EPM CHECKLIST

TIME DESCRIPTION AREA ASSIGNED PERSONNEL REMARKS


- Shut off 3000ACB Generator Switch Board Panel (6th Floor Genset Room)
supplying ATS A.
- Capturing of PE 1-4 & SE 1-2

- IF all PE & SE are captured,transfer supply to PE & SE to LVSA normal


supply @ Roofdeck Machine Room.
- Release PE & SE

- Shut off 3000ACB Switch Board Panel supplying ATS A normal power @
Transformer room GF.

- Shut off 400ACB supplying ATS C (fire pump) normal power @ Transformer
room GF.
Start of EPM for ATS A
- EE room Panel
- Transformer room
GF * ATS A
* Distribution Panel
* Switch Board Panel

- Fire Pump room


* ATS C
* transfer pump panel
- Sewage 1 Panel
B2 - Sump pit 1 Panel
- Sewage 2 Panel
- Sump pit 2 Panel
- Lighting & CO Panel
- Exhaust Panel
- Control room
- Supply Fan room
- Hotel Panels @ near SE landing
B1
- STP Panel
- Diesel room Panel

- SE Machine Room
- PE Machine Room
- Booster Room
8:00 AM - 12:00 AM Roof deck
- Pressurization Room 1
- Pressurization Room 2
- Pressurization Room 3
- Clearing of ATS A & braches
- Capturing of PE 1-4 & SE 1-2
- Energize Genset 1

- Turn ON 3000ACB Generator Switch Board Panel (6th Floor Genset Room)
supplying ATS A.

- IF all PE & SE are captured, transfer supply to PE & SE from LVSA normal
supply to ATS A @ Roofdeck Machine Room.
- Release PE & SE
- Shutdown HVSG A @ Transformer Room GF
- Start replacement of 5000ACB @ Transformer room
Start of EPM for LVSA
- Transformer room
* Transformer A
GF
* LVS A
- EE room
EE room
2F * MTS
* Panels
EE room
3F * MTS
* Panels
4F Panels
5F Panels
6F EE room
19F EE room
20F EE room
21F EE room
22F EE room
23F EE room
24F EE room
25F EE room
- Clearing of LVS A & braches
12:00PM - 12:50PM Lunch Break
- Capturing of TE 1-2
- If TE 1-2 are captured, turn OFF HVSG main switch @ GF
- Shutdown HVSG B @ 6F Genset room
- Shutdown VECO main fuse link
Start of EPM for ATS B
- Transformer room
* HVSG
GF - Kitchen Panels
- IF HVSG @ GF is already done in the EPM, VECO may return the main fuse
link ON and Energize the HVSG.
3F ramp ACCU/AHU Panels
- Chiller AHU Panels
- Offices ACCU Panels
4F - QH ACCU Panels
5F - QH ACCU Panels
- Genset room
* HVSG B
* Transformer B
12:50PM - 4:00PM * ATS B
6F
* LVS B
* Panels
- Chiller feed pump room
- EE room
7F - EE room
8F - EE room
9F - EE room
10F - EE room
11F - EE room
12F - EE room
13F - EE room
14F - EE room
15F - EE room
16F - EE room
17F - EE room
18F - EE room
Roofdeck - Heater Panels
- Clearing of LVS B & branches
- Turn ON HVSG B @ 6F Genset room

- Transformer room
Note: Ensure LVS A switch board panel ACB's are OFF
* Installation of 5000 ACB
* Retrofitting of busbar
* Testing of connections
* Clearing of 5000 ACB Panel
GF * Switching ON of HVSG A
4:OOPM - 12:00AM * Switching ON of 5000 ACB
* Programming of 5000ACB
* Testing and commissioning of 5000 ACB
* Compelete installation of 5000 ACB
* Switch ON LVS A switch board panel ACB's
* Turn ON 400ACB supplying ATS C (fire pump) normal
power.
- Genset room
6F
* Shutdown Genset 1