B/C until
pump cavitate
Reason For Change / Justification: (Initiator to attach P&ID for the proposed change, cost estimate, red line drawing, etc)
Approved by:
Initiated by:
(Section Head)
Name: Muhammad Syukri Abdul Aziz Name:
Position & Department : TCR Operation Terminals Department:
Date: 05/09/2011 Date:
Name:
Date:
Name: Name:
Date: Date:
Section 5 : Approval for the completed changes to be put into service/use or started up.
We have carefully reviewed and agreed that the completed change can be put into use/service or started up
Name: Name:
Date: Date:
MOC FORM (KTSB/MOC-01 / R6 - 16 Aug 2010) Page 1 of 4
PROJECT/MAINTENANCE
ASSESSMENT FOR CHANGE CHECKLIST
PROJECT/MAINTENANCE YES NO
5 Does the change affect current alarm system or any safety interlocks?
12 Is there any change to an existing structure (i.e. pipe racks, platform, etc)
13 Does this change add any new equipment to the loading/unloading facilities
19 Other issues:
I have reviewed this checklist and confirmed that this change shall require the above items.
I have reviewed the PCA package and confirmed that all items identified in the above checlist have been
completed and properly supported with related documentation.
Engineering/Maintenance Superintendent
Name::
PCA FORM Page 2 of 4
OPERATIONS
ASSESSMENT FOR CHANGE CHECKLIST
OPERATIONS YES NO
7 Does this change require critical spare parts items to be kept at Operations
Store?
8 Does this change require provision of additional lighting for night operation?
10 Other issues:
I have reviewed this checklist and confirmed that this change shall require the above items.
I have reviewed the PCA package and confirmed that all items identified in the above checlist have been
completed and properly supported with related documentation.
Operations Superintendent
Signature: _____________________
Name::
Date :
PROJECT/MOC TITLE:
DESCRIPTIONS ACTION?
2 If yes, has the Chemical Use Request/Approval Form (and the rest of
HSE - Chemical Management SOP) been completed and sent for approval?
7 Introduce a new respiratory hazard (dust, fume, mist, vapor, fibers, etc)?
2. SAFETY
3 Introduce any moving machinery hazards or pinch points that require guarding?
3. ENVIRONMENT
5 If yes to above, have waste profiles been developed e.g dispose arrangement
3 Does the change impact access to equipment for fire fighting or spill cleanup?
4 Have Pre-Incident Planning (PIP) and/or spill cleanup plans been developed/updated?
6 Does the change create a need for additional fixed fire detection or
suppression equipment?
3 Introduce any new sources of ignition in the operating and surrounding areas?
6. HUMAN FACTORS
7. PROCEDURES
5 Require any new permit or approval from regulatory agencies (BOMBA, DOSH, DOE).
REMARKS
I have reviewed this checklist and confirmed that this change shall require the above items.
Signature: _____________________
Name::
Date :
Responsibility PROCESS FLOW Documents Process Description
HSE Manager
Oper Manager PCA Form - PCA Final Approval for Implementation
EMP Manager Final Approval section 4 EE shall review the PCA package with the PCA Approvers, and
EE for obtain final approval to proceed with implementation
Implementation
Implementation
EE RFQ EE executes and completes the PCA package
Contractor Execution & Site RFS EE, Contractors, Area Owner shall jointly conduct site walk down
Area Owner Walk Down ITB upon completion of change execution to verify that work has been
Drawings done according to the original scope of work.
PCSR Any deviation shall be identified in a punch list.