Professional Documents
Culture Documents
Method Statement For Piping Installation
Method Statement For Piping Installation
: TA1000049-0000
VENDOR PRINT
Docu. No.:PLP-MKK-M003
Rev. No: A
PILIN PROJECT CO., LTD. Page :1/9
TITLE :
METHOD STATEMENT FOR PIPING INSTALLATION
FOR APPROVAL
REVIEW STAMP
☐ : APPROVED WITH NO COMMENT.
☐ : APPROVED AS NOTED
☐ : COMMENT
☐ : RESUBMIT
VENDOR PRINT
Docu. No.:PLP-MKK-M003
Rev. No: A
PILIN PROJECT CO., LTD. Page :2/9
CONTENTS
Page
1. SCOPE 3
3. PIPING ERECTION 5
ATTACHMENT 1 8
ATTACHMENT 2 9
MKK JOB No. : TA1000049-0000
VENDOR PRINT
Docu. No.:PLP-MKK-M003
Rev. No: A
PILIN PROJECT CO., LTD. Page :3/9
1. SCOPE
This document covers the sequence of activities for Fabrication, Erection and Installation procedure
for Metallic Piping (Carbon Steels, Alloy Steels, Stainless Steels, Nickel Alloys) systems and to
ensure the compliance to the above activities with the contractual applications in T-2 Project
2.1 Ensure that the drawing received bear the stamp "Issued for Construction" and are of latest
revision.
2.2 All materials shall be conformed to the IFC drawing with relevant material specifications before
receiving/ordering.
2.3 QC inspector shall conduct visual inspections, check color code, material certificates or
manufacturer's test reports (including size, wall thickness, rating, material code, heat no., quantity).
The receiving materials or equipment found defective or presenting non-conformance that shall be
clearly marked out and shall be returned to corresponding authority. Material shall be stored at
defined locations based on material classification. Carbon Steels, Alloyed Steels, Stainless Steels,
non-ferrous material etc...Large-sized fittings, flanges and valves shall be stored on wooden pallets
and no material is allowed to rest or store directly on ground at all time. All small-sized fittings,
flanges and valves, and all of gaskets shall be stored on racks/shelves.
VENDOR PRINT
Docu. No.:PLP-MKK-M003
Rev. No: A
PILIN PROJECT CO., LTD. Page :4/9
The isometric drawing shall be used as a weld mark-up format. The weld map shall be
unique and separate for each line, system, and component or assembly number.
The line diagram shall include weld location, weld numbers, tie point location, piece
numbers and weld type, including: Field weld, shop Weld, tie point, butt joint, socket joint,
fillet weld.
Length, height and width of the spools shall be within the limits of road transport and
erection possibility, unless specifically requested.
VENDOR PRINT
Docu. No.:PLP-MKK-M003
Rev. No: A
PILIN PROJECT CO., LTD. Page :5/9
The pipes shall be tack-welded in equidistant positions to avoid cracking and bending or
joint during welding. Tack weld shall be done by a qualified welder as per approved WPS.
In case of pipes with different thickness, the larger thickness shall be tapered in compliance
with standard to match smaller thickness.
Line numbers, Sheet numbers, Spool numbers, material code and Joint numbers are to be
clearly marked on the spools with the welder identification for each joint.
3. PIPING ERECTION
3.1 General
All lifting tools, equipments and ropes used for erection shall be inspected and certified by
HSE regulations. Activities shall be done according to the proper method statement for lifting
and handling.
Pre-fabricated spools shall be shifted to site carefully; care shall be taken while handling and
stacking of spools to prevent any possible damage.
The Pre-Fabricated spools shall be identified by spool and line numbers before erection.
Before erection of spools ensure for inside cleaning of the spools and their items.
The pre-fabricated supports shall be installed as per drawings, the pipe supports details
shall be followed in the piping layout drawings and Isometric drawing for location and
supports detail drawing.
All pipe openings shall be sealed before, during and after erection to prevent the ingress of
moisture and foreign matter. Threaded ends shall be plugged and sealed by waterproof
grease tape or purpose made plastic caps or plugs. End cap or cover shall be placed on the
open valve ends.
Erection of spools shall be carried out area by area as per piping layout drawings and
Isometric drawings.
Approved and safe scaffolding and temporary platforms shall be arranged to carry out
erection, fit up and welding of field joints at elevated positions.
Erect the spools in position using crane or other lifting devices as per the drawings.
Shifting of pipe spool on pipe racks should be done on the roller support if required.
Piping installation on pipe rack shall be from lower level to higher level.
Large bore random length shall be installed, which is followed by small bore field run pipe.
The sequence of composite spool will be same as of random length.
Joints shall be aligned and complete the fit-up / welding as per applicable WPS, Isometric
drawing and Project specifications.
NDT and other inspection shall be completed for the field joints and recorded properly.
The final correction and modifications made to fabricate spool in order to allow for stress
free installation, which should include; adjustment to pipe support, adjustment of flanges
MKK JOB No. : TA1000049-0000
VENDOR PRINT
Docu. No.:PLP-MKK-M003
Rev. No: A
PILIN PROJECT CO., LTD. Page :6/9
where free spaces are available in bolt holes, cutting and re- welding or introduction of
additional field joints or fit-up pieces.
3.3 Flushing
After completion and approval of hydrostatic testing of the system, all lines and equipments
shall be drained and flushed.
Special attention shall be given to points where water and sediments may be trapped, such
as valve bodies or low points.
A circulation loop may be established and the system flushed until circulating water is clear.
All pneumatic lines shall not be flushed.
Piping completed the Pressure Testing shall be internally cleaned to remove all remaining
foreign matter by water flushing or blowing with air.
Flushing shall be done with water and oil free air. Water used for flushing and cleaning
austenitic stainless steel shall contain less than 1ppm chlorides.
Instruments shall not be flushed through.
MKK JOB No. : TA1000049-0000
VENDOR PRINT
Docu. No.:PLP-MKK-M003
Rev. No: A
PILIN PROJECT CO., LTD. Page :7/9
Piping and equipment shall be dried and all traces shall be removed as per project
specifications.
Where special condition exist such as cleaning compressor section and oil lube piping,
separate cleaning method shall be adopted as per the Vendor's or Owner's specifications.
3.4 Re-Instatement
After successful completion of pressure testing, flushing and draining, the system shall be
returned to a state of commissioning readiness as per drawing specifications and Project
requirement.
All temporary materials such as spades, blinds, gaskets and temporary supports should be
removed from the system.
All spectacle blinds should be repositioned to the correct position as per the P&ID.
All accessible points of the system shall be inspect to ensure that it is free of scale, rust,
loose paint and film and is of correct surface appearance.
All items those were removed from the system before Hydro test such as control valves,
inline instruments etc. should be re installed after Hydro test and flushing.
All punch items should be removed and all test vents should be seal welded.
All completed system should be inspected for the correct flow direction in piping and
instruments.
MKK JOB No. : TA1000049-0000
VENDOR PRINT
Docu. No.:PLP-MKK-M003
Rev. No: A
PILIN PROJECT CO., LTD. Page :8/9
ATTACHMENT 1
WORK FLOW
PIPING PRE-FABRICATION AT PILIN’S SHOP
Fab. Schedule
Material Required
Dwg. Specification
Material Receiving
Fab. Sequence
ISO. Dwg. / WPS/ Con’s Spec.
ISO. Dwg. / Cutting Plan WPS/ ISO.Dwg.
Con’s Spec.
Con’s Spec./Procedure
MKK JOB No. : TA1000049-0000
VENDOR PRINT
Docu. No.:PLP-MKK-M003
Rev. No: A
PILIN PROJECT CO., LTD. Page :9/9
ATTACHMENT 2
WORK FLOW
PIPING ERECTION AT
SITE
Construction Schedule
Spool transfer to Site
Dwg. Specification
Material Receiving
Fab. Sequence
Touch-up
Pressure Test Final
Air flushing & Topcoat
Hydro / Pneumatic Painting Acceptance
Con’s Procedure
Welded damaged