You are on page 1of 7

Client: Site Acceptance Test Report for Protection Relay

Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9635
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-11
Date: 15-05-2023 Page 1 of 7

1. RELAY DATA :
MAKE : SCHNEIDER SERIAL NUMBER : 20120071
TYPE : SEPAM T82 PANEL REF : 3-1
CT Primary : 500 A CT SEC.CURRENT :1A
VT Primary : 3.3 KV VT Secondary : 110 V

2. GENERAL INSPECTION AND CHECKS:

Kind of check Remarks


OK
Check of transport damage

Visual check of external wiring OK

OK
Check of cubicle / relay earthing
OK
Check of supply voltage (DC)
OK
Check of settings
OK
Check of current transformer circuits

Check of voltage transformer circuits OK

OK
Secondary injection test
OK
Check of binary inputs

Check of binary output contacts OK

OK
Check of tripping circuits
OK
System time setting

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDYA
DATE: 15-05-2023 15-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report for Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9635
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-11
Date: 15-05-2023 Page 2 of 7

3. MEASUREMENTS :

3.1 CURRENT MEASUREMENT


CT RATIO : 500/1A

Current Injected Primary PRIMARY CURRENT MEASURED IN RELAY (A)


Phase in Secondary Current
(A) (A) L1 L2 L3
R 1.0 500 499.4 0 0
Y 1.0 500 0 499.9 0
B 1.0 500 0 0 499.7
R-Y-B 1.0 500 499.5 499.8 499.7

3.2 VOLTAGEMEASUREMENT
VT RATIO : 3.3kV/√3/110/√3

Voltage Primary VOLTAGE MEASUREMENT (kV)


Phase Injected in Voltage
Secondary(V) (kV) U1 U2 U3 U12 U23 U31
RN 63.51 1.905 1.904 0 0 1.904 0 1.904
YN 63.51 1.905 0 1.904 0 1.904 1.904 0
BN 63.51 1.905 0 0 1.905 0 1.905 1.905
RY 110 3.3 1.904 1.904 0 3.299 1.904 1.904
YB 110 3.3 0 1.904 1.905 1.905 3.299 1.905
BR 110 3.3 1.904 0 1.905 1.904 1.905 3.299
R-Y-B 110 3.3 1.904 1.904 1.905 3.299 3.299 3.298

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDYA
DATE: 15-05-2023 15-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report for Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9635
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-11
Date: 15-05-2023 Page 3 of 7

3.3 POWER MEASUREMENTS:

PowerMeasured
Voltage
Current Injected Angle [MW] [MVAr]
Injected PF
Expected Value Actual Value Expected Value Actual Value
63.5 V - 3 Ph 1 A - 3 Ph 0° 2.857 2.856 0 0 0.99
63.5 V - 3 Ph 1 A - 3 Ph 45° 2.020 2.022 -2.020 -2.017 0.70
63.5 V - 3 Ph 1 A - 3 Ph 90° 0 0 -2.857 -2.856 0
63.5 V - 3 Ph 1 A - 3 Ph 135° -2.020 -2.017 -2.020 -2.022 -.0.70
63.5 V - 3 Ph 1 A - 3 Ph 180° -2.857 -2.856 0 0 -0.99
63.5 V - 3 Ph 1 A - 3 Ph 225° -2.020 -2.022 2.020 2.017 -0.70
63.5 V - 3 Ph 1 A - 3 Ph 270° 0 0 2.857 2.856 0
63.5 V - 3 Ph 1 A - 3 Ph 315° 2.020 2.017 2.020 2.022 0.70
63.5 V - 3 Ph 1 A - 3 Ph 360° 2.857 2.856 0 0 0.99

4. Over Current - 51 : (3I>)


a) Pickup & Drop off : (3I>) Set: 0.60 A

Pick Up (A) Drop Off (A) DO/PU


Phase Set value (A) Ratio
Expected Operated Expected Operated Error (%)
R - ph 0.600 0.600 0.610 0.570 0.560 -3.365
Y - ph 0.600 0.600 0.605 0.570 0.560 -2.566
B - ph 0.600 0.600 0.605 0.570 0.560 -2.566

b) Curve Characteristic : IEC Very Inverse curve (3I>)


Set: 0.60 A TMS: 0.229 sec

Operating Time in (Sec) Operating Time in (Sec) Operating Time in (Sec)


Set 2*In set 5*In set 10*In set
Phase TMS
value Error Error Error
Expected Operated Expected Operated Expected Operated
(%) (%) (%)
R - ph 0.600 0.229 3.092 3.091 -0012 0.772 0.782 1.194 0.343 0.345 0.611

Y - ph 0.600 0.229 3.092 3.084 -0.023 0.772 0.774 0.262 0.343 0.351 2.30

B - ph 0.600 0.229 3.092 3.084 -0.026 0.772 0.784 1.439 0.343 0.348 1.31

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDYA
DATE: 15-05-2023 15-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report for Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9635
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-11
Date: 15-05-2023 Page 4 of 7

5. Over Current - 50 : (3I>>)


a) Pickup & Drop off : (3I>>) Set: 2.5 A
Pick Up (A) Drop Off (A) DO/PU
Phase Set value (A) Ratio
Expected Operated Expected Operated Error (%)
R - ph 2.50 2.50 2.513 2.37 2.324 -2.632

Y - ph 2.50 2.50 2.513 2.37 2.324 -2.632

B - ph 2.50 2.50 2.513 2.37 2.324 -2.632

b)Curve Characteristic : IEC Definite Time (3I>>) : Set: 2.5 A Time: 0.05 Sec

Injected current (A) Operating Time in (Sec) Error


Phase Set value (A) (ms)
1.25* In Expected Operated
R - ph 2.50 3.125 0.050 0.059 19.2

Y - ph 2.50 3.125 0.050 0.068 24.6

B - ph 2.50 3.125 0.050 0.068 36.2

6. OVER VOLTAGE PROTECTION

Pickup & Drop off : Set: 120% Vn=132.0V


Pick Up (V) Drop Off (V)
Phase Set value (V)
Expected Operated Expected Operated
RYB 132.00 132.00 132.15 125.39 127.99

Trip Test: Set: 120% Vn=132V Time: 1.00 Sec

Operating Time in (Sec) Error


Phase Set value (V) Injected voltage (V) (ms)
Expected Operated
RY - ph 132.00 135.00 1.00 1.018 17.500

YB - ph 132.00 135.00 1.00 1.009 9.00

BR - ph 132.00 135.00 1.00 1.025 25.00

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDYA
DATE: 15-05-2023 15-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report for Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9635
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-11
Date: 15-05-2023 Page 5 of 7

7. UNDER VOLTAGE PROTECTION

Pickup & Drop off : Stage-1> Set: 70% Vn=77V


Pick Up (V) Drop Off (V)
Phase Set value (V)
Expected Operated Expected Operated

RYB 77.00 77.00 76.900 78.80 79.498

Trip Test: Set: 70% Vn=77V Time: 3.00 Sec

Operating Time in (Sec) Error


Phase Set value (V) Injected voltage (V) (ms)
Expected Operated
RY - ph 77.00 72.74 3.00 3.018 17.50

YB - ph 77.00 72.74 3.00 3.012 12.10

BR - ph 77.00 72.74 3.00 3.026 26.10

8. UNDER VOLTAGE PROTECTION

Pickup & Drop off : Stage-2>> Set: 60% Vn=66V


Pick Up (V) Drop Off (V)
Phase Set value (V)
Expected Operated Expected Operated

RYB 66.00 66.00 65.989 69.28 68.067

Trip Test: Set: 60% Vn=66V Time: 2.00 Sec

Operating Time in (Sec) Error


Phase Set value (V) Injected voltage (V) (ms)
Expected Operated
RY - ph 66.00 62.35 2.00 2.008 8.00

YB - ph 66.00 62.35 2.00 2.018 18.10

BR - ph 66.00 62.35 2.00 2.018 18.00

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDYA
DATE: 15-05-2023 15-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report for Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9635
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-11
Date: 15-05-2023 Page 6 of 7

9. BINARY INPUT

S.N BI.No DESCRIPTION CHECKED


01 I101 CB CLOSED OK
02 I102 CB OPEND OK
03 I103 CB RACK IN OK
04 I104 CB RACK OUT OK
05 I105 ES CLOSED OK
06 I106 ES OPENED OK
07 I107 SELECTOR SWITCH IN SERVICE OK
08 I108 SELECTOR SWITCH IN TEST OK
09 I109 LOCKOUT RELAY OPERSTED OK
10 I110 TRIP CIRCUIT UNHEALTHY OK
11 I111 MCBs AC SUPPLY FAIL OK
12 I112 MCBs DC SUPPLY FAIL OK
13 I113 SPARE OK
14 I114 CB READY TO CLOSE OK
S.N BI.No DESCRIPTION CHECKED
01 I201 VT CIRCUIT HEALTHY OK
02 I202 OIL TEMPERATURE ALARM OK
03 I203 WINDING TEMPERATUR ALARM OK
04 I204 OIL LOW LEVEL ALARM OK
05 I205 PRESSURE RELEASE DEVICE ALARM OK
06 I206 PRESSURE VACUUM GAUGE ALARM OK
07 I207 OIL TEMPERATURE TRIP OK
08 I208 WINDING TEMPERATUR TRIP OK
09 I209 OIL LOW LEVEL TRIP OK
10 I210 PRESSURE RELEASE DEVICE TRIP OK
11 I211 PRESSURE VACUUM GAUGE TRIP OK
12 I212 SPARE OK
13 I213 SPARE OK
14 I214 SPARE OK

10. BINARY OUTPUT

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDYA
DATE: 15-05-2023 15-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report for Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9635
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-11
Date: 15-05-2023 Page 7 of 7

S.N BI.No DESCRIPTION CHECKED


01 O1 GENERAL TRIP OK
02 O2 CLOSE INHABIT OK
03 O3 SPARE CLOSE OK
04 O4 TRIP OR ALARM FOR LAMP OK
05 O5 WATCHDOG OK
06 O101 SEPAM TRIP OK
07 O102 ES CLOSED OK
08 O103 CB TEST OK
09 O104 SPARE OK
10 O105 SPARE OK
11 O106 SEPAM TRIP FOR LOCKOUT RELAY OK
12 O201 SPARE OK
13 O202 SPARE OK
14 O203 SPARE OK
15 O204 SPARE OK
16 O205 SPARE OK
17 O206 ES MAGNET OK

11. Remarks : Nil

12. Test Equipment Details :

EQUIPMENT CALIBRATION CALIBRATION


S.NO TYPE
Sl. NO DATE DUE DATE
1 Omicron CMC 356 HE053P 08.11.2022 07.11.2023
2 Fluke-179 5490041 11-08-2022 10-08-2023

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDYA
DATE: 15-05-2023 15-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation