Professional Documents
Culture Documents
Delivered by:
Dr Argaw Gurmu
Level 4 - John Hay Building, Deakin University, Geelong
Tel: +613 522 78663
E-mail: argaw.gurmu@deakin.edu.au
CLASS AND SEMINARS
Library - https://www.deakin.edu.au/library
Student Committee
Mark
Deliverable Format Submission Date
(%)
Assessment 1 – Quiz 1 10 Individual 24 March 2023 8pm to 31 March 2023 8pm
Assessment 1 – Quiz 2 10 Individual 28 April 2023 8pm to 5 May 2023 8pm
Assessment 2 – Interim Report 25 Group Thursday, 6 April 2023 by 8pm
Assessment 2 – Final Report 25 Group Friday, 12 May 2023 by 8pm
Reference correctly
1. An introduction to estimating
2. Construction estimating and its importance
3. A review on cost estimation tools and techniques
4. Detailed estimating
4.1 Material pricing
4.2 Labour cost
1. An Introduction to Estimating
1. An Introduction to Estimating
What is tendering?
A bidding process to choose or find a contractor to
complete the project at hand. This is often referred to as
‘procurement’ these days:
1. An Introduction to
Estimating
Bidding Flowchart
Estimating
Bidding
Flowchart
What is estimating?
The dataset in Table 1 shows cost overrun in 258 projects in 20 nations in five continents.
Reference: Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it
Bent Flyvbjerg
2. Construction estimating and its
importance
Examples of Projects with cost overrun
1. Epping to Chatswood Rail line Project- Sydney
Why estimating?
One of the main reasons for the projects cost
overrun, is an underestimation of the project costs!
2. Construction estimating and its
importance
Importance of cost estimating
An accurate cost estimate is necessary for:
1. Being successful in the bidding process
2. Maintaining a reasonable profit margin
success of an
estimating
Understanding of Understanding of
construction process
Experience fundamental principles
of estimating
3. Review of cost estimation tools and
techniques
3. Review of cost estimation tools and
techniques
Cost Estimation Tools and techniques based on
PMBOK:
1. Bottom-up estimating (detailed estimating)
2. Analogous estimating
3. Parametric estimating
4. Three-point estimating
5. Reserve analysis
6. Quotations
3. Review of cost estimation tools and
techniques
The accuracy of project estimates as the project progresses
Detailed
Estimating
3. Parametric
estimating
COST ESTIMATE CLASSIFICATION SYSTEM –AS APPLIED FOR THE BUILDING AND GENERAL CONSTRUCTION INDUSTRIES
3. Review of cost estimation tools and
techniques
Detailed estimating (Bottom-Up estimating)
Material Pricing
Labor Costs
Equipment costs Combining
Project cost
Subcontractor estimation
Profit and overhead
Contingencies
4.1 Material pricing
Material pricing:
Subtotal
Delivery
Subtotal
Sales tax
Total
Cost=(Quantity)*(Cost per unit)
4.1 Material pricing
Example 1.
Solution:
The material cost per square meter is determined as follows:
Material Cost = $2,430/150=$16.2 /m2
4.1 Material pricing
Example 2:
The price for a 10.1 Ton pump has been quoted FOB the factory. You have
obtained a shipping price of $500/ton to ship the pump from the factory
to the jobsite. Determine the cost of shipping the pump.
Solution:
Shipping Cost = $500 * 10.1 =$5,050
4.1 Material pricing
The sales tax rate is expressed as a percentage of the sales price of the
taxable materials.
The sales tax rate can vary by project, city, county, and state. It is important
for the estimator to determine the local sales tax rate for each project.
On-site :
May include temporary fencing or containers in which to store the material or security
to protect from theft.
Off-site:
Secure storage space for the materials may need to be rented. Shipment cost to the site
as they are needed, adds to the cost of the materials.
4.1 Material pricing
4.1.5- Escalation
When the material prices are expected to increase over the duration of
project, the estimator needs to include an escalation allowance in the material
prices to cover the anticipated increases.
4.1.5- Escalation
Example 3:
You have been quoted $62,825 for an order of pipe. You expect pipe prices
to increase by 4.5% between now and the time you place the order. How
much should you include in your bid to cover the cost of the pipe?
Solution:
Escalated Cost = $62,825 * (1+ 0.045 ) = $65,652
4.2 Labour Cost
Where,
“i” is the number of activity,
“labor hour” is number of labor hours required to complete the work and
“labor rate” is the hourly rate for an employee
“labor productivity” and “labor rate” are the inputs for calculating the labor cost
4.2 Labour Cost
Labour Productivity
Labour productivity
Labor productivity is a measure of how fast construction tasks can be
performed.
Labour productivity
Example for 1st method:
Productivity is [70 / (8*7)] = 1.25 cum of concrete per labor hour (lhr)
4.2 Labour Cost
Labour productivity
Example for 2nd method:
Convert the output of 70 cum of concreting per 8-hour day for
a seven-person concreting crew to labour hours per cum.
Labor productivity
1- Estimating labor productivity using national
reference books
The least accurate source of data is that from national
reference books.
Labor productivity varies greatly around the country.
4.2 Labour Cost
1- Estimating labor
productivity using national
reference books
4.2 Labour Cost
1- Estimating labor
productivity using national
reference books
4.2 Labour Cost
1- Estimating labor
productivity using national
reference books
Questions?