Professional Documents
Culture Documents
PROJECT DETAILS:
Page | 1
TASK/ PROJECT DETAILS: Installation of facade steel using a tower crane, a scissor lift under 11m.
NOTE:
1/ For any hot works on site including, Welding, Grinding and Oxy Cutting refer to Hot Works
2/ For use of powered and non-powered tools and equipment refer to Use of Unpowered hand tools,
Powered tools and equipment HIGH RISK WORK MATRIX
3/ For
RISK OF Manual handlingHEIGHT
FALLS FROM refer to Manual Handling
WORK ON A DEMOLITION OF LOAD-BEARING
GREATER THEN 2 METRES TELECOMMUNICATIONS TOWER STRUCTURE
4/ For use of hazardous Materials on site refer to -Use of Hazardous Materials Chemicals
WORK LIKELY TO INVOLVE TEMPORARY LOAD-BEARING WORK IN CONFINED SPACES
DISTURBING ASBESTOS SUPPORT STRUCTURES
WORK IN OR NEAR SHAFT OR USE OF EXPLOSIVES WORK ON OR NEAR PRESSURISED
TRENCH WITH AN EXCAVATED GAS PIPES
HAZARDOUS MATERIALS:
DEPTH GREATER THAN Adjuvate
1.5M ORCongrout,
A All Fasteners chemical anchor, Diesel fuel for the EWPs
TUNNEL For information on Hazardous Materials including use, clean up and first aid refer to SDS provided.
WORK ON OR NEAR CHEMICAL, WORK ON OR NEAR ENERGISED WORK IN AN AREA WITH
CONTAMINATED, FUEL OR ELECTRICAL INSTALLATIONS OR FLAMMABLE ATMOSPHERE
REFRIGERANT LINES SERVICES
WORK WITH TILT
COMMUNICATION UP OR PRECAST
METHOD USED BETWEEN PLANT WORK AND ON, IN OR ADJACENT
WORKERS: Two-way TO A will be used
radios for
WORK IN AN AREAbetween
communications WITH POWERED
the Crane, EWPs
CONCRETE
and ground ROAD,
staff as needed – positive communications – eye RAILWAY,
contact and handSHIPPING
signals. LANE OR MOBILE PLANT
OTHER TRAFFIC CORRIDOR IN USE BY
TRAFFIC OTHER THAN PEDESTRIANS
WORK IN OR AROUND AREAS WITH DRIVING WORK WORK IN OR NEAR WATER OR
ARTIFICAL EXTREME OTHER LIQUID THAT INVOLVES A
Page |2
TEMPERRATURES RISK OF DROWNING
PERSONS CONSULTED IN PRODUCING THIS QUALIFICATIONS/ VOC’s REQUIRED TO PLANT REQUIRED TO CARRY OUT THE
SWMS CARRY OUT THE WORK WORK
HRW DG ticket for slinging loads and directing crane Maeda 355 crane supplied by Dunsteel
HRW WP ticket for operation of the boom lift/ Tower Crane supplied by RICHARD
scissor lift over 11m CROOKS CONSTRUCTION
Page | 3
WHS Act 2011 Working at height, Obtained from Hard hat
RCC
MEASURES IN PLACE TO ENSURE BEYOND CONSTRUCTIONS WHS policies and procedures, general and workplace induction training, toolbox
COMPLIANCE TO SWMS? meetings, SWMS provided to and discussed with worker(s) at workplace and signed-off, ongoing workplace
supervision by experienced Supervisor.
Any reviews or amendments to this SWMS will be recorded below, all staff must then be re briefed and resign onto the latest revision
REVISIONS/ AMMENDEMENTS
Page | 5
HIGH RISK WORK WORK TASK ASSOCIATED/ IDENTIFIED HAZARDS RISK/ HAZARD CONTROLS
Page | 6
Work in an area with powered Use of the Tower crane Machine failure RICHARD CROOKS operator is to
mobile plant. (Supplied by RICHARD perform the appropriate prestart checks
CROOKS)
for the installation of the VCL
Structural steel.
Only RICHARD CROOKS authorised personal
RICHARD CROOKS will supply Unauthorised personal operating the crane are to operate and direct the crane
all relevant documents risk
assessments and SWMS for
the operation of their crane.
RICHARD CROOKS crane crew are to
ensure their lifting gear is within test date
Lifting gear failure and suitably rated to perform lifts
Page | 7
Crane tip over due to overloading
Page | 8
Qualified Operator.
Page | 9
hazards.
Overhead Obstructions.
Page | 10
Boom Lift
HIGH RISK WORK WORK TASK ASSOCIATED/ IDENTIFIED HAZARDS RISK/ HAZARD CONTROLS
Work in an area with powered Use of Maeda crane (Supplied Crane Condition and Fit for Purpose.
mobile plant. by Dunsteel) to install Daily checks of the Crane must be completed,
Structural steel, Façade Fins and logbook filled in at the beginning of the
and Purlins on West Side of shift or when first using the Crane for the Day,
VCL. refer to the operating manual on the crane
and comply with any manufacturers’
instructions and requirements.
Machine Failure.
Page | 11
If a fault is found, the Crane is to be tagged out
of service the defect or fault recorded in the
logbook, the key removed and reported to the
supervisor.
Page | 12
crane and manufacturer's instructions
Page | 13
Exclusion zones set up to control the lifting
area while using the Crane.
Page | 14
HIGH RISK WORK WORK TASK ASSOCIATED/ IDENTIFIED HAZARDS RISK/ HAZARD CONTROLS
- Work in an area Use of boom lifts Machine Failure. Daily checks of the Boom Lift must be
with powered (Supplied by completed, and logbook filled in at the
mobile plant. OUTRIGHT HIRE) to assist with beginning of the shift or when first using the
- Risk of falls from the placement Boom Lift for the day, refer to the operating
greater than 2 of the structural steel, manual on the Boom Lift and comply with any
metres. Installation of the fixings and manufacturer’s instructions and
releasing the lifting gear once in
requirements.
place
OUTRIGHT HIRE will supply all If a fault is found, the Boom Lift is to be
tagged out of service the defect or fault
relevant documents
recorded in the logbook, the key removed
for the Boom lifts. and reported to the supervisor.
Page | 16
Check ground conditions when setting up the
scissor Lift in the work area. Do not exceed the
gradeability of the Boom Lift.
Tip the Boom lift.
Maintain a safe distance from obstacles,
debris, drop offs, holes, depressions, ramps
and other hazards.
Page | 17
Lift malfunction or Entrapment. Refer to manufacturer's instructions for
rescue,
Page | 18
HIGH RISK WORK WORK TASK ASSOCIATED/ IDENTIFIED HAZARDS RISK/ HAZARD CONTROLS
Use Hazardous Risk of illness, Safety Data Sheet (SDS)are to be available for
Chemicals, Chemical all hazardous chemicals. Workers are to be
Anchor, diesel and trained and skilled in the safe use of
Congrout hazardous chemicals and access by all
workers to register.
Page | 19
All personnel/ workers required to carry out this work need to be listed below.
By signing this SWMS each person declares that they have read or been read, briefed, understand and have had an opportunity to
provide input into this SWMS and understand their responsibilities and requirements to complete the work.
PERSONNEL/ WORKER SIGN OFF
Page | 20
Page | 21