The Dubai Mall From (Date): 09 Aug 2022 Time (In): 12:00 AM
09 Aug 2022 02:45:03 PM To (Date): 16 Aug 2022 Time (Out): 12:45 PM
EMJWPP-0382265-AUG-2022 Approved By: Valerose Tinio
Comments:
H&S Comments:
Contractor to comply with TDM H&S standard requirements.
No noisy work during mall trading hours.
Ensure close supervision when carrying out the task by the main contractor.
Ensure floor protection are in place during the shifting of materials in public area.
Hot Work Permit shall be obtained separately and approved by TDM ERU and acetylene is not allowed in TDM.
Acetylene is not allowed in Dubai Mall. MAJOR WORK PERMIT
Diesel/petrol operated machine and equipment are not allowed inside the mall.
Tenant Details
Holding
Brand Name ECCO Unit No TDM-FF-154 Ecco Shoes L.L.C.
Company
Applicant Details
Applicant Name Anthony Mills Designation Projects Team Mobile Number 0506579098
Area
Sr. No
Area Name
Department
RDT
PERMIT PURPOSE
1 New Fit-out
Scope of Works
SUPPORTING DOCUMENTS
1 Letter of undertaking
2 Method Statement
3 Risk Assessment
ALI AL KENDI INTERIOR DESIGN AND DECORE LLC Yelala Ramchandran 0555591707
Mobile Number (Day Safety In-Charge) Safety In-Charge (Night) Mobile Number (Night Safety In-Charge)
0509434081 NAGAIAH 0549981871
Sub Contractor
Subcontractor Name Supervisor On Site Scope Of Work
Mobile
INSTRUCTIONS:
a) The work manager/engineer shall confirm all required safety equipment & procedures are in place prior to proceeding with the work and
fully responsible for implementation.
b) Ensure that a copy of this permit is available at all times on working site.
c) Ensure all applicable legislations, rules and regulations are followed at all times. The work will be stopped and the violator will be removed
from the mall for any non compliance.