ID % Complete Task Task Name Duration Start Finish Mar 1, '20 Mar 8, '20 Mar 15, '20

Mode S M T W T F S S M T W T F S S M T W T F S S
1 38% REFRACTORY WORKS IN SHAYBAH 42 days Tue 3/3/20 Tue 4/28/20
BURN PIT SCHEDULE
2 100% site mobilization 2 days Tue 3/3/20 Wed 3/4/20

3 100% Sand removal 2 days Thu 3/5/20 Fri 3/6/20

4 100% Damaged brick, castable Demolition 7 days Mon 3/9/20 Tue 3/17/20

5 100% Inspection by aramco 1 day Wed 3/18/20 Wed 3/18/20

6 10% damaged Wall concrete repair 3 days Fri 3/20/20 Mon 3/23/20

7 50% Damaged castable repair 2 days Tue 3/24/20 Wed 3/25/20

8 0% Back up board lining 1 day Thu 3/26/20 Thu 3/26/20

9 10% Brick installation 12 days Fri 3/27/20 Mon 4/13/20


10 100% Damaged Slab Removal 1 day Tue 4/14/20 Tue 4/14/20

11 0% concrete rebar & form work fixing 4 days Wed 4/15/20 Mon 4/20/20

12 0% concrete pouring 1 day Tue 4/21/20 Tue 4/21/20

13 0% Curing 4 days Wed 4/22/20 Mon 4/27/20

14 0% Final Inspection 1 day Tue 4/28/20 Tue 4/28/20

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: Shaybah Burn Pit Shutd
Milestone Inactive Summary Start-only Baseline
Date: Mon 3/16/20
Summary Manual Task Finish-only Baseline Milestone

Project Summary Duration-only External Tasks Baseline Summary

Page 1
Mar 22, '20 Mar 29, '20 Apr 5, '20 Apr 12, '20 Apr 19, '20 Apr 26, '20
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: Shaybah Burn Pit Shutd
Milestone Inactive Summary Start-only Baseline
Date: Mon 3/16/20
Summary Manual Task Finish-only Baseline Milestone

Project Summary Duration-only External Tasks Baseline Summary

Page 2