Internal Meeting 30/12/2022

1. Prakash – Temporary project manager

With help of Nik

Initial delay PO issuance Vestigo-PTV, PTV-Access

Go live-latest December to go live

Present to the board – we may need to provide some lesson learned.

TNAG structure issue, power issue – main lead

Pending – power delivery (fuel cell) 2 nd Jan would be to port flight (7-10 days)

MOB hopefully end of month or mid Jan. By Feb, we on air/go live.

QMS – Prakash needs to do this (create one procedure, forms, standard checklist)

Power not included – next project needs to be informed

Project Schedule – about 20% off bcs engineering (fuel cell engineering). They propose, a form called
VDML, would take wtv list, doc, reports, calculation by when, and transfer submit to us then submit
to client for submission. Supposedly submit the actual documents and all.

Sedia Teguh – supply and delivery the fuel cell

Sepakat – Design

Nong – Fabricate, Paint and offshore installation (Asri and Amirul train to look out for
commissioning) / (Nong’s team to supervisor)

2. Nik Jefry

GE Digital – the first potential

Access can be vendor to Essem

Essem will have connection with GE Digital – Essem punya business card if liaise dgn
client/customers

3. Ibrahim