Blu Rock Quarry Alfred Road Estcourt

TEL: (036) 3521244 or 0717261521


ATTENTION Mark TEL NO:
COMPANY: Bergmix - Mooi River FAX NO:
REPORT No: 48566 CELL NO:
PROJECT: Klein Mooi Bridge P28-1 EMAIL: testresults@bergmix.co.za

CONCRETE CUBE REPORT


Job Date cast Specimen Data Date Rec Cube Customer Test date Test Problem Dimensions Mass Compressive Std.
number number marking age code mm x mm x mm (kg) Strength Dev.
days Load (kN) MPa
21000100 29 Jan 21 Cust Ref: M12373 01 Feb 21 174599 None 05 Feb 21 7 7 100 100 100 2.496 125.6 12.5 1.32
Mix MPa: 15.0
Mix Code: 15/20 SP
29 Jan 21 01 Feb 21 174600 None 05 Feb 21 7 7 100 100 100 2.387 145.9 14.5
29 Jan 21 01 Feb 21 174601 None 05 Feb 21 7 7 100 100 100 2.404 147.6 15.0
29 Jan 21 01 Feb 21 174602 None 12 Feb 21 14 9 100 100 100 2.392 192.5 19.5
29 Jan 21 01 Feb 21 174603 None 26 Feb 21 28 100 100 100 2.381 213.1 21.5 1.61
29 Jan 21 01 Feb 21 174604 None 26 Feb 21 28 100 100 100 2.404 247.1 24.5
29 Jan 21 01 Feb 21 174605 None 26 Feb 21 28 100 100 100 2.371 240.7 24.0
Reason slump figures not required: Not Requested
Data reported here for job number 21000100 contains material amendments made after issue of report numbers 48270 and 48348 .
Data reported here for job number 21000100 replaces that in report numbers 48270 and 48348

PROBLEM CODES
1 Cube honeycombed/voided 2 Cube damaged 3 Cube mass low 4 Abnormal cube failure pattern 5 Cube dimensionally non-standard 6 Test results low strength 7 Test results
exceed allowed variance 8 Cubes received and tested dry 9 Non-std test, SABS requires 3 cubes/ set/ test age 10 See attached photo's 11 No concrete specification given to
CMT LAB 12 High variance of test results

CMT LAB cured cubes, where possible and conducted strength testing on cubes, however, CMT LAB was not involved in any processes that were outside its scope of work,
as defined by the customer. Such processes may have included sampling concrete, making, transporting and curing of cubes, as relevant. Cubes were cured by CMT LAB
from date received to date tested, as relevant

SABS 0100-2, clause 3.5.4, states: "valid test result: the average result obtained from three test cubes of concrete that have been tested in accordance with SABS method 863,
with the additional reuirement that curing water must be maintained at a temperature between 22 deg C and 25 deg C".

SABS 0100-2, clause 14.3.1.4, states: "The cubes shall be tested in accordance with SABS method 863. Three cubes shall be tested for acceptance at the age specified, which is
usually 28 days. For prestressed concrete, sets of three cubes shall be tested at 3 days. Sets of three cubes may be tested at other ages for information".

SABS method 863, clause 4, states: "Obtain samples of concrete and prepare and cure a set of three test specimens, as described in the relevant clauses of SABS method 862-
3, respectively".

If the cube strengths given in this report are to be used for acceptance in accordance with SABS 0100-2 (or any other specification with similar requirements to those of SABS
0100-2) then the above requirements must be complied with otherwise, acceptance based on cube strengths using the results given in this report, cannot be made

ALL CUBES ARE TESTED IN ACCORDANCE WITH SABS STM 863


The results relate only to the items tested.
The test report shall not be reproduced except in full, without approval of CMT Lab
CMT Lab

Reported on: 01 March 2021 at 09:02 CMT Laboratories (Pty) Ltd Reg:2017 TD 025/01 Page 1 of 1