You are on page 1of 211

` Activity Description

1 Earthwork Is the permanent benchmarks and reference base


1.1 Marking lines
Is thechecked?
establishment of main grid lines in both
directions areinasboth
benchmarks per directions
the drawings?
are as per the
drawings?
Are the markings of BM's, CL's & grid line are
checked
Is as per specifications?
the protection of the survey pillar up to the
mark?
Is the establishment of block levels are
acceptable?
Is the control of survey work in the vertical
direction checked?
Is the EGL map prepared?
Is the area to be excavated is cleared of all
1.2 Excavation obstructions?
excavation marked on the ground is as per the
plan?
Is there adequate working spaces provided all
around?
Is the founding
pockets? If not, strata
remove suitable
and fillforwith
laying
leanppc?
concrete/sand.
Check if the dressing of the excavated area is
good?
Check if the stability of side slopes acceptable?
Is the dewatering
Check of thesoil
if the excavated waterlogged
is disposed area done?
to the
specific
Have thearea?
barricading & caution signs been
provided for deep excavations?
Check if the joint inspection is done?

1.3 Backfilling for backfilling?


the level as specified?
and compaction been done as specified?
Is the backfilled level been recorded?
been completed as specified?

1.4 Anti Termite Treatment the area complete?


cleaned?
been completed as specified?
Is the chemical being used as per specifications?
acceptable?
good working condition?
emulsion is as specified?
emulsion.
2 Structural work
2.1 PCC completed?
acceptable?
Check if the mix proportion is as specified?
specified?
Check if the finished level is as specified?
Is the surface finish acceptable?
Check if the curing is done properly?

2.2 Before concreting acceptable?


structural design?
been completed?
acceptable?
walkways is done properly.
concrete aids
understood by the concreting group?
done?

2.3 During Concreting correct?


ensured?
acceptable?
embedment?
layers?
by the labours.
initial setting time of cement?
wherever necessary.
& pavements done?

2.4 After concreting done.


for the specified period?
are flush with the concrete surface
service conduits & fittings wherever applicable.
defects on exposed concrete?
done properly

2.5 Brickwork masonry requirements?


concrete, debris, etc on the end of each day?
specified?
acceptable?
Check for wetting of bricks before using it
thickness are as specified.
Are the bricks being laid up with their frogs up?
are as specified?
new masonry.
Is the staggering of vertical joints being ensured?
as per the drawings.
Check for cleaning & raking of joints
sufficiently.
Check for removal of debris.

2.6 Stone masonry requirements?


properly hammer dressed to get desirable shapes?
desired?
Is the wetting of size stones being ensured?
Is the mortar mix proportion as specified?
Is the staggering of vertical joints being ensured?
in the drawing?
Are the dimensions & levels as per drawings?
stone chips are done effectively?
properly?
Is the cleaning of dead mortar completed?
Is the curing done properly?
2.7 Blockwork Masonry requirements?
concrete, debris, etc.?
drawings?
acceptable?
suitable?
thickness
Check for block sizes & wall dimensions
as specified?
Check for bond between old & new masonry
Is the staggering of vertical joints being ensured?
Check for sizes of door & window openings
Check for cleaning & raking of joints
Is the curing for old masonry enough?
Check for removal of debris
3 Reinforcement Is the bar bending schedule ready?
reference?
(bbs)?
Check for cleanliness of bars.
drawings?
satisfactory?
Check for location of service conduits
for concreting

4 Shuttering Is the cleanliness of forms acceptable?


forms
Shuttering schemes?
to fix reinforcement
scheme
after specified duration
forms
removal)
grade in the drawings?
(post-removal)

5 Plastering properly?
rcc surfaces
surfaces
Check for suitability & safety of scaffolding
stains from the exposed concrete surfaces
required for plastering
Check for proper mixing of mortar
Check for mortar mix proportion
if specified
plastering
its way downwards to the floor?
done.
plumb
setting time of cement?
finish
bands, etc
plaster
Check for removal of dead mortar & debris
scaffolds
walls?
properly?
duration.

6 Architectural and Structural Compliance


6.1 Tiling debris been removed from the work area?
properly?
junction boxes, etc are done as specified.
reference?
Are slopes for the tiled surface finalized?
construction aids before the work starts.
Check for availability of tiling masons
specified?
Check if the thickness of mortar bed acceptable?
Check for pattern of laying
Check for the thickness of joints between tiles
columns, partitions, etc
Check the finishing of edges for cut tiles
required
specified period
Check for cleaning of tile surface
Check for grinding & polishing
finishes, slope, etc
joints between tiles properly?
6.2 Painting painting available for reference?
Check for availability of approved shade details
Check for the cleanliness of wall & ceiling.
mortar, dirt, dust, algae, grease, etc?
plaster
Check for suitability & safety of scaffolding
so as to protect the surface from being painted?
of plastic emulsion containers
Check for availability of painting groups
specified.
manufacturer’s specifications?
Check for the consistency of paint
Check for uniform application of paint
Check the number of coats of painting done.
Check the interval time between two coats.
proper stacking.

6.3 Doors and Windows Masonry opening.


plumb.
by screws
Check for dimensions of jambs & reveals
Final check for paint, surface finishes & glazing
cleaning of the aluminium door before handover

6.5 Frame Arrangement arrangement.


in nature
6.6 Design Requirements structure.
per relevant Indian Standard Codes

7 Electrical and Plumbing


7.1 Electrical verified?
correct?
the button mark?
Are all of the fixed boxes in one level?
is correct?
Are the required tools for chipping available?
corner of the chipped area?
Have the conduits been inserted into the box?
Is the proper sized box fixed?
places where chasing/chipping has been done.
with concrete/cement mortar?

7.2 Plumbing Are the latest drawings for the activity available?
Are all the required tools available?
team been given to start the plumbing work?
the approved drawings?
has been completed?
meter marking?
with teflon tape?
wherever required?
using spirit level?
drawings?
done?
sewage and wastewater lines as specified?
away from the bore packing area?
prescribed in the drawings?
basement
chambers
minimise the choke up problem
floor plan & elevation & structural design.
cription Yes/No References/ Remarks
hmarks and reference base
main grid lines in both
e drawings?
rections are as per the
M's, CL's & grid line are
cations?
survey pillar up to the
block levels are
y work in the vertical

red?
ated is cleared of all
the ground is as per the
ing spaces provided all

suitable
e and fillforwith
laying
leanppc?
of the excavated area is

of side slopes acceptable?


desoil
waterlogged area
is disposed done?
to the
& caution signs been
avations?
ection is done?

done as specified?
been recorded?
cified?

cified?
used as per specifications?

on?
d?

ortion is as specified?

evel is as specified?
ceptable?
done properly?
perly.

creting group?

ement?

d?
crete surface
ings wherever applicable.
ncrete?

n the end of each day?

ricks before using it


ied.
aid up with their frogs up?

rtical joints being ensured?

raking of joints

debris.

sed to get desirable shapes?

tones being ensured?


ortion as specified?
rtical joints being ensured?

levels as per drawings?


ffectively?

mortar completed?
perly?
& wall dimensions

en old & new masonry


rtical joints being ensured?
r & window openings
raking of joints
asonry enough?
debris
edule ready?

of bars.

service conduits

rms acceptable?

& safety of scaffolding


d concrete surfaces

ng of mortar
proportion

the floor?

dead mortar & debris


rom the work area?

done as specified.

d surface finalized?
re the work starts.
of tiling masons

of mortar bed acceptable?


ying
s of joints between tiles
c
edges for cut tiles

tile surface
polishing

operly?
reference?
of approved shade details
ess of wall & ceiling.
e, grease, etc?

& safety of scaffolding


face from being painted?
ntainers
of painting groups

cations?
ncy of paint
plication of paint
coats of painting done.
e between two coats.

of jambs & reveals


surface finishes & glazing
ium door before handover
ndard Codes

xes in one level?

for chipping available?


area?
n inserted into the box?
x fixed?
chipping has been done.
mortar?

s for the activity available?


ols available?
rt the plumbing work?
s?

r lines as specified?
cking area?
ings?

problem
& structural design.
Inspection Item
Sr. No. Construction Safety Checklist
1 Excavations, trenching, and shoring
1.1 Walkways and runways kept clear of excavated material

Walkway planks placed parallel to length of walk, closely spaced, fastened to prevent
1.2 displacement, and cleaned if slick conditions will prevail
1.8 Reflectorized vests worn by flagmen and others exposed to traffic.
1.4 Personnel not permitted under loads being handled by power equipment.
Truck and other haul-unit operators kept clear of units during loading (exception allowed if cab is
1.5 braced and shielded).
1.6 Wells, pits, and shafts covered or barricaded to protect all personnel.
1.7 Underground utilities located and staked before excavation.
1.8 Utilities left in place are protected by barricade, shoring, or suspension.
1.9 Excavations sloped to stable angles or shored and braced.
1.1 Cribbing and shoring installed in accordance with design performed by licensed engineer
1.11 Excavated material placed and other material stored at least 2 feet from excavation edges
When work is done below hazardous rock slopes, workers and equipment protected by scaling
slopes as necessary to minimize danger, bolting rocks and affixing wire mesh after scaling, and
1.12 placing timber or wire mesh barricades.
1.13 Scalers equipped with safety belts or boatswain chairs.
1.14 Scalers’ lifelines tied to at least two secure objects.
1.15 Workers not permitted to work one above the other in rock material.
1.16 Rock removed from top downward on steep slopes. Access to slope is from top only.
Sides of steep excavations shored and braced when heavy equipment operated close to excavation
1.17 edges.
1.18 Dust controlled to acceptable levels.
1.19 Guardrails built along walkways over excavations.
Workers in trenches 5 feet deep or more protected with shields or by sloping or shoring and bracing
1.2 excavation banks.

Trench bracing and shoring installed during excavation: cross braces or jacks placed horizontally,
1.21 spaced vertically, and secured to prevent unintended movement.

1.22 Trench supports removed from bottom upward. Ropes used to remove jacks in unstable soil.

1.23 Ventilation provides adequate oxygen and applicable specified atmospheric conditions.

1.24 Ladders or steps installed no more than 25 feet apart in trenches more than 4 feet deep.
2 Concrete, concrete forms, and shoring

2.1 Excavations sloped or shored so forms and concrete materials can be installed safely

Work platforms provided or safety belts worn by workers when reinforcing steel is placed in walls,
2.2 piers, and columns
2.3 Work not allowed above unprotected vertical-protruding reinforcing steel.
2.4 Vertical steel is guided or supported to prevent collapse.
2.5 Wire mesh rolls are secured at both ends to prevent recoiling.
2.6 Access points at all work areas accessed for safety by contractor before concrete placing begins.
Silos and bulk storage bins for concrete built with tapered bottoms and equipped with vibrators to
2.7 start flow.
2.8 Bull float handles made of nonconductive material.
2.9 Powered concrete trowels equipped with hand-release shutoff switches.
2.1 Handles on concrete buggies do not extend beyond wheels
When pump-creting is used, hose lines and discharge pipe are supported and joints and connectors
2.11 are protected with safety chains or by other positive methods
2.12 Cranes used to position concrete buckets. Crane cable equipped with safety hook.
2.13 Personnel prohibited from riding concrete buckets for any purpose.
2.14 Placing and vibrating crews not allowed under suspended buckets.
2.15 Wheels chocked and brakes set on concrete trucks when discharging on slopes.

2.16 Protective eye and face equipment worn by workers placing pneumatically applied concrete.
2.17 Forms and shoring material are free of splits, rots, cuts, or other defects.
2.18 Forms installed that will support all concrete loads safely
2.19 Nails and other accessories removed from stripped forms before stockpiling.
2.2 Slings fastened securely to gang forms if forms moved by crane.
2.21 Workers vacated from lower levels before forms are released and moved.
2.22 Personnel not permitted to ride forms being raised or moved.
Face helmets, goggles, or airline hoods worn by sand blasting crews.

2.23
2.24 Eye protection worn by finishers doing chipping or grinding repairs.
2.25 Concrete heating units and accessories meet safety requirements.
2.26 Heating units placed to provide safe clearance from enclosure frames and coverings.
2.27 Concrete enclosures lighted and ventilated.
3 Blasting and the use of explosives
3.1 Only authorized personnel permitted to handle or use explosives
3.2 Blasting personnel required to furnish evidence of competency in handling and using explosives
3.3 Smoking, matches, open flame, sparks, firearms, and other heat-producing devices prohibited near
storage magazines and during transport and use of explosives.
3.4 All explosives stored in locked magazines when not being used
3.5 Storage magazines ventilated. Magazines are fire resistant, weatherproof, and bullet resistant
3.6 Contractors maintain inventory and use records of all explosives

3.7 Appropriate authorities notified of loss or theft or of entry into magazines


3.8 Explosives transported to jobsite in original containers.
3.9 Blasting capsand
Signs, flags, notbarricades
transportederected
in same vehicle
and other with other explosives
precautions taken to ensure employee and public
3.1 safety
3.11 Blasting operations restricted to daylight hours.
3.12 All personnel removed from blasting areas during electrical storms.
3.13 Warning signs, 4-inch red letters on white backgrounds, reading “BLASTING AREA–RADIO
TRANSMITTING PROHIBITED,” posted on all roads within
3.14 Radio transmitters prohibited within 100 feet of electric blasting caps.
3.15 Empty explosive boxes
Utility companies and paper
and owners wrappings
or operators of destroyed by burning.
adjacent properties notified before blasting; necessary
3.16 precautions taken to prevent property damage.
3.17 All blasts fired electrically except in areas of extraneous electric currents.
Foundation Preparation Checklist
comprehensive list of items to check
4 Clearing and grubbing
4.1 The limits for clearing and grubbing are clearly marked.
4.2 Surveys are completed prior to clearing and grubbing when necessary for computing quantities.
4.3 All materials are removed and disposed of as specified.
4.4 The contractor's operation does not damage adjacent property.
4.5 The contractor's operation does not damage trees that shall remain
4.6 Burning is performed according to local ordinances and job specifications.
4.7 The timing and rate of clearing conforms to specifications.
5 Structural removal
5.1 Structural removal limits are clearly identified.
5.2 All materials are removed and either salvaged or disposed of as specified.
5.3 The removal operation does not damage adjacent property.
5.4 Burning is performed according to local ordinances and job specifications.
6 Stripping
6.1 The areas to be stripped are staked per plans.
6.2 Stripping is performed to the minimum specified limits.
6.3 All unsuitable materials are removed and disposed of as specified.
6.4 Surveys are performed
The responsible as is
engineer needed for quantity
consulted computations
if there are uncertainties about the suitability of stripped
6.5 materials for construction.
6.6 Stripping below the specified lower limits is quantified and paid for as foundation excavation.
7 Scarifying
7.1 All holes or depressions are filled.
7.2 Materials used to fill holes are compacted as specified.
7.3 The foundation is scarified to the specified extent.
7.4 Large rocks brought to the surface are removed
8 Dispersive,
The foundation and surrounding areascollapsible,
are visually and soluable
inspected for materials
signs of dispersive, collapsible, or
8.1 Tests
solubletomaterials.
verify the existence of dispersive, collapsible, or soluble materials are conducted when
8.2 applicable.
The responsible engineer is contacted whenever the presence of dispersive, collapsible, or soluble
materials
8.3 All is suspected.
dispersive, collapsible, and soluble materials are removed from the foundation to the depth and
8.4 extent specified or as otherwise directed by the engineer
8.5 Surveys to quantify
Documentation the amount
is obtained of dispersive,
as necessary collapsible,
to compensate theand soluble for
contractor materials
added are
work completed.
caused by
8.6 removal of dispersive, collapsible, and soluble materials.
9 Foundation compaction and moisture control
9.1 The
The moisture
responsibleandengineer
density is
ofconsulted
the foundation
if it ismeets or exceeds
necessary the specified
to deviate requirements
from the specification
9.3 requirements.
10.1 All loose
cracks,undesirable materials
crevices, and are removed
overhangs are cleanedandandthe concreted
foundationorsurface
groutedisand
cleaned
thereasare
specified.
no negative
10.2 slopes or overhangs remaining on the foundation surface
10.3 All loose and weathered materials are removed from the foundation surface
10.4 Subsurface grouting is performed as specified.
10.5 The
The responsible
geologist andengineer is notified
the responsible of discrepancies
engineer between
are consulted design and
to determine thefield conditions.
full extent of
10.6 documentation needed to adequately document foundation preparation measures and procedures.
11 The cutoff trench is staked at the specified Cutoff
locationtrench
and quantity surveys are attained to define the
11.1 upper limits
11.2 The trench is excavated to the specified or modified limits.
11.3 The trench extends to or into the specific layer of material shown on the drawings
11.4 Changes to the lower limits are documented and approved by the responsible engineer.
11.5 When applicable, lower limits are surveyed for quantity computations
11.6 Foundation materials are at the specified moisture and density at the time of backfill placement.
11.7 Only specified and suitable materials are placed in the cutoff trench.
11.8 Materials are placed at the specified moisture and compacted to the specified density.
12 Foundation drains
12.1 Foundation drains are staked and drainfill quantity surveys attained.
12.2 Foundation drains are constructed to the specified limits
12.3 Segregation of drainfill materials is prevented.
12.4 Internal perforated pipes are undamaged, clear of obstructions, and placed at the proper location.
12.5 Drainfill materials are compacted to meet specification requirements
13 Final foundation preparation
13.1 All unsuitable materials have been removed
13.2 The cutoff trench is installed.
13.3 Just
Drainage
prior features
to placingareearthfill,
installed.
the moisture content and density of the foundation meet specification
13.4 requirements
13.5 All subsurface grouting has been completed.
13.6 All rock surfaces are cleaned and grouted
13.7 All loose and drummy rock has been removed from the surface
13.8 All negative slopes have been corrected
RCC Construction Checklist
The following checklist provides guidance for examining the quality of RCC construction. The checklist does not ad
to RCC construction. The checklist should be used for guidance only as the inspector examines the work, and shoul
items to check.
14 Materials
14.1 Types of cement and pozzolan used in the RCC mix is in accordance with the job mix.
14.2 Temperature of cement and pozzolan at time of delivery is at or below the specified maximum.
14.3 Cement and pozzolan are maintained in an uncontaminated dry condition..
14.4 Combined (coarse and fine) aggregate used in the mix is graded in accordance with the job mix.
14.5 Quality of the mix water complies with specified requirements
14.6 Admixture is in accordance with the job mix.
15 Mix Design
15.1 Other
Mix proportions
than minorare in accordance
reductions with
in water the jobthe
content, mix.
job mix does not change without the engineer’s
15.2 concurrence.
16 Contractor’s test section plan has been submitted Test Section
and concurred with by the engineer prior to
16.1 beginning the test section
16.2 Test section is constructed at the approved location.
16.3 Approved
Productionjob mixand
roller is the onlycompaction
special mix placed in the test section.
equipment used in the test section meet specified
16.4 requirements and are the same planned for use during RCC production.
16.5 Compaction equipment is operated at normal operating speeds.
16.6 If the test section is not incorporated into the structure, it is disposed of as specified.
17 Plant operator’s experience is documented Batching
and the and mixingexhibits the capability to oversee the
operator
17.1 batching and mixing operation
17.2 Batching equipment is in good condition, has adequate capacity, and hoppers discharge completely
17.3 Drums are inspected and cleaned as needed.
17.4 Specified
Adequate minimum
quantities quantities of aggregates
of all ingredients are maintained
(aggregates, on site during
cement, pozzolan, water,production.
and admixtures) are
17.5 available on site to allow uninterrupted production
17.6 Only nonsegregated
Aggregate aggregates
moisture is monitoredare introduced
and adjustmentsintomade
the mixer
to the mix at least once each shift or as
17.7 needed to comply with job mix moisture requirements
17.8 Drum mixers are not overcharged.
17.9 Transit mixers are not used for mixing RCC.
17.1 Admixtures are metered at the specified rate.
17.11 Plant operator visually inspects the mix for uniformity on a continuous basis
17.12 Periodic visual inspections for mix uniformity are being made by quality control personnel.
17.13 Mix appears uniform or uniformity testing is conducted to verify uniformity
17.14 Causes of uniformity are isolated and corrected.
17.15 Mix uniformity is documented periodically and before and after uniformity problems are corrected
18 Conveying
18.1 Consistency or workability of RCC is maintained during conveyance.
18.2 RCC mixture is protected during conveyance from excessive drying or rain
18.3 Belt conveyors are of ample width
18.4 Drop chutes of sufficient length and diameter are provided where necessary to prevent segregation.
18.5 Hauling equipment does not contaminate or damage recently placed RCC surfaces
18.6 Long, inclined chutes are not used
18.7 Conveyance time does not exceed the maximum specified time.
18.8 Critical conveyor components are accessible for machine removal.
19 Wet Weather
19.1 There is no mud or standing water on the bonding surface at the time of placement
19.2 Placement ceases if changes in mix consistency indicate a significant increase in mix moisture.
19.3 Unhardened RCC is protected from erosive high intensity rainfall
19.4 RCC is not placed in rain falling at a rate equal to or greater than 0.1 inch in 20 minutes
20 Cold Weather
20.1 When
RCC isthere
not placed whenfor
is potential thecold
air temperature
weather, all drops below
materials, 35 ºF
labor, or equipment
and the RCC mix is less
needed forthan 40 ºF
adequate
20.2 RCC
protection are on hand
temperature and readyatfor
is maintained or use prior
above 35to ºFbegin_x0002_ning placement.
for a protection period equal to the curing period
20.3 plus 7 days.
20.4 Air
When andrequired
RCC temperatures are monitored
by the specifications, and documented.
the RCC is insulated if the air temperature is 25 ºF cooler than
20.5 that of the RCC during the protection period.
When specified, the RCC temperature does not drop more than 20 ºF within the first 24 hours after
20.6 insulation is removed
21 Hot Weather
If misters are used for cooling, a fine mist is used to avoid adding too much moisture to the fine
21.1 aggregate.
Mix placement temperature is monitored and documented and RCC is placed at a temperature at or
21.2 below
All icethe maximum
added specified
for cooling placement
is melted temperature.
and distributed throughout the mix before being discharged
21.3 from the tilting drum or compulsory mixer.
21.4 Curing is begun immediately after compaction.
22 Foundation preparation
22.1 Foundation is excavated or filled to the specified lines and grades.
22.2 Density of earthen foundation is uniform and meets specified requirements.
22.3 Density of earthen foundation is uniform and meets specified requirements.
22.4 Rock foundations are clean.
22.5 Foundation temperature is greater than or equal to 35 ºF
22.6 Foundation is moist but free of standing water.
23 Forming
23.1 Forms conform to the plan for obtaining vertical surfaces.
23.2 Forms are set to the planned line and grade and are well anchored and braced.
23.3 Form oil is uniformly applied but not allowed to contact any bonding surface.
23.4 Care is taken in the removal and resetting of forms to avoid damage to the previously placed RCC.
24 Spacing and spreading
24.1 Foundation or lift joint preparation is complete as specified
24.2 Care
Formsisare set to
taken to prevent
specified line and
damage to grade, well placed
previously anchored,
RCCand oiledsetting forms or conducting other
when
24.3 operational.
24.4 Lifts are of a uniform thickness to produce the designed grade within allowable tolerances.
24.5 Equipment does not contaminate or damage the lift surface.
24.6 Mix is deposited away from forms
24.7 Mix is deposited in a manner to limit segregation.
24.8 Mix is placed as near to its final location as possible.
24.9 Mix is spread quickly and in a manner to limit segregation.
24.1 Mix is placed in a configuration that limits edge joints.
24.11 Segregated mix is remixed or wasted.
24.12 Tests are conducted to verify and document specification compliance
25 Compaction
25.1 Production roller and special compaction equipment meet the specified requirements.
25.2 Production roller is used where possible.
25.3 Special compaction rollers are only used where absolutely necessary.
25.4 Lift thickness is controlled to prevent surface damage caused by over compacting.
25.5 RCC is compacted to the specified density.
25.6 Compaction
Requirementisfor uniformity ofasdensity
accomplished soon asispossible
met. after the RCC is placed, and within the specified
25.7 time limit.
26 Joints
26.1 All transverse edge joints are spaced a minimum of 20 feet apart.
26.2 All edge joints are trimmed as specified.
26.3 All joints are treated as specified.
26.4 All joints are kept moist and clean.
26.5 Specified neat cement grout or bonding mortar is used.
26.6 Bonding materials are evenly distributed and spread to the specified thickness.
26.7 Bonding materials are not disturbed after placement.
26.8 Bonding materials are not exposed longer than specified.
26.9 Bonding materials do not set up or dry out before being covered with RCC.
27 Curing and materials are onsite and ready to be
Prior to beginning RCC placement, curing equipment
27.1 deployed.
27.2 Curing begins immediately after compaction.
27.3 Curing continues until the RCC has been maintained at or above 40 ºF for 14 days.
27.4 Curing of repairs begins immediately after repair completion.
27.5 Repair curing continues until the repair has been maintained at or above 40 ºF for 7 days
27.6 Application of curing water does not erode the surface.
27.7 Coverings are secured to prevent the movement of air between the RCC and the covering.
27.8 Only white or reflective coverings are used during hot weather.
27.9 Curing compounds are not applied to bonding surfaces or areas to be repaired.
27.1 Curing compounds conform to specification requirements.
27.11 All standing water is removed prior to applying the curing compound.
27.12 Continuously agitating sprayers are used to apply curing compound.
27.13 Manual hand pump sprayers are not used.
27.14 Curing compound is reapplied every 7 days during the curing period.
27.15 here curing compound is used, the entire surface is uniformly covered at the specified rate.

Construction Equipment Safety checklist


28 SanitationMedical services and safety
28.1 Potable water supply available at jobsite.
28.2 Potable water dispensers clearly marked; each equipped with tight cover and tap.
28.3 No common drinking cups.
28.4 Waste receptacles available for disposable cups and other litter, if single service cups are supplied.
28.5 Electrolyte supplements available as needed. (NRCS OSHA Supplement)
28.6 Adequate toiletsof
Phone numbers provided at jobsite.
offsite medical attention and ambulance service posted outside first aid facility
28.7 and all jobsite offices.
Locations of first aid kits and other medical supplies posted conspicuously on signs outside first aid
28.8 facility
Complete andfirst
all aid
jobsite
kitsoffices.
available, compliant with ANSI Z308.1–1998 Type III. Minimum of 1 kit per
28.9 employees.
28.1 Employee with a valid certificate in first aid is assigned during each work shift.
28.11 At least one stretcher and two blankets available at jobsite.
29 Head protection
29.1 Hard
Hard hats worn
hat area by all3-persons
signs, entering
by 4-foot minimumany size,
part of jobsite.
erected at (NRCS OSHA
all jobsite Supplement)
access locations. (NRCS
29.2 OSHA Supplement)
30 Noise exposure
30.1 Ear protection devices worn when noise exceeds allowable exposure.
31 Illumination
31.1 Worksites, offices, shops, and storage areas lighted as required.
32 Eye and face protection
32.1 Eye and face protection provided for hazardous jobs.
32.3 Goggles or other protective equipment kept clean and in good repair.
33 Respiratory protection
33.1 Respirators are worn when dust concentrations exceed safe hygienic levels.
33.2 Employees protected from other hazardous concentrations.
33.3 Respirators kept clean and in good condition. Respirators inspected regularly.
34 Employees protected by safety Fallbelts
protection
and lines(OSHA 1926 Subpart
when working on steepM)
slopes or unguarded heights.
34.1 Employees
(NRCS OSHA Supplement)
working on surfaces 6 feet or higher with an unprotected side or edge are protected
34.2 from falling.
35 Working over or near water
35.1 U.S. Coast Guard-approved life jackets or vests worn by employees if there is danger of drowning.
35.2 Protective equipment inspected for defects that would alter the buoyancy and strength.
35.3 Ring buoys and 90-foot lifelines readily available for rescue operations.
36 Fire extinguisher with 10B rating requiredFire protection
within 50 feet when more than 5 gallons of combustible
36.1 liquid are used
36.2 Portable extinguishers serviced and maintained
36.3 Fire extinguishers have been listed or approved by a nationally recognized testing laboratory.
37 Fire prevention
37.1 Combustion engine exhaust kept clear of combustible materials
37.2 Signs posted at and around operations having fire hazards, “NO SMOKING OR OPEN FLAME.”
37.3 Storage area kept free of weeds, grass, and other combustible materials
37.4 Materials stored indoors are handled and piled in ways that minimize fire hazard.
38 Temporary heating devices
38.1 Solid
Adequate fresh air provided
noncombustible to ensure
material used topersonnel safety.units. Material extends 2 feet beyond each
support heating
side of heater.
38.2 Minimum 10-foot clearance provided in temporary job enclosures between heater and combustible
38.3 coverings.
38.4 Oil-fired heaters equipped with safety oil stop for protection during possible flame out.
39 Signs, signals, and barricades
39.1 Barricades erected and legible traffic signs posted at hazardous locations.
39.2 Signs posted and barricades installed to prevent public access.
39.3 Nighttime signs and barricades lighted or reflectorized.
39.4 Flaggers used when working conditions warrant.
39.5 Red flags or sign paddles 18-inches square used by flaggers to make hand signals.
39.6 Reflectorized safety on
Detour signs posted vests or coats
streets and worn by flaggers.
highways. Sign types and placement meet State and local
39.7 regulations and codes
40 . Material handling, storage, use, and disposal
40.1 Storage areas kept approximately level, well arranged, and free of flammable materials.
40.2 Construction material stacked, racked, or blocked to prevent movement.
40.3 Lifelines with safety belts used by workers entering hoppers or tanks.
40.4 Excess material not stored on scaffolds or runways.
40.5 All nails removed from used lumber.
40.6 Material to be handled by crane stored in area clear of overhead power lines
41 Rigging equipment for material handling
41.1 Equipment inspected before use and during material handling.
41.2 Equipment is adequate to handle loads
41.3 Tagged equipment (determined by the contractor to be defective) removed or replaced.
42 Waste material disposal
42.1 Solvent
Scrap lumber,
waste,waste, andand
oily rags, rubbish removed
flammable as work
material progresses.
stored in covered metal containers until removed
42.2 from jobsite.
43 Power and hand tools
43.1 Power tools equipped with guards (as manufactured) over all exposed moving parts.
43.2 Handheld power tools equipped with pressure control switches.
43.3 Goggles and other protective equipment worn by workers as required.
43.4 Tools with mushroomed heads or defective handles prohibited
43.5 Electric-powered tools double insulated or grounded with 3-wire conductors.
44 Gas welding and cutting

44.1 Gas
Hosecylinders meet U.S. Department
lines distinguished either by colorof Transportation
(such as, fuel isrequirements.
red, oxygen is green) or by surface texture.
44.2 Oxygen and fuel lines shall not be interchangeable
Cylinders placed upright when stored or in use, chained to prevent overturning, and capped tightly
44.3 when not in
Cylinders use.upright when moved (tilt and roll on bottom edge) and anchored to pallet before
kept
44.4 hoisting.
44.5 Cylinders protected from excessive heat or cold and from electric currents.
44.6 Defective gauges, regulators, valves, and hoses repaired or replaced.
44.7 Friction lighters used to ignite gas torches. Matches prohibited.
44.8 Welding and cutting done only by authorized operators
44.9 Goggles or shields worn by welders and helpers.
45 Electrical
45.1 Hot circuits de-energized or equipped with guards before starting work
45.2 Hot voltage circuits equipped with guards. Signs posted, “DANGER–HIGH VOLTAGE.”
46 Ladders (OSHA 1926.1053)
46.1 Ladders provided for access to work.
46.2 Ladders meet requirements of OSHA 1926.1053.
46.3 Portable ladders set on solid bare ground. Space around top and bottom of each ladder kept clear.
46.4 Portable ladders
3-inch cleats tied
18 to 23orinches
blocked to and
long, prevent movement.
12 inches between cleats. Rails notched to fit cleats, or fill
46.5 blocks used to secure cleats.
46.6 Length between supports (base and top landing) of job-made ladders does not exceed 30 feet.
46.7 Top of each ladder extends at least 36 inches above top landing.
47 than 4 feet aboveground or adjoining surfaces Scaffolding
and on all platforms built more than 10 feet
aboveground
47.1 Guardrail or adjoining
dimensions surfaces.
are 2- by 4-inch rails installed 42 inches above floor, 1by 6-inch intermediate
47.2 Platform
rail, 4-inch-high
plankingtoeboard,
extendedand 2- by64-inch
at least inchessupports at 8-foot
over supports. spacing.
Planking overlapped 12 inches or
47.3 anchored.
47.4 Ladders provided for access.
47.5 Overhead protection provided in hazardous areas.
47.6 Platform surfaces kept clean so workers are not in danger of tripping.
47.7 Design andand
Metal tube construction of wooden
coupler scaffolds meetscaffolds meet requirements.
requirements. Scaffolds erected as specified by
47.8 manufacturers. Expected loading meets minimum safety factor.
48 Floor and qall openings and stairways
48.1 Floor openings covered on all sides except at entrances protected by covers or guardrails.
48.2 Guardrails built if wall openings are less than 3 feet above floors, and drops are more than 4 feet.
48.3 Toeboards built if wall openings are more than 3 inches above floors.
48.4 Guardrails built along open-sided floors that are 6 feet or more aboveground.
48.5 Handrails
Handrails placed
built along
30 tostairways
34 inchesthat havethe
above at top
leastoffour
eachrisers.
riser. Raised handrail built along open side
48.6 Smooth
of stairs surfaces
and landings.
of handrail material positioned on top and sides. Handrail mounted at least 3
48.7 inches from sidewalls.
48.8 Stairs interrupted every 12 feet (vertical distance) with 30-inch landing.
Yes / No / NA Reference

(OSHA 1926.651(a))

ed to prevent
OSHA 1926.651(c)(1)(ii))
(OSHA 1926.651(d))
(OSHA 1926.651(e))
xception allowed if cab is

(OSHA 1926.651(b)(2))
(OSHA 1926.651(b)(4))

icensed engineer (OSHA 1926.652(b)(4)(i))


xcavation edges
nt protected by scaling
mesh after scaling, and

om top only.
erated close to excavation

ping or shoring and bracing


(OSHA 1926.652(a)(1))

acks placed horizontally,

cks in unstable soil.

ric conditions.

an 4 feet deep.

talled safely (OSHA 1926.652(a))

ng steel is placed in walls,


(OSHA 1926.501(b)(5))
l. (OSHA 1926.701(b))
(OSHA 1926.703(d)(1))
concrete placing begins.
quipped with vibrators to
(OSHA 1926.702(a)(1))
(OSHA 1926.702(h))
(OSHA 1926.702(c))
(OSHA 1926.702(d))
and joints and connectors

ety hook. (OSHA 1910.179)

slopes.

ly applied concrete.

(OSHA 1926.703(a)(1))
ing. (OSHA 1926.25(a))

(OSHA 1910.94(a)(1)(iii));
1926.57(f)(1)(ii); 1926.57(f)(2)
(i))
(OSHA 1926.28(a))

d coverings.

ng and using explosives (OSHA 1926.901(c))


ng devices prohibited near
(OSHA 1926.904(c))
(27 CFR Part 55, Subpart K)
, and bullet resistant (27 CFR Part 55, Subpart K)
(27 CFR Part 55, Subpart K)

s (27 CFR Part 55.30, Subpart C)


(OSHA 1926.903(q))
e employee and public (OSHA 1926.903(p))
(OSHA 1926.909(c))

TING AREA–RADIO
d before blasting; necessary

. (OSHA 1926.906(e))
n Checklist
ms to check

r computing quantities.

s.

d.

s.

suitability of stripped

oundation excavation.

ls
dispersive, collapsible, or
ls are conducted when
ve, collapsible, or soluble
oundation to the depth and

aterials
added are completed.
work caused by

ol
ed specification
requirements

sand
cleaned
thereasare
specified.
no negative
ace

defield conditions.
full extent of
measures and procedures.
are attained to define the

drawings
sible engineer.

e of backfill placement.

ified density.

d at the proper location.

ndation meet specification

Checklist
n. The checklist does not address all of the conditions that may exist related
xamines the work, and should not be relied upon as a comprehensive list of
k.

h the job mix.


e specified maximum.
n..
dance with the job mix.

ge without the engineer’s

the engineer prior to


ion meet specified

s specified.
capability to oversee the

ppers discharge completely

g production.
ter, and admixtures) are

st once each shift or as

asis
control personnel.
mity

ity problems are corrected

ain

ary to prevent segregation.


C surfaces

placement
rease in mix moisture.

h in 20 minutes

CC mix
ment is less
needed forthan 40 ºF
adequate
ement.
equal to the curing period

erature is 25 ºF cooler than


hin the first 24 hours after
uch moisture to the fine
aced at a temperature at or
efore being discharged

nts.
nts.

aced.
face.
he previously placed RCC.

forms or conducting other

owable tolerances.

equirements.

mpacting.

, and within the specified


kness.

CC.
onsite and ready to be

or 14 days.

40 ºF for 7 days

and the covering.

aired.

the specified rate.

(OSHA 1926.51(a))
and tap. (OSHA 1926.51(a)(2))
(OSHA 1926.51(a)(4))
service cups are supplied. (OSHA 1926.51(a)(5))
) in OSHA 1926.51(c),
d outside first aid facility (OSHAtable D–1. and
1926.50(f)
ly on signs outside first aid NRCS(NRCS
OSHAOSHA
Supplement)
pe III. Minimum of 1 kit per 25 Supplement)
(2) and NRCS OSHA
Supplement)
k shift. (OSHA 1926.50(c))

Aess
Supplement)
locations. (NRCS

(OSHA 1926.101)

(OSHA 1926.56)

(OSHA 1926.102)
(OSHA 1926.102(a)(4))

els.
(OSHA 1910.134)
larly. (OSHA 1910.134)
opes or unguarded heights.
e or edge are protected
(OSHA 1926.501(b)(1))

ere is danger of drowning. (OSHA 1926.106(a))


and strength. (OSHA 1926.106(b))
(OSHA 1926.106(c))
n 5 gallons of combustible
(OSHA 1926.150(c)(1)(vi))
(OSHA 1926.150(c)(1)(viii))
ed testing laboratory. (OSHA 1926.150(c)(1)(ix))

(OSHA 1926.151(a)(2)
NG OR OPEN FLAME.” (OSHA 1926.151(a)(3)

e hazard. . (OSHA 1926.151(d)(3)

tends 2 feet beyond each (OSHA 1926.154(a)(2))


en heater and combustible (OSHA 1926.154(b)(3))
(OSHA 1926.154(b)(4))
ible flame out. (OSHA 1926.154(e)(1))

. (OSHA 1926.200(b)(1))

d signals.
meet State and local
(OSHA 1926.200(g)(2))
al
mable materials.
(OSHA 1926.250(a)(1))
(OSHA 1926.250(b)(2))
(OSHA 1926.250(b)(5))
(OSHA 1926.250(b)(8)(i)
nes
(OSHA 1926.251(a)(1))
(OSHA 1926.251(a)(2))
ed or replaced.

containers until removed (OSHA 1926.252(c))


(OSHA 1926.252(e))

oving parts. (OSHA 1926.300(b)(1))


(OSHA 1926.300(d)(3))
(OSHA 1926.300(c))
(OSHA 1926.301(c) and (d))
tors.

(49 CFR–178–C) and (OSHA


reen) or by surface texture. 1926.350(c)(2))
urning, and capped tightly (OSHA 1926.350(f)(1))
chored to pallet before (OSHA 1926.350(a))
(OSHA 1926.350(a)(3))
ts.

(OSHA 1926.350(g)(3))

(OSHA 1926.404(d)(2)(ii))
GH VOLTAGE.”

of each ladder kept clear.


otched to fit cleats, or fill

s not exceed 30 feet.

more than 10 feet


or, 1by 6-inch intermediate
rlapped 12 inches or (OSHA 1926.451(b)(4))

s specified by (OSHA 1926.451)


(OSHA 1926.451)
ers or guardrails. (OSHA 1910.23(a)(1))
ops are more than 4 feet.

und.
drail built along open side
ail mounted at least 3 (OSHA 1910.23(e)(2))
code as per Q
Sr. No. Activity DAR
1 exceeding 1.5 m in width as EXCAVATION
well as 10 sqm on plan including getting
1.1 out and disposal of excavated earth upto 50 m and lift upto 1.5 m. 2.1
1.1.1 All kinds of soil 2.1.1

banks or filling up ground depressions, lead upto 50 m and lift upto 1.5
1.2 m 2.2
1.2.1 All kinds of soil 2.2.1

roads, flood banks, marginal banks, and guide banks etc., lead upto 50
1.3 m and lift upto 1.5 m 2.3
1.3.1 All kinds of soil 2.3.1

Deduct for not rolling with power roller of minimum 8 tonnes for banking
1.4 excavated earth in layers not exceeding 20 cm in depth. 2.4

1.5 Deduct for not watering the excavated earth for banking 2.5

Earth work in excavation by mechanical means (Hydraulic


excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m
in width as well as 10 sqm on plan) including getting out and disposal
of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by
1.6 Engineer-in-charge 2.6
Earth work in excavation by mechanical means (Hydraulic
excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m
in width as well as 10 sqm on plan) including getting out and disposal
of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by
1.7 Engineer-in-charge. 2.7
1.7.1 Ordinary rock 2.7.1
1.7.2 Hard rock (requiring blasting) 2.7.2

1.7.3 Hard rock (blasting prohibited) 2.7.3

Earth work in excavation by mechanical means (Hydraulic excavator) /


manual means in foundation trenches or drains (not exceeding 1.5 m in
width or 10 sqm on plan), including dressing of sides and ramming of
bottoms, lift upto 1.5 m, including getting out the excavated soil and
1.8 disposal of surplus excavated soil as directed, within a lead of 50 m. 2.8
(For all kinds of soil)

Excavation work by mechanical means (Hydraulic excavator)/ manual


means in foundation trenches or drains (not exceeding 1.5m in width or
10 sqm on plan), including dressing of sides and ramming of bottoms,
lift upto 1.5 m, including getting out the excavated soil and disposal of
1.9 surplus excavated soils as directed, within a lead of 50 m. 2.9
1.9.1 Ordinary rock 2.9.1
1.9.2 Hard rock (requiring blasting) 2.9.2

1.9.3 Hard rock (blasting prohibited) 2.9.3


Excavating trenches of required width for pipes, cables, etc including
excavation for sockets, and dressing of sides, ramming of bottoms,
depth upto 1.5 m, including getting out the excavated soil, and then
returning the soil as required, in layers not exceeding 20 cm in depth,
including consolidating each deposited layer by ramming, watering, etc.
and disposing of surplus excavated soil as directed, within a lead of 50
1.10 m 2.10
1.10.1 For all kinds of soil 2.10.1

1.10.1.1 Pipes, cables etc, not exceeding 80 mm dia. 2.10.1.1


Pipes, cables etc. exceeding 80 mm dia. but not exceeding 300 mm
1.10.1.2 dia 2.10.1.2

1.10.1.3 Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm 2.10.1.3

Extra for excavating trenches for pipes, cables etc. in all kinds of soil
for depth exceeding 1.5 m, but not exceeding 3 m. (Rate is over
1.11 corresponding basic item for depth upto 1.5 metre). 2.11
Extra for excavating trenches for pipes, cables, etc, in all kinds of soil
for depth exceeding 3 m in depth, but not exceeding 4.5 m. (Rate is
1.12 over corresponding basic item for depth upto 1.5 metre.) 2.12

Excavating trenches of required width for pipes, cables, etc, including


excavation for sockets, depth upto 1.5 m, including getting out the
excavated materials, returning the soil as required in layers not
exceeding 20 cm in depth, including consolidating each deposited
layers by ramming, watering etc., stacking serviceable material for
measurements and disposal of unserviceable material as directed,
1.13 within a lead of 50 m 2.13
1.13.1 Ordinary rock 2.13.1
1.13.1.1 Pipes, cables etc. not exceeding 80 mm dia 2.13.1.1

1.13.1.2 Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia 2.13.1.2
1.13.1.3 Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia 2.13.1.3

1.13.2 Hard rock (requiring blasting) 2.13.2


1.13.2.1 Pipes, cables etc. not exceeding 80 mm dia 2.13.2.1

1.13.2.2 Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia 2.13.2.2
Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm
1.13.2.3 dia 2.13.2.3

1.13.3 Hard rock (blasting prohibited) 2.13.3


1.13.3.1 Pipes, cables etc. not exceeding 80 mm dia 2.13.3.1

1.13.3.2 Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia 2.13.3.2
Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm
1.13.3.3 dia 2.13.3.3

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard


rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over
1.14 corresponding basic item for depth upto 1.5 metre) 2.14

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard


rock exceeding 3m in depth but not exceeding 4.5 m. (Rate is over
1.15 corresponding basic item for depth upto 1.5 metre) 2.15

Close timbering in trenches including strutting, shoring and packing


cavities (wherever required) complete. (Measurements to be taken of
1.16 the face area timbered). 2.16
1.16.1 Depth not exceeding 1.5 m 2.16.1
1.16.2 Depth exceeding 1.5 m but not exceeding 3 m 2.16.2
1.16.3 Depth exceeding 3 m but not exceeding 4.5 m 2.16.3

Close timbering in case of shafts, wells, cesspits, manholes and the


like including strutting, shoring and packing cavities (wherever
required) etc. complete. (Measurements to be taken of the face area
1.17 timbered). 2.17
1.17.1 Depth not exceeding 1.5 m 2.17.1
1.17.2 Depth exceeding 1.5 m but not exceeding 3 m 2.17.2
1.17.3 Depth exceeding 3 m but not exceeding 4.5 m 2.17.3

Close timbering over areas including strutting, shoring and packing


cavities (wherever required) etc. complete. (Measurements to be taken
1.18 of the face area timbered): 2.18
1.18.1 Depth not exceeding 1.5 m 2.18.1
1.18.2 Depth exceeding 1.5 m but not exceeding 3 m 2.18.2
1.18.3 Depth exceeding 3 m but not exceeding 4.5 m 2.18.3

Extra for planking, strutting and packing materials for cavities (in close
timbering) if required to be left permanently in position. (Face area of
1.19 timber permanently left to be measured) 2.19
Open timbering in trenches including strutting and shoring complete
1.20 (measurements to be taken of the face area timbered) 2.20
1.20.1 Depth not exceeding 1.5 m 2.20.1
1.20.2 Depth exceeding 1.5 m but not exceeding 3 m 2.20.2
1.20.3 Depth exceeding 3 m but not exceeding 4.5 m 2.20.3

Open timbering in case of shafts, wells, cesspits, manholes and the like
including strutting and shoring complete (Measurements to be taken of
1.21 the face area timbered): 2.21
1.21.1 Depth not exceeding 1.5 m 2.21.1
1.21.2 Depth exceeding 1.5 m but not exceeding 3 m 2.21.2
1.21.3 Depth exceeding 3 m but not exceeding 4.5 m 2.21.3

Open timbering over areas including strutting, shoring etc. complete.


1.22 (Measurements to be taken of the face area timbered): 2.22
1.22.1 Depth not exceeding 1.5 m 2.22.1
1.22.2 Depth exceeding 1.5 m but not exceeding 3 m 2.22.2
1.22.3 Depth exceeding 3 m but not exceeding 4.5 m 2.22.3

Extra for planking and strutting in open timbering if required to be left


permanently in position. (Face area of the timber permanently left to be
1.23 measured). 2.23

1.24 Extra rates for quantities of works, executed: 2.24


In or under water and/or liquid mud, including pumping out water as
1.24.1 required 2.24.1
1.24.2 In or under foul position, including pumping out water as required 2.24.2
Filling available excavated earth (excluding rock) in trenches, plinth,
sides of foundations etc. in layers not exceeding 20cm in depth,
consolidating each deposited layer by ramming and watering, lead up
1.25 to 50 m and lift upto 1.5 m. 2.25

Extra for every additional lift of 1.5 m or part thereof in excavation /


banking
1.26 excavated or stacked materials. 2.26
1.26.1 All kinds of soil 2.26.1
1.26.2 Ordinary or hard rock 2.26.2

Supplying and filling in plinth with sand under floors, including watering,
1.27 ramming, consolidating and dressing complete. 2.27

Surface dressing of the ground including removing vegetation and in-


equalities not exceeding 15 cm deep and disposal of rubbish, lead up
1.28 to 50 m and lift up to 1.5 m. 2.28
1.28.1 All kinds of soil 2.28.1

Ploughing the existing ground to a depth of 15 cm to 25 cm and


1.29 watering the same. 2.29
1.29.1 All kinds of soil 2.29.1

Excavating holes more than 0.10 cum & upto 0.5 cum including getting
out the excavated soil, then returning the soil as required in layers not
exceeding 20 cm in depth, including consolidating each deposited layer
by ramming, watering etc, disposing of surplus excavated soil, as
1.30 directed within a lead of 50 m and lift upto 1.5 m. 2.30
1.30.1 All kinds of soil 2.30.1
Clearing jungle including uprooting of rank vegetation, grass, brush
wood, trees and saplings of girth up to 30 cm measured at a height of 1
m above ground level and removal of rubbish up to a distance of 50 m
1.31 outside the periphery of the area cleared. 2.31

Clearing grass and removal of the rubbish up to a distance of 50 m


1.32 outside the periphery of the area cleared. 2.32

Felling trees of the girth (measured at a height of 1 m above ground


level), including cutting of trunks and branches, removing the roots and
1.33 stacking of serviceable material and disposal of unserviceable material. 2.33
1.33.1 Beyond 30 cm girth upto and including 60 cm girth 2.33.1
1.33.2 Beyond 60 cm girth upto and including 120 cm girth 2.33.2
1.33.3 Beyond 120 cm girth upto and including 240 cm girth 2.33.3
1.33.4 Above 240 cm girth 2.33.4

Supplying chemical emulsion in sealed containers including delivery as


1.34 specified. 2.34
1.34.1 Chlorpyriphos/ Lindane emulsifiable concentrate of 20% 2.34.1
Diluting and injecting chemical emulsion for POST-
CONSTRUCTIONAL antitermite treatment (excluding the cost of
1.35 chemical emulsion) 2.35

Extra for levelling & neatly dressing of disposed soil completely as


1.36 directed by Engineer-in-charge. 2.36

Supply and stacking of Fly ash conforming to IRC- 58 at site, including


carriage, loading , unloading & stacking up to any lead (measured
1.37 stacks will be reduced by 20% for payment). 2.37

Filling with available fly ash and earth (excluding rock) in trenches or
embankment in layers (each layer should not exceed 15 cm), with
intermediate layer of compacted earth (Soil density of 98%) after every
four layers of compacted depth of fly ash, sides & top layer of filling
shall be done with earth having total minimum compacted thickness 30
cm or as decided by Engineer - in-charge, including compacting each
layer by rolling/ ramming and watering, all complete as per drawing and
1.38 direction of Engineer -in - charge. 2.38
QUALITY
Description

Is the area to be excavated is cleared of all obstructions?


Check if the layout, alignment & size of excavation marked on the ground is as per the plan?
Check
Is if the excavated
the excavated soilplaced
materials is disposed to the specific
at a distance area?
of at least one metre or half the depth of
excavation, whichever is more and cleared off the edge of excavation?
In firm soils, is the sides of the trenches kept vertical upto a depth of 2 metres from the bottom?

The work shall be executed true to levels, slopes, shape and pattern as indicated in the drawings.
Is the natural drainage of the area maintained to avoid water logging?
Is
Is the
the bottom levelled
filling made withorearth
graded and
duly rammed properly
consolidated in case?of deeper excavation more than required
level ?
Unsuitable sub-grade material under embankments or below pavement layers has been removed
and replaced?

Is eachfilling
When layer has
uponbeen compacted
existing to 100%orMDD
embankments (Characteristic
hillsides, Value)
slopes of the original ground have been
terraced.
Trimming of embankments provide a neat finish of sub-grade surface. Waterways have been
cleared of debris resulting from the trimming operation.
the sub-base.

In case of special soils like marine clay, is the allowance for change in the original levels due to load of
an embankment is specified.

Is the banking have not been affected by water inflow


Contractor?
blinding concrete.
space available for employing these machines.)

Is Excavation in ordinary rock shall be carried out by crow Pars, pick axes, or pneumatic drills?
Explosives are stored in a secure place, clearly identified with warning signs.
Care has been taken to protect any permanent or temporary structures nearby while blasting.
methods to be adopted.
A warning siren is sounded before any shot is fired.
are not practicable.
Excavated rock suitable for stone pitching, gabions etc has been reserved if required.
Compaction has been continued until movement of the surface under the roller is negligible.
Rock cuts have been excavated to at least sub-grade level to a firm and reasonably uniform surfac

Is Excavation in ordinary rock shall be carried out by crow Pars, pick axes, or pneumatic drills?
Explosives are stored in a secure place, clearly identified with warning signs.
Care has been taken to protect any permanent or temporary structures nearby while blasting.
methods to be adopted.
A warning siren is sounded before any shot is fired.
are not practicable.
Excavated rock suitable for stone pitching, gabions etc has been reserved if required.
Compaction has been continued until movement of the surface under the roller is negligible.
Rock cuts have been excavated to at least sub-grade level to a firm and reasonably uniform surfac

Is Excavation in ordinary rock shall be carried out by crow Pars, pick axes, or pneumatic drills?
Explosives are stored in a secure place, clearly identified with warning signs.
Care has been taken to protect any permanent or temporary structures nearby while blasting.
methods to be adopted.
A warning siren is sounded before any shot is fired.
are not practicable.
Excavated rock suitable for stone pitching, gabions etc has been reserved if required.
Compaction has been continued until movement of the surface under the roller is negligible.
Rock cuts have been excavated to at least sub-grade level to a firm and reasonably uniform surfac

After pipes and cables are laid returning, filling and ramming is done?
Is the surplus soil present after returning, filling and ramming is removed?
Is earth used for filling is free from stone, shingle or boulder not larger than 75 mm in any direct
Is the width of the trench is arrived by adding 25 cm to the external diameter of the pipe (not
socket), cable, conduit, etc
Is the diameter taken is horizontal distance from outside to outside of outermost pipe, cable,
conduit, etc.
available, when depth of 30 cm is present above the crown of the pipe

Check trenches, the space around the foundations, pipes, drains, etc, is cleared of all debris,
brickbats, etc

Is the filling in trenches is done in layers not exceeding 20 cm in each layer.

Is the excavation exceeds 1.5m in width or 10 sqm. On plan and to any depth in trenches (excluding
trenches for pipes, cables, conduits etc.)
socket), cable, conduit, etc
Is the width of the trench is arrived by adding 25 cm to the external diameter of the pipe (not
socket), cable, conduit, etc
conduit, etc.

Is Explosives are stored in a secure place, clearly identified with warning signs.
Care has been taken to protect any permanent or temporary structures nearby.

Is the warning siren is sounded before any shot is fired?


If the work is accessible by the general public, before any shots are fired, knowledge of the
apparent danger must be conveyed to all persons in the area.
Check of existing structure within 200 m from Blasting operations site?.
amended from time to time.

are not practicable.

Excavated rock suitable for stone pitching, gabions etc has been reserved if required.
Compaction has been continued until movement of the surface under the roller is negligible.
Rock cuts have been excavated to at least sub-grade level to a firm and reasonably uniform surfac

Is the space alround the pipes, cables conduits etc. is cleared of all debris, brick bats etc

Where the trenches are excavated in hard/ soft soil, Is the filling done with earth on the side and
top of pipes in layers and not exceeding 20 cm in depth.
excavated earth is used for filling.
Is excavated material contains deleterious material, salt peter earth etc.

Are all trenches exceeding 2.0 m in depth is securely shored and timbered as determined by the
Engineer-in-charge?
Is approved quality of SAL wood is used for shoring and timbering a trench?
Is
or the
soil sheathing is held
which is under securely in
hydrostatic place against
pressure, thepiece
Is each wall of sheathing
the trench is
bydriven
wales?into the bottom of the
trench so as to be firmly held in place?
Are wedges provided between a wale and the sheathing so that rightly uniform support is given to all
individual pieces of sheathing?
Are the struts held securely in place by wedges, driven between struts and the wales?

Are all trenches exceeding 2.0 m in depth is securely shored and timbered as determined by the
Engineer-in-charge?
Is approved quality of SAL wood is used for shoring and timbering a trench?
Is the
or soil sheathing is held
which is under securely in
hydrostatic place against
pressure, thepiece
Is each wall of sheathing
the trench is
bydriven
wales?into the bottom of the
trench
Are so as provided
wedges to be firmly held inaplace?
between wale and the sheathing so that rightly uniform support is given to all
individual pieces of sheathing?
Are the struts held securely in place by wedges, driven between struts and the wales?

Are all trenches exceeding 2.0 m in depth is securely shored and timbered as determined by the
Engineer-in-charge?
Is approved quality of SAL wood is used for shoring and timbering a trench?
Is the
or soil sheathing is held
which is under securely in
hydrostatic place against
pressure, thepiece
Is each wall of sheathing
the trench is
bydriven
wales?into the bottom of the
trench
Are so as provided
wedges to be firmly held inaplace?
between wale and the sheathing so that rightly uniform support is given to all
individual pieces of sheathing?
Are the struts held securely in place by wedges, driven between struts and the wales?

Is the contractor responsible to take all necessary steps to prevent the sides of trenches from
collapse.
strutting arrangements and specifying the profile of excavation.
Charge
Are the boards placed in position vertically in pairs?
Are the planking and struting is positioned as one boards on either side of cutting.
spacing of 1.2 metres cross strutted with ballies, or as directed by Engineer-in-Charge.

Is a toe board provided to prevent material rolling down the slope and falling into the part of the trench
with vertical walls?
Is Approved quality of SAL wood is used for shoring and timbering a trench?
Is The
or sheathing
soil which heldhydrostatic
is under securely inpressure,
place against thepiece
Is each wall of
ofthe trench by driven
is sheathing wales?into the bottom of the
trench so as to be firmly held in place?
Are wedges provided between a wale and the sheathing so that rightly uniform support is given to all
individual pieces of sheathing?
Are the struts held securely in place by wedges, driven between struts and the wales?

Is a toe board provided to prevent material rolling down the slope and falling into the part of the trench
with vertical walls?
Is Approved quality of SAL wood is used for shoring and timbering a trench?
Is
or The sheathing
soil which heldhydrostatic
is under securely inpressure,
place against thepiece
Is each wall of
ofthe trench by driven
is sheathing wales?into the bottom of the
trench
Are so as provided
wedges to be firmly held inaplace?
between wale and the sheathing so that rightly uniform support is given to all
individual pieces of sheathing?
Are the struts held securely in place by wedges, driven between struts and the wales?

Is a toe board provided to prevent material rolling down the slope and falling into the part of the trench
with vertical walls?
Is Approved quality of SAL wood is used for shoring and timbering a trench?
Is The
or sheathing
soil which heldhydrostatic
is under securely inpressure,
place against thepiece
Is each wall of
ofthe trench by driven
is sheathing wales?into the bottom of the
trench
Are so as provided
wedges to be firmly held inaplace?
between wale and the sheathing so that rightly uniform support is given to all
individual pieces of sheathing?
Are the struts held securely in place by wedges, driven between struts and the wales?

In case
Are of open boards
the vertical planking and
250 mmstrutting,
wide & the entire
38 mm surface
thick, of the sufficiency
is spaced side of the apart
trenchtoisleave
covered?
unsupported
strips
Is the of 50 cmarrangement,
detailed average width.
sizes of the timber and the distance apart shall be subject to the approval
of the Engineer-in- Charge.

-
Normally
Earth excavated
used for filling earth from
shall be same
free fromarea shallrank,
shrubs, be used for filling.
vegetation, grass, brushwood, stone shingle and
boulders (larger than 75mm in any direction), organic or any other foreign matter.
Earth containing
All clods and lumps deleterious materials, salt
of earth exceeding 8 cmpeter earth
in any etc. shall
direction shallnotbebe used or
broken forremoved
filling. before the
earth is used for filling.

Are all useful materials obtained from clearing and grubbing operation is stacked in the manner as directed by the Engineer -in-
Are the trunks and branches of trees is cleared of limbs and tops and stacked neatly at places indicated by the Engineer-in- Ch
Are all unserviceable materials which in the opinion of the Engineer-in-Charge cannot be used or CPWD SPECIFICATIONS 20
Is it ensured by the contractor that unserviceable materials are disposed off in such a manner that there is no likelihood of gettin

Is Depth of filling shall be the consolidated depth ?


The dimensions of filling shall be on the basis of pre-measurement correct to the nearest cm and cubical content worked out in

Surface dressing shall include cutting and filling upto a depth of 15 cm and clearing of shrubs, rank
vegetation, grass, brushwood, trees and saplings of girth upto 30 cm measured at a height of one metre
above the ground level and removal of rubbish and other excavated material upto a distance of 50
metres outsideofthe
High portions theperiphery of the
ground shall bearea underand
cut down surface dressing
hollows depression filled upto the required level with
the excavated earth so as to give an even, neat and tidy look.

Is the dewatering of the waterlogged area done?


Check if the layout, alignment & size of excavation marked on the ground is as per the plan?
Is there adequate working spaces provided all around?
Is the founding strata is free from all the soft pockets? If not, remove and fill with lean concrete/sand.

Is the founding strata is free from all the soft pockets? If not, remove and fill with lean concrete/sand.
Check if the stability of side slopes acceptable?
Check if the excavated soil is disposed to the specific area?
Have the barricading & caution signs been provided for deep excavations?
Check if the joint inspection is done?

Is uprooting of rank vegetation, grass, brushwood, shrubs, stumps, trees and saplings of girth upto 30
cm measured
Check All holesator
a height
hollowsofformed
one metre
due above the ground
to removal of rootslevel.
shall be filled up with earth rammed and
levelled
Is the roots of trees and saplings is removed to a depth of 60 cm below ground level or 30 cm below
formation
Are levelmaterials
all useful or 15 cmobtained
below sub-grade level,and
from clearing whichever
grubbingisoperation
lower. is stacked in the manner as
directed by the Engineer -in-Charge.

Is removal of rubbish
SPECIFICATIONS upto46a auctioned
2019 distance ofis50 m outside
removed thea periphery
up to of 50
distance of themarea under
outside theclearance.
periphery of the
areathe
Are under clearance.
trunks and branches of trees is cleared of limbs and tops and stacked neatly at places indicated
byitthe
Is Engineer-in-
ensured by the Charge.
contractor that unserviceable materials are disposed off in such a manner that there
is no likelihood of getting mixed up with the materials meant for construction

While clearing jungle, Are the growth trees above 30 cm girth (measured at a height of one metre above
ground
Is level)
Felling treestoinclude
be cut, taking
is approved by the
out roots uptoEngineer-in-Charge and
60 cm below ground then
level ormarked at site.formation level or
30 cm below
15 cm
with below material
suitable sub-grade
in 20level,
cmwhichever
layers andiscompacted
lower. thoroughly so that the surfaces at these points
conform to the
Is the trunks andsurrounding
branches of area.
trees is cleared of limbs and tops and cut into suitable pieces as directed
by the Engineer-in-Charge.

Is the Chemical diluted with water in required quantity before it is used ?


Are the concentrated chemical is placed in a sealed container?
achieve the desired percentage of concentration?
issued for use to meet the day’s requirements ?
Are the chemicals of different types and concentration is placed separately.
day’s work is returned to the Engineer-in-Charge or his authorized representative?
These chemicals are available in concentrated form in the market and concentration is indicated
on the sealed containers.
proportion to achieve the desired percentage of concentration.
closed in stores so that children or pet cannot get at them
compacted in successive horizontal layers of loose material not more than 200 mm thick
day’s work shall be returned to the Engineer-in-charge or his authorized representative.
Is the use of chemical is prohibited near wells or other water supplies becoming contaminated.

Check if the dressing of the excavated area is good?


Check if the stability of side slopes acceptable?
Is the dewatering of the waterlogged area done?

Is the flyash is kept moist by sprinkling water to prevent dust?


Is the space around the foundation and drains in trenches is cleared of all debris, brick bats etc.
layers of compacted depth of flyash

Is the flyash is kept moist by sprinkling water to prevent dust?


Is the space around the foundation and drains in trenches is cleared of all debris, brick bats etc.
Is the filling with available excavated earth and flyash is done in regular horizontal layers?
to achieve soil density of 98%
layers of compacted depth of flyash
30 cm.
Yes/No References/ Remarks sl.no
er as directed by the Engineer -in-Charge.
s indicated by the Engineer-in- Charge.
d or CPWD SPECIFICATIONS 2019 46 auctioned is removed up to a distance of 50 m outside the periphery of the area under clearance.
r that there is no likelihood of getting mixed up with the materials meant for construction.

and cubical content worked out in cubic metres correct to two places of decimal.

e plan?

n concrete/sand.

n concrete/sand.
SAFETY
Activity Description Yes/No
hery of the area under clearance.
References/ Remarks
Sr. No. Activity
2 CONCRETE WORK
2.1

Providing and laying in position cement concrete of specified grade excluding the cost of
centering and shuttering - All work up to plinth level :

1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal


2.1.2 size
1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal
2.1.3 size)
1:2:4 (1 Cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 40 mm nominal
2.1.4 size)
1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal
2.1.5 size)
1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal
2.1.6 size)
1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal
2.1.7 size)
1:5:10 (1 cement : 5 coarse sand (zone-III): 10 graded stone aggregate 40 mm nominal
2.1.9 size)
2.1.10 1:5:10 (1 (1
1:2:3½:9 cement : 5 fine
ordinary sandcement
portland : 10 graded stone
: 2 Fly ash :aggregate
3½ coarse40sand
mm (zone-III)
nominal size)
: 9 graded
2.1.11 stone aggregate
1:2:3½:9 40 mm
(1 ordinary nominal
portland size): 2 Fly ash : 3½ coarse sand (zone-III) : 9 graded
cement
2.1.12 stone
fillets, aggregate 40etc.,
sunken floor mm upnominal size)
to floor five level, excluding the cost of centering, shuttering
2.2 and finishing
1:1½:3 (1 cement : 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal
2.2.1 size).
2.2.3 1:2:4 (1 Cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
2.2.4 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
1:5:10 (1 cement : 5 coarse sand (zone-III) : 10 graded stone aggregate 40 mm nominal
2.2.5 size).

2.3 Centering and shuttering including strutting, propping etc. and removal of form work for
2.3.1 Foundations, footings, bases for columns
Retaining walls, return walls, walls (any thickness) including attached pilasters,
2.3.2 buttresses, plinth and string courses fillets, kerbs and steps etc.
2.3.3 Columns, piers, abutments, pillars, posts and struts
Providing and laying cement concrete in kerbs, steps and the like at or near ground level
2.4 excluding the cost of centering, shuttering and finishing.
1:1½:3 (1 Cement: 1½ coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal
2.4.1 size)
Providing and fixing up to floor five level precast cement concrete string or lacing courses,
copings, bed plates, anchor blocks, plain window sills, shelves, louvers, steps, stair cases,
etc., including hoisting and setting in position with cement mortar 1:3 (1 Cement : 3 coarse
2.5 sand), cost of required Centering complete.
1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20mm nominal
2.5.1 size)
Providing and fixing at or near ground level precast cement concrete in kerbs, edgings
etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Cement : 3
2.6 coarse sand), including the cost of required centering, shuttering complete
1:1½:3 (1 Cement: 1½ coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal
2.6.1 size).
Providing and fixing up to floor five level precast cement concrete solid block, including
hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of
2.7 required centering, shuttering complete :
1:1½:3 (1 Cement: 1½ coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal
2.7.1 size)
Providing and fixing up to floor five level precast cement concrete hollow block, including
hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of
2.8 required centering, shuttering complete.
1:1½:3 (1 Cement: 1½ coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal
2.8.1 size) .

Precasting and placing in position 125 mm dia Bollards 600 mm high of required shape
including providing M.S. Pipe Sleeve 50 mm dia 300 mm long in the Bollard and M.S.
Pipes 40 mm dia and 450mm long with 150x150x6mm M.S. plate welded at bottom and
embedded 150mm in cement concrete 1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6
graded stone aggregate 20 mm nominal size), including necessary excavation of size
2.9 250x250x450mm deep for the same in bitumen/ concrete pavement at specified spacing
Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1
2.1 cement : 2 coarse sand (zone-III): 4 graded stone aggregate 12.5mm nominal size)
Providing and laying damp-proof course 50mm thick with cement concrete 1:2:4 (1
2.11 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 20mm nominal size).
Extra for providing and mixing water proofing material in cement concrete work in doses
2.12 by weight of cement as per manufacturer's specification

Providing & applying a coat of residual petroleum bitumen of grade of VG-10 of approved
quality using 1.7kg per square metre on damp proof course after cleaning the surface with
2.13 brushes and finally with apiece of cloth lightly soaked in kerosene oil.
Extra for concrete work in superstructure above floor V level for each four floors or part
2.14 thereof
Extra for laying concrete in or under water and/or liquid mud including cost of pumping or
2.15 bailing out water and removing slush etc. complete.
2.16 Extra for laying concrete in or under foul positions

Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand :
6 graded stone aggregate 20 mm nominal size) over 75mm thick bed of dry brick ballast
40 mm nominal size, well rammed and consolidated and grouted with fine sand, including
2.17 necessary excavation, levelling & dressing & finishing the top smooth.

Extra for addition of synthetic Polyester triangular fibre of length 12mm, effective diameter
10-40 microns and specific gravity of 1.34 to 1.40 in cement concrete/RCC/Flooring/water
retaining structures by using 125gms of synthetic Polyester triangular fibre for 50 Kg
2.18 cement used as per directions of Engineer-in-Charge.
Providing and laying in position ready mixed plain cement concrete, using fly ash and
cement content as per approved design mix and manufactured in fully automatic batching
plant and transported to site of work in transit mixer for all leads, having continuous
agitated mixer, manufactured as per mix design of specified grade for plain cement
concrete work, including pumping of R.M.C. from transit mixer to site of laying and curing,
excluding the cost of centering, shuttering and finishing, including cost of curing,
admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of
concrete, improve workability without impairing strength and durability as per direction of
the Engineer-in-charge. Note : (1) Excess/less cement used than specified in this item is
payable/ recoverable separately. (2) Fly ash conforming to grade I of IS 3812 (Part-1) only
be used as part replacement of OPC as per IS : 456. Uniform blending with cement is to
2.19 be ensured in accorda
2.19.1 All works upto plinth level
2.19.1.1 M-15 grade plain cement concrete (cement content considered @ 240 kg/cum)
2.19.1.2 M-10 grade plain cement concrete (cement content considered @ 220 kg/cum)
2.19.2 All works above plinth and upto floor V level
2.19.2.1 M-15 grade plain cement concrete (cement content considered @ 240 kg. / cum)
2.19.2.2 M-10 grade plain cement concrete (cement content considered @ 220 kg/cum)

Providing and laying in position ready mixed plain cement concrete, with cement content
as per approved design mix and manufactured in fully automatic batching plant and
transported to site of work in transit mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for plain cement concrete work,
including pumping of R.M.C. from transit mixer to site of laying and curing, excluding the
cost of centering, shuttering and finishing, including cost of curing, admixtures in
recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete,
improve workability without impairing strength and durability as per direction of the
Engineer-in-charge. Note : 1) Excess/less cement used than specified in this item is
2.20. payable/ recoverable separately
2.20.1 All works upto plinth level
2.20.1.1 M-15 grade plain cement concrete (cement content considered @ 240 kg/cum)
2.20.1.2 M-10 grade plain cement concrete (cement content considered @ 220 kg/cum)
2.20.2 All works above plinth and upto floor V level
2.20.2.1 M-15 grade plain cement concrete. (cement content considered @ 240 kg. /cum)
2.20.2.2 M-10 grade plain cement concrete (cement content considered @ 220 kg/cum)
Code as per QUALITY
DAR Description Yes/No
Is the specification for coarse and fine aggregate from natural sources for
concrete?
Is the Plain and reinforced concrete being used as per the Code of
practice?
What is the method of test used to determine the strength of concrete?
4.1 What is the method used for sampling and analysis of concrete?
What
Is the is the methodfor
specification of bitumen
measurement
felt forofwater
building and civil
proofing andengineering work?
damp proofing
given as per the standards

4.1.2

4.1.3 Have the preceding activities for ppc of the area completed?

4.1.4 Check if the formwork dimensions are acceptable?

4.1.5 Check if the mix proportion is as specified?

4.1.6 Is the placement & compaction done properly as specified?

4.1.8 Check if the finished level is as specified?

4.1.10 Is the surface finish acceptable?


4.1.11 Check if the curing is done properly?
4.1.12 Is
Arethethe
formwork & reinforcement
other preceding as per
activities like structural
fixing design?
of inserts, embedments
4.1.13 & service conduits, etc. Has been completed?
Is the support
4.2 Check to forms of
if the provision & access
rigidityplatforms
of the assembly acceptable?
& walkways is done
4.2.2 properly.
4.2.3 Check for the provision and working condition of concrete aids
4.2.5 group?

4.2.8 Is the readiness of concrete & finishing group done?

4.3
4.3.1 Is the slump of the concrete being poured is correct?

4.3.2 Is the continuous flow of concreted being ensured?


4.3.3 Check if the pouring height of concrete is acceptable?
Is there a proper vibration for the concrete to fit tightly against all the
4.4 surfaces, reinforcements & embedment?

4.4.1 Is the concrete blend being poured in separate layers?

4.5 Check for the correct use of plant & machinery by the labours.
Check if the concrete is being poured with an initial setting time of
4.5.1 cement?
4.6 Check for provision of construction joints, wherever necessary.
Is there levelling & finishing of the exposed concrete surface for
4.6.1 planar structures likes slabs & pavements done?

4.7

4.7.1 Check if the suitable curing arrangements are done.

Is the adequate amount of curing being ensured for the specified


4.8 period?
Check for inserts and embedments exposure that are flush with the
4.8.1 concrete surface

Check if there is a clear marking of location for service conduits &


4.9 fittings wherever applicable.
Is there corrective actions being taken for surface defects on exposed
4.1 concrete?

4.11 Check if the removal of forms and its cleaning done properly

4.12

4.13

4.14

4.15
4.16

4.17

4.18
4.19
4.19.1
4.19.1.1
4.19.1.2
4.19.2
4.19.2.1
4.19.2.2

4.20.
4.20.1
4.20.1.1
4.20.1.2
4.20.2
4.20.2.1
4.20.2.2
References/ Remarks
Sr. No. Activity
3 RCC
excluding the cost of centering, shuttering, finishing and reinforcement - All work up to
3.1 plinth level :
1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm
3.1.2 nominal size)
3.1.3 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)

abutments, posts and struts etc. above plinth level up to floor five level, excluding cost
3.2 of centering,
1:1.5:3 shuttering,
(1 cement finishing
: 1.5 coarse and reinforcement
sand(zone-III) :
: 3 graded stone aggregate 20 mm
3.2.2 nominal size)

cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5
3.3 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).

Providing and laying up to floor five level reinforced cement concrete in kerbs, steps
and the like excluding the cost of centering, shuttering, finishing and reinforcement
with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm
3.4 nominal size).

Reinforced cement concrete work in arches, archribs, domes, vaults, shells, folded
plate and roofs having slope more than 15° up to floor five level, excluding the cost of
centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse
3.5 sand (zone-III) : 3 graded stone aggregate 20 mm nominal size).

Reinforced cement concrete work in chimneys, shafts, up to floor five level , excluding
the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement :
3.6 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).
Reinforced cement concrete work in well-steining, excluding the cost of centering,
shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-
3.7 III) : 3 graded stone aggregate 20 mm nominal size).

Reinforced cement concrete work in vertical and horizontal fins individually or forming
box louvers, facias and eaves boards above plinth level up to floor five level,
excluding the cost of centering, shuttering, finishing and reinforcement with 1:1½:3 (1
3.8 cement : 1½ coarse sand(zone-III) : 3 graded stone aggregate 20mm nominal size).

Centering and shuttering including strutting, propping etc. and removal of form for all
3.9 heights :

Providing and fixing tie bolt, spring coil and plastic cone in wall shuttering complete as
3.10 per the direction of Engineer-in-charge.
3.10.1 12 mm dia. & 100 mm length
3.10.2 12 mm dia. & 150 mm length
3.10.3 20 mm dia. & 150 mm length
3.10.4 20 mm dia.& 225 mm length

Extra for additional height in centering, shuttering where ever required with adequate
bracing, propping etc., including cost of de-shuttering and decentering at all levels,
over a height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area
3.11 to be measured).

3.11.1 Suspended floors, roofs, landing, beams and balconies (Plan area to be measured)
Providing, hoisting and fixing above plinth level up to floor five level precast reinforced
cement concrete work in string courses, bands, copings, bed plates, anchor blocks,
plain window sills and the like, including the cost of required centering, shuttering but ,
excluding cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3
3.12 graded stone aggregate 20 mm nominal size).

Providing, hoisting and fixing up to floor five level precast reinforced cement concrete
in small lintels not exceeding 1.5m clear span up to floor five level, including the cost
of required centering, shuttering but , excluding the cost of reinforcement, with 1:1.5:3
(1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal
3.13 size).

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced
cement concrete in mouldings as in cornices, windows sills etc, including setting in
cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering
but, excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse
3.14 sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced
cement concrete in lintels, beams and bressumers, including setting in cement mortar
1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but ,
excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)
3.15 : 3 graded stone aggregate 20 mm nominal size)

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced
cement concrete in shelves, including setting in cement mortar 1:3 (1cement : 3
coarse sand), cost of required centering, shuttering and finishing with neat cement
punning on exposed surfaces but , excluding the cost of reinforcement, with 1:1.5:3 (1
3.16 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).
Providing, hoisting and fixing above plinth level up to floor five level precast reinforced
cement concrete in vertical & horizontal fins, individually or forming box louvers,
setting in cement mortar 1:2 (1 cement : 2 coarse sand), including the cost of required
centering, shuttering but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement :
3.17 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).

Providing precast cement concrete Jali 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4


graded stone aggregate 6mm nominal size ), reinforced with 1.6 mm dia mild steel
wire, including centering and shuttering, roughening cleaning, fixing and finishing in
cement mortar 1:3 (1 cement: 3 fine sand) etc. complete, excluding plastering of the
3.18 jambs, sills and soffits
3.18.1 50 mm thick
3.18.2 40 mm thick
3.18.3 25 mm thick

Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3
(1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal
size, including centering and shuttering complete but , excluding cost of
3.19 reinforcement.

Encasing rolled steel section in grillages with cement concrete 1:1.5:3 (1 cement : 1.5
coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size, including
3.20 centering and shuttering but, excluding cost of expanded metal and hangers.

Extra for providing and fixing expanded metal mesh of size 20x60 mm and strands
3.25 mm wide 1.6 mm thick weighing 3.64 kg per sqm for encasing of rolled steel
3.21 sections in beams, columns and grillages, excluding cost of hangers.

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing
3.22 in position and binding all complete upto plinth level.
3.22.1 Mild steel and Medium Tensile steel bars
3.22.2 Hard drawn steel wire
3.22.3 Cold twisted bars
3.22.4 Hot rolled deformed bars
3.22.5 Hard drawn steel wire fabric
3.22.6 Thermo-Mechanically Treated bars of grade Fe-500D or more.

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing
3.22A in position and binding all complete above plinth level.
3.22A.1 Mild steel and Medium Tensile steel bars
3.22A.2 Hard drawn steel wire
3.22A.3 Cold twisted bars
3.22A.4 Hot rolled deformed bars
3.22A.5 Hard drawn steel wire fabric
3.22A.6 Thermo-Mechanically Treated bars of grade Fe-500D or more

Smooth finishing of the exposed surface of R.C.C. work with 6 mm thick cement
3.23 mortar 1:3 (1 Cement : 3 fine sand).

Extra for rendering smooth the top of suspended floors, landings and staircases
(treads and risers) with cement mortar 1:2 (1 cement : 2 coarse sand), including a
floating coat of neat cement and protecting the surface with a layer of 7.5 cm of earth
laid over 15 mm of fine sand in case of suspended floor and bricks laid in mud mortar
in case of landings and steps, including subsequent removal and cleaning of the
3.24 same.

3.25 Providing and fixing in position copper plate as per design for expansion joints.

3.26 Providing and filling in position, blown bitumen in expansion joints.

Providing and filling in position bitumen mix filler of Proportion 80 kg. of hot bitumen, 1
3.27 kg. of cement and 0.25 cubic metre of coarse sand for expansion joints.
Providing and fixing in position 12mm thick bitumen impregnated fiber board
conforming to IS: 1838, including cost of primer, sealing compound Grade-A in
3.28 expansion joints.

Providing and fixing sheet covering over expansion joints with iron screws as per
3.29 design.
3.29.1 Non-asbestos fibre cement board 6 mm thick as per IS: 14862.
3.29.1.1 150mm wide
3.29.1.2 200mm wide

3.29.2 Aluminium fluted strips 3.15 mm thick.


3.29.2.1 150 mm wide
3.29.2.2 200 mm wide

3.29.3 Non-asbestos Cement bonded wood particle board 6mm thick as per IS : 14276
3.29.3.1 150 mm wide
3.29.3.2 200 mm wide

3.30 Add for plaster drip course/ groove in plastered surface or moulding to R.C.C. projectio
code as per
DAR Description Yes/No
5
5.1 Structural removal limits are clearly identified
5.1.2 the removal operation does not damage adjacent property
5.1.3 ypes of cement and pozzolan used in the RCC mix is in accordance with the job mix
Compaction equipment is operated at normal operating speeds
For rock foundations, all grouting is complete and surface irregularities are filled as specified.

5.2
5.2.2 Quality of the mix water complies with specified requirements.
Mix appears uniform or uniformity testing is conducted to verify uniformity.
Forms conform to the plan for obtaining vertical surfaces.
Mix is placed in a configuration that limits edge joints.

5.3 Production roller and special compaction equipment meet the specified requirements.
Production roller is used where possible.
Curing begins immediately after compaction
Form removal is accomplished without damage to the RCC

5.4 Cement and pozzolan are maintained in an uncontaminated dry condition..


Free fall is limited to 5 feet or less.
There is no mud or standing water on the bonding surface at the time of placement.
Forms are set to the planned line and grade and are well anchored and braced.

5.5 Forms conform to the plan for obtaining the required surfaces
Lifts are of a uniform thickness to produce the designed grade within allowable tolerances.
Production roller is used where possible
All edge joints are trimmed as specified.

5.6 Specified neat cement grout or bonding mortar is used.


All standing water is removed prior to applying the curing compound.
Vehicular traffic is prohibited if it causes damage to the RCC.
Tie wire is annealed and not less than 1.25mm in diameter.
Check for readiness of reinforcement to release for concreting

5.7 Elongation
Bars percent
are spliced andonlapped
gaugeas length
shownis 5.65
on theA Drawing or as approved by the
Engineer.
Concrete is not dropped from a height of more than 2 m which may cause
segregation. A tremie or approved pump is to be used to place from height.
Check that the concrete
Is the Reinforcement bent andis placed
fixed within the
in accordance withtime limits in indicated
the procedure the specification.
in IS 2502 :
1963 ?

5.8 Steel has the specified cover.


Reinforcement is inspected and approved before placement of concrete.
Reinforcement is cold bent around the appropriate pin diameter.
Verticality of forms, location of blockouts and cross-sectional dimensions of concrete elements cast, satisfy re

5.9
Is the Props for centering made of steel, timber posts or ballies?
Is Ballies
check rested squarely
of Wedges or otheron wooden
devices base below
is used plates the
or any other
props load bearing
to ensure material?
tight fitting again to
formwork?
check Steel plates used should have no projections of bolts and nuts?
Is all surfaces of shuttering, in contact with concrete,is treated with a non-staining mineral oil ?
Is suitable camber given for horizontal members?

5.10
5.10.1 Check for sealing of joints & holes in shutter forms
5.10.2 Check for assembly of scaffolds & shutters w.r.t. Shuttering schemes?
5.10.3 Check for readiness of shutter forms for release to fix reinforcement
5.10.4 Check for provision & arrangement of shuttering scheme

5.11

5.11.1 Forms conform to the plan for obtaining vertical surfaces.


Forms are set to the planned line and grade and are well anchored and braced
Check that formwork used for exposed surfaces has the correct surface finish.
Check formwork re-entrant angles are chamfered and corners filleted.
Check for rigidity and safety of the assembled forms
Check for cleaning of scaffolds & shutters (post-removal)
lines & grade in the drawings?
Check for proper stacking of scaffolds & shutters (post-removal)

Are heavy units like precast concrete members is stacked near the hoist
5.12 and the ramp?
signals?
hoist heavy pieces of stones, to place these in correct position?

5.13
and the ramp?
signals?
hoist heavy pieces of stones, to place these in correct position?

5.14
and the ramp?
signals?
hoist heavy pieces of stones, to place these in correct position?

5.15
and the ramp?
signals?
hoist heavy pieces of stones, to place these in correct position?

5.16
and the ramp?
signals?
hoist heavy pieces of stones, to place these in correct position?
5.17
and the ramp?
signals?
hoist heavy pieces of stones, to place these in correct position?

5.18 Are those involved in the manufacturing of precast panels trained in current
5.18.1 procedures and quality control processes?
5.18.2 Are the shop drawings (design documentation) completed for each panel?
5.18.3 Has
Is a manufacturer’s certificate
the concrete been of tested
correctly compliance provided
to ensure for every
its strength panel?
is as specified in
the shop drawings?
Have all structural components in the panel been inspected by a competent
person prior to casting?

The appropriate method of cutting steel has been used, surfaces are of the
5.19 required Classorand
Straightening corners
bending of rounded to a radius
steel is done of 2mm
by means of steady pressure and not
hammering unless the Engineer has approved the use
Welding and cutting equipment is of an approved type and of heat.
used in
accordance with manufacturers recommendations.
The steelwork has been trial assembled prior to despatch to the site.
Components are inspected and passed by the Engineer upon delivery.

The appropriate method of cutting steel has been used, surfaces are of the
5.20 required Classorand
Straightening corners
bending of rounded to a radius
steel is done of 2mm
by means of steady pressure and not
hammering
Welding andunless
cuttingthe Engineerishas
equipment approved
of an approvedthetype
use and
of heat.
used in
accordance with manufacturers recommendations.
The steelwork has been trial assembled prior to despatch to the site.
Components are inspected and passed by the Engineer upon delivery.

5.21 The mesh should be as specified by the engineer incharge?


It should have the standard capacity to hold?
Is skilled workers employed for mesh installation?
Is proper fixing done using iron nails?

5.22
5.22.1 Reinforcement steel placed as per structural drawing
5.22.2 Bar bending schedule prepared.
Connection
5.22.3 Placing ofdiameter,
of bar bars to existing
number,dowels checked
spacing matchfor alignment
with the construction
5.22.4 schedule.
5.22.5 Check rebars are straight.
5.22.6 Check hooks and bends are placed as specified by structural designer.
Lap length, position of lap is ok.
Check the clear cover and cover blocks

5.22A Maintain records and getting approval for additional reinforcement not
shown
5.22A.1 To checkin drawings.
the construction joint for proper concrete bonding before
5.22A.2 placing reinforcement
5.22A.3 Check for test reports for steel and approved brand.
5.22A.4 Identification color coding ok.
5.22A.5 Check the rebars are rust free and crack free
5.22A.6 Check minimum 1 inch clear distance is maintained between two bars.
Check the rods are tied properly with binding wire.

Check for smooth finish using spirit levels for undulations, cracks and
5.23 evenness/straightness in vertical and horizontal directions.
Ensure plastered surface is cured for the entire recommended period.
the ceiling from this level – it should be even at all points
Ensure plastering thickness is even at all points during plastering.
Ensure the button marking tiles are removed.

Ensure availability of specialized trowels to obtain different structural


5.24 finishes
Check for undulations and unevenness by using spirit levels.
period.
Ensure plastered surface is cured for the entire recommended period.
from plaster

5.25 pipeline
Any shipping device or stabilizers should be removed
Ensure that there are no foreign objects impeding the expansion joint
5.26 right direction
Check that all anchors and supports match the system drawings
Pipe supports and guides should allow for pipe movement
Make sure that the joints are all properly aligned
during shipping or installation

Check each anchor, guide, and support to make sure that no warping,
5.27 flexing, or loosening has occurred
joint moves
Look for any signs of leaking or depressurization

5.28 Record any damage that has been sustained since installation
directions
Ensure that there are no foreign objects impeding the expansion joint

5.29
5.29.1
5.29.1.1
5.29.1.2

5.29.2
5.29.2.1
5.29.2.2

5.29.3
5.29.3.1
5.29.3.2

5.30
References/ Remarks
elements cast, satisfy required tolerances.
.
Code as per
Sr. No. Activity DAR
4 3
4.1 Cement mortar 1:1 (1 cement : 1 fine sand) 3.1
4.2 Cement mortar 1:2 (1 cement : 2 fine sand). 3.2
4.3 Cement mortar 1:2 (1 cement : 2 fine sand). 3.3
4.4 Cement mortar 1:4 (1 cement : 4 fine sand). 3.4
4.5 Cement mortar 1:5 (1 cement : 5 fine sand). 3.5
4.6 Cement mortar 1:6 (1 cement : 6 fine sand). 3.6
4.7 Cement mortar 1:2 (1 cement : 2 coarse sand). 3.7
4.8 Cement mortar 1:3 (1 cement : 3 coarse sand). 3.8
4.9 Cement mortar 1:4 (1 cement : 4 coarse sand). 3.9
4.10 Cement mortar 1:5 (1 cement : 5 coarse sand). 3.10
4.11 Cement mortar 1:6 (1 cement : 6 coarse sand). 3.11
4.12 Cement mortar 1:2 (1 cement : 2 stone dust). 3.12
4.13 Cement mortar 1:2 (1 cement : 2 marble dust). 3.13
4.14 Cement mortar 1:5 (1 cement : 5 marble dust). 3.14
4.15 White cement mortar 1:2 (1 white cement : 2 marble dust). 3.15
4.16 White cement mortar 1:3 (1 white cement : 3 marble dust). 3.16
4.17 White cement mortar 1:5 (1 white cement : 5 marble dust) 3.17
4.18 Mud mortar 3.18
4.19 Mortar in lime, surkhi (50% red and 50% light yellow) and
3.19
marble dust 1:1.5:0.5
Description Yes/No
Are all used
Water the field and laband
for mixing tests beenshall
curing conducted?
be clean and free from injurious quantities of alkalies,
acids, oils, salts, sugar, organic materials, vegetable growth
Proportion of mix ?
Addition of water proofing compound
Check the mortar preparation and mix consistency
Application of cement slurry on concrete surface/Space for tile area, cutting for skirting area
Material stacked – Cement, sand at various locations?
Cleaning of dead mortar
Check strength of mortar by scratching with sharp instrument like screw driver.
Check quality of sand in mortar. (Test for fineness modulus and silt content).
Check mixing of mortar whether done by hand or by machine, whether mixing is done on a proper platform.
check Quality of Sand – screening silt ?
Check for collection of mortar spills
References/ Remarks
CPWD 2019 Specs, Pg 63. 1 IS 269
2 IS 383
3 IS 455
4 IS 460 (Part I)
5 IS 650
6 IS 1269
7 IS 1344
8 IS 1489
9 IS 1542
10 IS 1727
11 IS 2116
12 IS 2250
13 IS 2386 (Pt-I)
14 IS 2386 (Pt-II)
15 IS 2386 (Pt-III)
16 IS 3025
17 IS 3406
18 IS 3812 (Pt-I)
19 IS 3812 (Part II)
20 IS 4031 (Part I) t
21 IS 4032
22 IS 8041
23 IS 8042
24 IS 8043
25 IS 8112
26 IS 11652
27 IS 11653
28 IS 12174
LIST OF BUREAU OF INDIAN STANDARD CODES
Specification for 33 grade ordinary Portland cement
Specification for coarse and fine aggregate from natural source for concrete
Specification for Portland slag cement
Specification for test sieves: wire cloth test sieves
Specification for standard sand for testing of cement
Specification for 53 grade ordinary Portland cement
Specification for calcined clay Pozzolana.
Specification for Portland pozzolana cement
Specification for sand for plaster
Methods of Test for Pozzolanic materials
Specification for sand for masonry mortar.
Code of practice for preparation and use of masonry Mortar.
Method of test for aggregate for concrete (Particle size and shape)
Do- Estimation of deleterious materials and organic impurities.
-Do- Specific gravity, density, voids, absorption and bulking
Method of sampling and test for water
Specification for masonry cement.
Specification for fly ash for use as pozzolana in cement mortar and concrete
Specification for flyash for use as admixture in cement mortar and concrete
Method of Physical test for hydraulic cement
Method of chemical analysis of Hydraulic cement.
Rapid hardening Portland cement.
Specification for white cement
Hydrophobic Portland cement
Specification for 43 grade ordinary Portland cement
Woven HDPE sacks for packing cement
Woven polypropylene sacks for packing cement
Jute synthetic union bags for packing cement
Sr. No. Activity Description Yes/No
References/ Remarks
QUAL

Sr. No. Activity


5 BRICKWORK
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in
foundation and plinth in:
5.1

5.1.1 Cement mortar 1:4 (1 cement : 4 coarse sand)


5.1.2 Cement mortar 1:6 (1 cement : 6 coarse sand)

5.2

Brick work with common burnt clay modular bricks of class designation 7.5 infoundation and
plinth in:
5.2.1 Cement mortar 1:4 (1 cement : 4 coarse sand)

5.2.2 Cement Mortar 1:6 (1 cement : 6 coarse sand).


5.3 Brick work with common burnt clay machine moulded perforated bricks of class designation
12.5 conforming to IS: 2222 in superstructure above plinth level up to
floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) :
5.3.1 With F.P.S.(non modular) bricks
5.3.2 With Modular bricks
5.4
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in
superstructure above plinth level up to floor V level in all shapes
and sizes in :

5.4.1 Cement mortar 1:4 (1 cement : 4 coarse sand)

5.4.2 Cement mortar 1:6 (1 cement : 6 coarse sand)


5.5 Extra for brick work / AAC block masonry / Tile brick masonry in superstructure above floor
V level, for each four floors or part thereof by mechanical means.
5.6 Extra for forming cavity 5 cm to 11.5 cm wide in cavity walls with necessary weep and vent
holes including use of cores and cost of providing and fixing bitumastic
coated M .S. ties 300 mm long of 25x3 mm section at not less than 3 ties per sqm
as per approved design.
5.7 Providing half brick masonry with common burnt clay F.P.S. (non modular) bricks of class
designation 7.5 in cement mortar 1:3 (1 Cement : 3 coarse sand) in
superstructure for closing cavity 5 to 7.5 cm wide in cavity wall complete with 10
cm / 11.4 cm wide bitumen felt type 3 grade 1.
Brick work 7 cm thick with common burnt clay F.P.S. (non modular) brick of class
designation 7.5 in cement mortar 1:3 (1 cement : 3 coarse sand) in superstructure above
5.8 plinth level and upto floor five level.
5.9 Brick work in plain arches in superstructure above plinth level and upto floor five level
including centering and shuttering complete for span up to 6 metres with
common
shutteringburnt clay F.P.S.
complete, (non
for span upmodular)
to 6 meters with common burnt clay F.P.S. (non
5.10 modular) bricks of class designation 7.5.

Extra for additional cost of centering for arches exceeding 6m span including all
5.11 shuttering,
Half bolting, wedging
brick masonry with common and removal
burnt clay(Area
F.P.S.of the soffit
(non to be measured).
modular) bricks of class
5.12 designation 7.5 in foundations and plinth in :
5.12.1 Cement mortar 1:3 (1 cement : 3 coarse sand)
5.12.2 Half
Cementbrickmortar
masonry1:4 with
(1 cement
common : 4 burnt
coarseclaysand)
F.P.S. (non modular) bricks of class
5.13 designation 7.5 in superstructure above plinth level up to floor V level.
5.13.1 Cement mortar 1:3 (1 cement :3 coarse sand)
5.13.2 Cement
Extra formortar 1:4masonry
half brick (1 cement in :4 coarse sand) above floor V level for every four
superstructure,
5.14 floors or part thereof by mechanical
Extra for providing and placing in position means. 2 Nos 6mm dia. M.S. bars at every
5.15 thirdbrick
Tile course of half with
masonry brickcommon
masonry.burnt clay F.P.S. (non modular) tile bricks of
5.16 class designation 10 in foundation and plinth in:
5.16.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
5.16.2 designation
Cement mortar 12.51:6 (1 cementto: 6IScoarse
conforming : 2690sand)
(Part I) in foundation and plinth in cement
5.17 mortar 1:6 (1 cement : 6 coarse sand).
class designation 10 in superstructure above plinth level up to floor V level in
5.18 cement
floor fivemortar
level in1:6 (1 cement
cement : 61:4
mortar coarse sand).: 4 coarse sand) including centering
(1 cement
5.20 and shuttering
floor five level incomplete.
cement mortar 1:4 (1 cement : 4 coarse sand) including centering
5.21 andbricks
tile shuttering complete.
of class designation 10 in cement mortar 1:3 (1 cement : 3 coarse sand)
5.22 in superstructure
designation 7.5 inabove
super plinth andabove
structure upto floor
plinthfive level.
level upto floor V level with cement
5.23 mortar 1:4 (1 cement : 4 coarse sand).
Extra for laying brick work in or under water and/or liquid mud including cost of
5.24 pumping or bailing out water and removing slush etc. complete.
5.25 Extra for 10
grooves laying
mm brick
wide work12 mm in or
deepunder foul position.
complete in cement mortar 1:6 (1 cement : 6
5.26 coarse sand)
5.26.1 From ground level upto plinth level
5.26.2 exposed
Above plinth bricklevel
workupto floor Vmaking
including level horizontal and vertical grooves 10mm wide
5.27 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand).
5.27.1 From ground level upto plinth level
5.27.2 grooves
Above plinth10 mm level upto
wide 12floor
mmVdeep levelcomplete in cement mortar 1:6 (1 cement : 6
5.28 coarse sand).
5.28.1 From ground level upto plinth level
5.28.2 Above
horizontalplinth
andlevel uptogrooves
vertical floor V level
10 mm wide 12 mm deep complete in cement
5.29 mortar 1:6 (1 cement : 6 coarse sand).
5.29.1 From ground level upto plinth level
5.29.2 work
Aboveincluding
plinth level upto horizontal
making floor V leveland vertical grooves 10mm wide 12 mm deep
5.30 complete in cement mortar 1:6 (1 cement : 6 coarse sand).
5.30.1 From ground level upto plinth level
5.30.2 Above
makingplinth level and
horizontal uptovertical
floor V grooves
level 10 mm wide 12mm deep complete in cement
5.31 mortar 1:6 (1 cement : 6 coarse sand).
5.31.1 From ground level upto plinth level
5.31.2 Brick
Abovework plinth level
with clayupto floorF.P.S.
flyash V level(non modular) brick of class designation 7.5 in
5.32 superstructure above plinth level up to floor five level in :
5.32.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
5.32.2 Cement
designation mortar 1:6 (1 cement
10 average : 6 coarse
compressive sand)in super structure above plinth level
strength
5.34 up to floor V level in :
5.34.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
5.34.2 Cement mortar 1:6 (1 cement : 6 Coarse sand)
IS:4139, class designation 10 average compressive strength in super structure
5.35 above plinth level up to floor V level in :
5.35.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
5.35.2 Brick
Cement mortar
work 1:6 (1 cement
with modular : 6 Coarse
extruded brunt flysand)
ash clay sewer bricks (Conforming to
5.36 IS: 4885 ) in foundation and plinth :
5.36.1 Cement
IS : 4885)mortar 1:4 (1
in arches in cement : 4 coarse
foundation sand)
and plinth in cement mortar 1:3 ( 1 cement : 3
5.37 fine sand).
mortar 1:4 (1 cement : 4 coarse sand ). The rate includes providing and placing in
5.38 position 2 Nosin6 superstructure
specifications mm dia M.S. bars aboveat every
plinththird
levelcourse of masonry
up to floor V level. work.
Gypsum
5.40 blocksfor
Extra willGypsum
have a panel
minimum compressive
Partitions strength ofabove
in superstructure 9.3 kg/cm2
floor V level for every
5.41 four floors
F.P.S. (nonormodular)
part thereof.
bricks of class designation 7.5 including grouting with cement
5.44 mortar
Half 1:4masonry
brick (1 cement : 4non
with finemodular
sand). fly ash bricks of class designation 10,
5.45 conformingio IS :12894, in super structure above plinth and upto floor V level.
5.45.1 Cement mortar 1 : 3 (1 cement : 3 coarse sand)
5.45.2 modified
Cement mortar
adhesive 1:4 (1 cement
mortar : 4 coarse
all complete sand)
as per direction of Engineer-in-Charge. (The
5.47 payment of RCC band and reinforcement shall be made for seperately).
QUALITY
Code as per
DAR Description Yes/No
6

6.1 Is there availability of bricks as per daily requirements?


Is the work area cleaned off of the loose mortar, concrete,
debris, etc on the end of each day?
6.1.1 Is the alignment & location of masonry as specified?
6.1.2 Is the suitability & safety of scaffolding acceptable?
Check for wetting of bricks before using it
Check if the mortar mix proportion & joint thickness are as
specified.
Are the bricks being laid up with their frogs up?
Are the dimensions, plumb level & right angles are as
specified?

6.2 Check if there is a proper bond between old & new masonry.
6.2.1 Is the staggering of vertical joints being ensured?
Check for the sizes of door & window openings as per the
6.2.2 drawings.
Check for cleaning & raking of joints
Check if the curing for old masonry is done sufficiently.
6.3 Check for removal of debris.
6.3.1 Are all the tests conducted before the progress of brickwork?
6.3.2 Are the bricks free from cracks, flaws and nodules of free lime?
Are they of uniform colour and texture?
Is the mortar for brickwork as specified and conforms to the
accepted standards?
Are the bricks soaked in water sufficiently for the water to just
6.4 penetrate the whole depth of bricks?
Are the cross joints and wall joints properly flushed and packed
6.4.1 with mortar to avoid hollow spaces?
Are the openings such that it would reduce the cutting of bricks to a
6.4.2 minimum?
6.5

6.6

6.7
6.8
Are uncut bricks used in plain arches?
Is
Thethecentering
thicknessand
of joints between
shuttering 5 mm
for the to 15
arches is mm? SP 62 (S & T) : 1997
6.9 approved by the Authority?
6.10 Are modular bricks used? SP 62 (S & T) : 1997
Are bricks laid with radial joints to the full depth of arch and
voussoirs breaking jonts with each other
6.11
6.12
6.12.1
6.12.2
6.13
6.13.1
6.13.2
6.14
6.15
6.16
6.16.1
6.16.2
6.17
6.18
6.20
6.21
6.22
6.23
6.24
6.25
6.26
6.26.1
6.26.2
6.27
6.27.1
6.27.2
6.28
6.28.1
6.28.2
6.29
6.29.1
6.29.2
6.30
6.30.1
6.30.2
6.31
6.31.1
6.31.2
6.32
6.32.1
6.32.2
6.34
6.34.1
6.34.2
6.35
6.35.1
6.35.2
6.36
6.36.1
6.37
6.38
6.40
6.41
6.44
6.45
6.45.1
6.45.2
6.47
References/ Remarks Sr. No. Activity

IS 2222
IS 2222
SAFETY

Description Yes/NoReferences/ Remarks


Sr. No.
6

6.1

6.1.1
6.2
6.2.1
6.4
6.4.1
6.4.2
6.5
6.6
6.6.1
6.7
6.7.1
6.8
6.8.1
6.8.2
6.10
6.10.1
6.10.2
6.11

6.12

6.12.1
6.12.1.1
6.12.1.2
6.12.2
6.12.2.1
6.12.2.2
6.13
6.13.1
6.13.1.1
6.13.1.2
6.13.2
6.13.2.1
6.13.2.2
6.14
6.14.1
6.14.1.1
6.14.1.2
6.14.2
6.14.2.1
6.14.2.2
6.15
6.15.1
6.15.1.1
6.15.1.2
6.15.2
6.15.2.1
6.15.2.2
6.16
6.17
6.17.1
6.18
6.19
6.20
6.20.1
6.20.2
6.21
6.21.1
6.21.2
6.22
6.23
6.23.1
6.23.1.1
6.23.1.2
6.23.1.3
6.23.1.4
6.23.1.5
6.23.2
6.23.2.1
6.23.2.2
6.23.2.3
6.23.2.4
6.23.2.5
6.23.3
6.23.3.1
6.23.3.2
6.23.3.3
6.23.3.4
6.23.3.5
6.23.4
6.23.4.1
6.23.4.2
6.23.4.3
6.23.4.4
6.23.4.5
6.23.5
6.23.5.1
6.23.5.2
6.24
6.25
6.26
6.27
6.28
6.28.1
6.28.1.1
6.28.2
6.28.2.1
6.29
6.29.1
6.29.2
6.30
6.31
6.32
6.32.1
6.32.2
6.33
6.33.1
6.33.2
6.34
6.35
6.36
6.37
6.37.1
6.37.1.1
6.38
6.38.1
6.38.1.1
6.38.1.2
6.39
6.40
6.40.1
6.40.2

6.41
6.42
QUALITY
Activity
STONEWORK

levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded


stone aggregate 20 mm nominal size) upto plinth level with :

:Cement
6 coarse mortar
sand 1:6
: 12(1graded
cement : 6 coarse
stone sand)
aggregate 20 mm nominal size) at window sills,
ceiling level and the like.
Cement mortar 1:6 (1 cement : 6 coarse sand)
Extra for random rubble masonry with hard stone in :
Square or rectangular pillars
Circular
Extra forpillars
random rubble masonry with hard stone curved on plan for a mean
radius not exceeding 6 m.
Coursed rubble masonry (first sort) with hard stone in foundation and plinth with :
Cement mortar 1:6 (1 cement : 6 coarse sand)
Coursed rubble masonry (second sort) with hard stone in foundation & plinth with :
Cement mortar
Coursed rubble 1:6 (1 cement
masonry : 6 coarse
with hard stonesand)
(first or second sort) in superstructure
above plinth level and upto floor five level.
Masonry work (first sort), in cement mortar 1:6 (1 cement : 6 coarse sand)
Masonry work (second sort), in cement mortar 1:6 (1 cement: 6 coarse sand)
Extra for coursed rubble masonry with hard stone (first or second sort) in:
Square or rectangular pillars
Circular
Extra forpillars
coursed rubble masonry with hard stone (first or second sort) curved on
plan for a
Stone work mean radius
in plain not in
ashlar exceeding 6 m. upto floor five level in cement mortar
super structure
1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white
cement : 2 stone dust) with an admixture of pigment matching the stone shade :

One face dressed


Red sand stone
White sand stone
Both face dressed
Red sand stone
Whitewhite
with sandcement
stone mortar 1:2 (1 white cement : 2 stone dust) with an admixture of
pigment matching the stone shade.
One face dressed
Red sand stone
White sand stone
Both face dressed
Red sand stone
Whitewhite
with sandcement
stone mortar 1:2 (1 white cement : 2 stone dust) with an admixture of
pigment matching the stone shade.
One face dressed
Red sand stone
White sand stone
Both face dressed
Red sand stone
White
1:2 (1 sand
white stone
cement : 2 stone dust) with an admixture of pigment matching the stone
shade.
One face dressed
Red sand stone
White sand stone
Both faced punched
Red sand stone
White for
Extra sand stone
stone work, random rubble / coursed rubble masonry / ashlar masonry
above floor V level for every four floors or part thereof.
Extra for plain ashlar or ashlar punched in :
Square
Extra fororstone
rectangular pillars
work; plain ashlar or ashlar punched curved on plan with a mean
radius not exceeding 6 m.
Extra for additional cost of centering for arches exceeding 6m span including all
strutting,
mortar 1:2bolting, wedging
(1 white cementetc.
: 2 and removal
stone (area
dust) with anof soffit to be
admixture of measured).
pigment matching the
stone shade :
Red sand stone
White sand stone
Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in :
Triangular or Square or rectangular pillars
Circular or polygonal pillars
Extra
to the for stoneand
backing workthe
ashlar
sidessunk or moulded
by means in cornices.
of cramps and pins which shall be paid for
separately) :
Red sand stone - exposed face fine dressed with rough backing.
70 mm thick
60 mm thick
50 mm thick
40 mm thick
30 mm thick
Red sand stone - Exposed face machine cut and table rubbed with rough backing.
70 mm thick
60 mm thick
50 mm thick
40 mm thick
30 mm thick
White sand stone - exposed face fine dressed with rough backing .
70 mm thick
60 mm thick
50 mm thick
40 mm thick
30 mm thick
White sand stone - Exposed face machine cut and table rubbed with rough backing
70 mm thick
60 mm thick
50 mm thick
40 mm thick
30 mm thick
Gang saw cut stone
30mm thick White sand stone
30mm
Extra forthick Redwork
stone sand(veneer
stone work) curved on plan with a mean radius not
exceeding 6 m.
wall lining in cement mortar 1:2 (1 cement : 2 coarse sand), including making the
necessary
per design chases
in cementin stone
mortarand
1:2holes in walls
(1 cement : 2wherever required.
coarse sand), including making the
necessary
stones chases.
in stone wall lining in cement mortar 1:2 (1 cement : 2 coarse sand),
including: 4making
cement coarsethe necessary
sand), chases.
including pointing in cement mortar 1:2 (1 white cement :
2 stone dust) with an admixture of pigment matching the stone shade :
Red sand stone :
With common burnt clay F.P.S.(non modular) bricks of class designation 7.5
White sand stone :
With common
white burnt clay
cement mortar 1:2 F.P.S.(non modular)
(1 white cement bricksdust)
: 2 stone of class
with designation 7.5
an admixture of
pigment matching the stone shade :
Red sand stone
White sand
brackets, stone
fixed in walls with cement mortar 1:4 (1 cement : 4 coarse sand), including
finishing complete.
including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm long
and dowel
with bars 7.5mortar
white cement cm long1:26(1
mm dia cement
white as per design.
: 2 stone dust) with an admixture of
pigment matching the stone shade.
Red sand stone
White
cementsand stonedust) with an admixture of pigment, matching the stone shade,
: 2 stone
jali slab without any chamfers etc.
Red sand stone
White for
Extra sand stone
laying stone work in or under water and/or liquid mud including cost of
pumping or bailing out water and removing slush etc. complete.
Extra for laying stone work in or under foul position
Wall lining butch work upto 10m height with Dholpur stone 40 mm thick rough
facing on the exposed surface with stone strips of minimum length 300 mm and
required width, including embedding every tenth layer and bottom most layer in
masonry or concrete after making necessary chases of size 75x75 mm and by
providing layer of 75 mm thick strips i/c 12 mm thick bed of cement mortar 1:3 (1
Cement : 3 coarse sand) i/c ruled pointing in cement mortar 1:2 (1 white cement :2 stone dust) with
an admixture of pigment to match the shade of stone complete
as per direction
rubbing of Engineer-in-charge.
and polishing complete. (To be secured to the backing and the sides by
means of cramps and pins which shall be paid for separately).
Kota stone slabs exposed face dressed and rubbed.
25 mm
thick bedthick
of cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in
white cement with an admixture of pigment to match the stone shade.
8mm thick (mirror polished and machine cut edge)
Granite stone of any colour and shade
Raj Nagar plain white marble/ Udaipur green marble/ Zebra black marble
Extra for stoneofwork
and direction for wall lining on(The
Engineer-in-charge. exterior
steelwalls
frameof work,
heightstainless
more steel cramps
and pins etc. shall be paid for separately).
Red sand stone - 30mm thick gang saw cut stone
White sand stone - 30mm thick gang saw cut stone

Providing and fixing structural steel frame (for dry cladding with 30 mm thick
gang saw cut with machine cut edges sand stone) on walls at all heights using
M.S. square/ rectangular tube in the required pattern as per architectural drawing,
including cost of cutting, bending, welding etc. The frame work shall be fixed to
the wall with the help of M.S. brackets/ lugs of angle iron/ flats etc. which shall be
welded to the frame and embedded in brick wall with cement concrete block 1:2:4
(1 cement :2 coarse sand :4 graded stone aggregate 20 mm nominal size) of size
300x230x300 mm, including cost of necessary centring and shuttering and with
approved expansion hold fasteners on CC/RCC surface, including drilling
necessary holes. Approved cramps/ pins etc. shall be welded to the frame work
to support stone cladding, the steel work will be given a priming coat of Zinc primer as approved by
Engineer-in-charge and painted with two or more coats of epoxy paint (Shop drawings shall be
submitted by the contractor to the Engineerin- charge for approval before execution). The frame work
shall be fixed in true horizontal & vertical lines/planes. (Only structural steel frame work shall be
measured for the purpose of payment, stainless steel cramps shall be paid for separately and
nothing
at extra
suitable shall be
location, paid). making necessary recesses in stone slab, drilling
including
required holes etc complete as per direction of the Engineer-in-charge.
Code as perQUALITY
DAR
7

7.1

7.1.1
7.2
7.2.1
7.4
7.4.1
7.4.2
7.5
7.6
7.6.1
7.7
7.7.1
7.8
7.8.1
7.8.2
7.10
7.10.1
7.10.2
7.11

7.12

7.12.1
7.12.1.1
7.12.1.2
7.12.2
7.12.2.1
7.12.2.2
7.13
7.13.1
7.13.1.1
7.13.1.2
7.13.2
7.13.2.1
7.13.2.2
7.14
7.14.1
7.14.1.1
7.14.1.2
7.14.2
7.14.2.1
7.14.2.2
7.15
7.15.1
7.15.1.1
7.15.1.2
7.15.2
7.15.2.1
7.15.2.2
7.17
7.17
7.17.1
7.18
7.19
7.20
7.20.1
7.20.2
7.21
7.21.1
7.21.2
7.22
7.23
7.23.1
7.23.1.1
7.23.1.2
7.23.1.3
7.23.1.4
7.23.1.5
7.23.2
7.23.2.1
7.23.2.2
7.23.2.3
7.23.2.4
7.23.2.5
7.23.3
7.23.3.1
7.23.3.2
7.23.3.3
7.23.3.4
7.23.3.5
7.23.4
7.23.4.1
7.23.4.2
7.23.4.3
7.23.4.4
7.23.4.5
7.23.5
7.23.5.1
7.23.5.2
7.24
7.25
7.27
7.27
7.28
7.28.1
7.28.1.1
7.28.2
7.28.2.1
7.29
7.29.1
7.29.2
7.30
7.31
7.32
7.32.1
7.32.2
7.33
7.33.1
7.33.2
7.34
7.35
7.37
7.37
7.37.1
7.37.1.1
7.38
7.38.1
7.38.1.1
7.38.1.2
7.39
7.40
7.40.1
7.40.2

7.41
7.42
QUALITY
Description Yes/No
Is there availability of size stones as per daily requirements?
Are the hearting, bond, quoin & face stones properly hammer dressed to get desirable shapes?
Is the alignment & location of masonry as desired?
Is the wetting of size stones being ensured?
Is the mortar mix proportion as specified?
Is the staggering of vertical joints being ensured?
Is the thickness of mortar joints are as specified in the drawing?
Are the dimensions & levels as per drawings?
Is the packing of interstices within masonry with stone chips are done effectively?
Is the cleaning & raking of joints being done properly?
Is the cleaning of dead mortar completed?
Is the curing done properly?
Is there availability of size stones as per daily requirements?
Are the hearting, bond, quoin & face stones properly hammer dressed to get desirable shapes?
Is the alignment & location of masonry as desired?
Is the wetting of size stones being ensured?
Is the mortar mix proportion as specified?
Is the staggering of vertical joints being ensured?
Is the thickness of mortar joints are as specified in the drawing?
Are the dimensions & levels as per drawings?
Is the packing of interstices within masonry with stone chips are done effectively?
Is the cleaning & raking of joints being done properly?
Is the cleaning of dead mortar completed?
Is the curing done properly?

Are all the tests conducted in accordance to the standards before the commencement of work?
In case of working under rainy conditions or under water, the location of pumps, pumping hours
decided from time to time in consultation with the Engineer-in-charge?

De-watering shall be done conforming to BIS Code IS: 9759

Is the height of stone within 300 mm?


Is each stone be hammer dressed on the face, the sides and the beds?
Are the bond stone and headers properly laid into the work and marked by the contractor with white lead paint?
Are all the joints on the faces , pointed or plastered racked out with racking tool to a
depth of 20mm while the mortar is still green?
Are the face
Masonry work joints less than
in cement 20 mm thick?
or composite (should
mortar shallnot be more
be kept than 20moist
constantly mm thick)
on all faces for a
minimum period of seven days.
Is the work suitably protected from damage, mortar dropping and rain during construction?

Has the contractor got the stones approved by the Engineer-in-Charge?


All bed joints shall be horizontal and all side vertical
Is the stone hard, sound, durable and tough, free from cracks, decay and weathering and defects like
cavities, cracks, flaws, sand holes, veins, patches of soft or loose materials etc.
The length of the stone shall not exceed three times the height and the breadth on base shall not be greater than three-fourth o
Has the contractor got the stones approved by the Engineer-in-Charge?
Are all stones shall be wetted before placing in position?

Check if the dressed surface shall not be more than 3 mm from a


straight
In edge
case of placed
sunk on it. masonry, the corner stone shall be dressed at true right angles or
or moulded
true to the shape as specified.

Is the centering and shuttering required for arch dome or circular moulded work be constructed
as directed by the Engineer-in-Charge?
The chajjas are provided with cove supports, where cove is in brick masonry

Are stone jalis fixed in grooves/rebates etc. to adjoining Stone work/Brick work/RCC as
shown in the drawing or as directed by Engineer-in-Charge.
References/ Remarks

Sr. No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17

IS 1124 , IS 1121 Part II ,


IS1706, IS 1126

e lead paint?
be greater than three-fourth of the thickness of wall nor less than 15 cm.
LIST OF BUREAU OF INDIAN STANDARD CODES

IS Code No.
IS 737
IS 1121 - (Pt. I)
IS 1122
IS 1123 Methods of identification of natural building stones.
IS 1124
IS 1125
IS 1126
IS 1128
IS 1129 Recommendations for dressing of natural building stones.
IS 1200 (Pt. IV)
IS 1197 (Pt. I)
IS 1597 (Pt. II)
IS 1805
IS 3620
IS 3622
IS 4104 (Pt. I)
IS 4101 (Part II)
Sr. No. Activity

Subject

Methods of determination of properties and strengths of natural building


stones (Part-I compressive strength).

Methods for determination of specific gravity of natural building stone

Methods of identification of natural building stones.


Methods of measurements of building and Civil engineering works stone
Masonry.
Sand stone (Slab & Tiles)
Code of practice for external facings and veneers (Part I-Stone facing).

Code of practice for external facing and veneers: (Part II-Cement Concrete
facing).
SAFETY
Description Yes/NoReferences/ Remarks
QU
Sr. No. Activity
7 cutting, hoisting, fixing in position and applying a priming coat of approved steel
7.1 primer all complete.

work, including cutting, hoisting, fixing in position and applying a priming coat of
7.2 approved steel primer all complete.

Providing and fixing in position collapsible steel shutters with vertical channels
20x10x2 mm and braced with flat iron diagonals 20x5 mm size, with top and bottom
rail of T-iron 40x40x6 mm, with 40 mm dia steel pulleys, complete with bolts, nuts,
locking arrangement, stoppers, handles, including applying a priming coat of
7.3 approved steel primer.

Providing and fixing 1 mm thick M.S. sheet sliding-shutters, with frame and diagonal
braces of 40x40x6 mm angle iron, 3 mm M.S. gusset plates at the junctions and
corners, 25 mm dia pulley, 40x40x6 mm angle and T- iron guide at the top and
7.4 bottom respectively, including applying a priming coat of approved steel primer.

Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm angle iron
and 3 mm M.S. gusset plates at the junctions and corners, all necessary fittings
7.5 complete, including applying a priming coat of approved steel primer.
7.5.1 Using M.S. angels 40x40x6 mm for diagonal braces
7.5.2 Using flats 30x6mm for diagonal braces and central cross piece
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end
by end locks, mounted on specially designed pipe shaft with brackets, side guides
and arrangements for inside and outside locking with push and pull operation
complete, including the cost of providing and fixing necessary 27.5 cm long wire
springs manufactured from high tensile steel wire of adequate strength conforming to
7.6 IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters.
7.6.1 80x1.25 mm M.S. laths with 1.25 mm thick top cover
7.6.2 80x1.20 mm M.S. laths with 1.20 mm thick top cover
7.6.3 80x0.90 mm M.S. laths with 0.90 mm thick top cover
7.7 Providing and fixing ball bearing for rolling shutters.
Extra for providing grilled rolling shutters manufactured out of 8 mm dia M.S. bar
instead of laths as per design approved by Engineer-in- charge, (area of grill to be
7.9 measured).
Fixing standard steel glazed doors, windows and ventilators in walls, including fixing
of float glass panes with glazing clips and special metal-sash putty of approved make,
or metal beading with screws, (only steel windows, glass panes cut to size and
glazing clips or metal beading with screws, shall be supplied by department free of
7.10. cost.
Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10
cm of C.C. 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm
7.10.1 nominal size)
Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid
7.10.2 for separately)

Providing and fixing factory made ISI marked steel glazed doors, windows and
ventilators, side /top /centre hung, with beading and all members such as F7D, F4B,
K11 B and K12 B etc. complete of standard rolled steel sections, joints mitred and
flash butt welded and sash bars tenoned and riveted, including providing and fixing of
hinges, pivots, including priming coat of approved steel primer, but excluding the cost
of other fittings, complete all as per approved design, (sectional weight of only steel
7.11 members shall be measured for payment).
Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10
cm of C.C. 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm
7.11.1 nominal size)
Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid
7.11.2 for separately)
Providing and fixing T-iron frames for doors, windows and ventilators of mild steel
Tee-sections, joints mitred and welded, including fixing of necessary butt hinges and
7.13 screws and applying a priming coat of approved steel primer.
Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10
cm of C.C. 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm
7.13.1 nominal size)
Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid
7.13.2 for separately)
Providing and fixing pressed steel door frames conforming to IS: 4351, manufactured
from commercial mild steel sheet of 1.60 mm thickness, including hinges, jamb, lock
jamb, bead and if required angle threshold of mild steel angle of section 50x25 mm,
or base ties of 1.60 mm, pressed mild steel welded or rigidly fixed together by
mechanical means, including M.S. pressed butt hinges 2.5 mm thick with mortar
guards, lock strike-plate and shock absorbers as specified and applying a coat of
approved steel primer after pre-treatment of the surface as directed by Engineer-in-
7.14 charge
7.14.1 Profile B
7.14.1.1 Fixing with adjustable lugs with split end tail to each jamb
Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid
7.14.1.2 for separately)
7.14.2 Profile C
7.14.2.1 Fixing with adjustable lugs with split end tail to each jamb
Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid
7.14.2.2 for separately)
7.14.3 Profile E
7.14.3.1 Fixing with adjustable lugs with split end tail to each jamb
Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid
7.14.3.2 for separately)
Providing and fixing M.S. Tubular frames for doors, windows, ventilators and
cupboard with rectangular/ L-Type sections, made of 1.60 mm thick M.S. Sheet, joints
mitred, welded and grinded finish, with profiles of required size, including fixing of
necessary butt hinges and screws and applying a priming coat of approved steel
7.15 primer.
Providing and fixing M.S. Tubular frames for doors, windows, ventilators and
cupboard with rectangular/ L-Type sections, made of 1.60 mm thick M.S. Sheet, joints
mitred, welded and grinded finish, with profiles of required size, including fixing of
necessary butt hinges and screws and applying a priming coat of approved steel
7.15.1 primer.
Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid
7.15.2 for separately)
Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses
etc., including cutting, hoisting, fixing in position and applying a priming coat of
approved steel primer, including welding and bolted with special shaped washers etc.
7.16 complete.
7.16.1 Hot finished welded type tubes
7.16.2 Hot finished seamless type tubes
7.16.3 Electric resistance or induction butt welded tubes
Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar, bent to shape
with hooked ends in R.C.C. slabs or beams during laying, including painting the
7.17 exposed portion of loop, all as per standard design complete.

Providing and fixing circular/ Hexagonal cast iron or M.S. sheet box for ceiling fan
clamp, of internal dia 140 mm, 73 mm height, top lid of 1.5 mm thick M.S. sheet with
its top surface hacked for proper bonding, top lid shall be screwed into the cast iron/
M.S. sheet box by means of 3.3 mm dia round headed screws, one lock at the
corners. Clamp shall be made of 12 mm dia M.S. bar bent to shape as per standard
7.18 drawing.
Providing and fixing mild steel round holding down bolts with nuts and washer plates
7.19 complete.
7.20. Providing and fixing bolts including nuts and washers complete
7.21 Providing and fixing M.S. rivets of sizes in position.
7.22 Welding by gas or electric plant including transportation of plant at site etc. complete
Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing
in position and applying a priming coat of approved steel primer using structural steel
7.23 etc. as required.
In stringers, treads, landings etc. of stair cases, including use of chequered plate
7.23.1 wherever required, all complete
7.23.2 In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing, staircase railing and similar works, including applying priming coat of
7.24 approved steel primer.
7.24.1 M.S. tube
7.24.2 E.R.W. tubes
7.24.3 G.I. pipes

Providing and fixing carbon steel galvanised ( minimum coating 5 micron) dash
fastener of 10 mm dia double threaded 6.8 grade (yield strength 480 N/mm2), counter
sunk head, comprising of 10 m dia polyamide PA 6 grade sleeve, including drilling of
7.25 hole in frame , concrete/ masonry, etc. as per direction of Engineer-in-charge.
7.25.1 10 x 60 mm
7.25.2 10 x 80 mm
7.25.3 10 x 120 mm
7.25.4 10 x 140 mm
7.25.5 10 x 160 mm

Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes,
channels, plates etc., including welding, grinding, buffing, polishing and making
curvature (wherever required) and fitting the same with necessary stainless steel nuts
and bolts complete, i/c fixing the railing with necessary accessories & stainless steel
dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or
the side of waist slab with suitable arrangement as per approval of Engineer-in-
charge, (for payment purpose only weight of stainless steel members shall be
7.26 considered excluding fixing accessories such as nuts, bolts, fasteners etc.).
Providing & fixing fly proof wire gauze to windows, clerestory windows & doors with
7.27 M.S. Flat 15x3 mm and nuts & bolts complete.
Galvanised M.S. Wire gauze with 0.63 mm dia wire and 1.4 mm aperture on both
7.27.1 sides
Stainless steel (grade 304) wire gauze of 0.5 mm dia wire and 1.4 mm aperture on
7.27.2 both sides
Providing & fixing glass panes with putty and glazing clips in steel doors, windows,
7.28 clerestory windows, all complete with :
7.28.1 4.0 mm thick glass panes
7.28.2 5.5 mm thick glass panes

Providing and fixing angle iron frames for doors, windows and ventilators of mild steel
Angle sections of size 35x35x5 mm, joints mitred and welded by angle iron 35x35x5
mm or 35x 5 mm flat pieces to the existing T-iron frame or to the wall with dash
fastener, including fixing of necessary butt hinges and screws and applying a priming
coat of approved steel primer, all complete as per the direction of
7.29 Engineer_In_charge.
Code as per QUALITY
DAR Description
10
10.1 Welders Qualifcation record
Structural steel shall conform to IS 1997:1975, IS2062 :1992
Are Bending and cutting done in a skilled manner and does not impair the metal strength?
Are there no joints between members to acheive the required full length?
Are the cut ends finished smooth?
A primer coat such as Red oxide/ zinc chromate shall be applied before the steel member is placed in posit
Suitabilitly and capacity of equipment used for erection are thoroughly checked?
Is fabrication done as specified in IS 800?
is the method of hoisting and erecting the steel structure approved?
Be responsible for ensuring that welding techniques are compatible with the materials used.
Deposited weld metal shall be free of defects

10.2 A figure of the steel structure to be fabricated shall be drawn on a level platform to full scale?
Fabrication shall be done as specified in IS 800.
Position
black boltsof rivet
plus holes
1.5 mmmarked accurately?
for rivets/ bolts of nominal diameter less than or equal to 25 mm” and 2.0 mm
for rivets of nominal diameter exceeding 25 mm care shall be taken in this respect for all single riveted
together before and during riveting, and special
connections
The nominal length of the bolt shall be the distance from the underside of the head to the
further end and
Bolts, nuts of the shank. shall be thoroughly cleaned and dipped in double boiled linseed
washers
oil, before use.
Trusses are lifted only at nodes?

The collapsible gate shall be provided with necessary bolts and nuts, locking arrangement,
10.3 All
stoppers and handles.
the members of the collapsible gate including T-iron are thoroughly cleaned off rust, scales,
dust etc. and given a priming coat?

10.4

10.5
10.5.1
10.5.2
10.6
10.6.1
10.6.2
10.6.3
10.7 Rolling shutters shall conform to IS 6248

10.9

10.10. Check for dents, buckles, wraps

10.10.1

10.10.2

10.11

10.11.1

10.11.2

10.13

10.13.1

10.13.2
10.14
10.14.1
10.14.1.1

10.14.1.2
10.14.2
10.14.2.1

10.14.2.2
10.14.3
10.14.3.1

10.14.3.2

10.15

10.15.1

10.15.2

10.16
10.16.1
10.16.2
10.16.3

10.17

10.18

10.19
10.20.
10.21
10.22

10.25

10.23.1
10.23.2

10.26
10.26.1
10.26.2
10.26.3

10.27
10.27.1
10.27.2
10.27.3
10.27.4
10.27.5

10.28

10.29

10.29.1

10.29.2

10.30.
10.30.1
10.30.2

10.31
Yes/No References/ Remarks Sr. No.

el member is placed in positIS 2074

aterials used.

m to full scale?
IS 800

to 25 mm” and 2.0 mm


ect for all single riveted

IS 1363

rrangement,
off rust, scales,
IS 2074
SAFETY
Activity Description Yes/NoReferences/ Remarks
ces/ Remarks
Sr. No. Activity
8 marble shade (To be secured to the backing by means of cramps, which shall be paid
8.1 for separately).
8.1.1 Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.
8.1.1.1 Area of slab upto 0.50 sqm
8.1.1.2 Area of slab
cement, over
mixed 0.50
with sqm pigment, epoxy touch ups, including rubbing, curing,
matching
8.2 moulding and polishing to edges to give high gloss finish etc. complete at all levels.
8.2.1 Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble
8.2.1.1 Area of slab upto 0.50 sqm
8.2.1.2 Area of slab over 0.50 sqm
8.2.1 Granite of any colour and shade
8.2.1.1 Area of slab upto 0.50 sqm
8.2.1.2 Area of slab
including over 0.50
machine sqm to edge to give high gloss finish etc. complete as per
polishing
8.3 design approved by Engineer-in-Charge.
8.3.1 Marble work
8.3.2 Granite work
facia and drops of width upto 150 mm with epoxy resin based adhesive, including
8.4 cleaning
including etc. complete.
necessary holes for pillar taps etc. including moulding, rubbing and polishing
8.5 of cut edges etc. complete.
Mirror polishing on marble work/Granite work/stone work where ever required to give
8.6 high gloss finish
necessary hole incomplete.
stones and embedding the cramp in the hole (fastener to be paid
8.7 separately).
8.7.1 Gunmetal cramps
8.7.2 Stainless steel cramps

Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface
8.8 backing including drilling necessary holes and the cost of bolt etc complete.
8.8.1 Wedge expansion type
8.8.1.1 Fastener with threaded dia 6 mm
8.8.1.2 Fastener with threaded dia 10 mm
8.8.1.3 Fastener with threaded dia 12 mm
Stone tile (polished) work for wall lining over 12 mm thick bed of cement mortar 1:3 (1
cement : 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing in white
8.9 cement complete.
8.9.1 8mm thick
8.9.1.1 Raj nagar plain white marble/ Udaipur green marble/ Zebra black marble
8.9.1.2 Granite of any colour and shade

Providing and fixing stone slab with table rubbed, edges rounded and polished, of
size 75x50 cm deep and 1.8 cm thick, fixed in urinal partitions by cutting a chase of
appropriate width with chase cutter and embedding the stone in the chase with epoxy
grout or with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone
aggregate 6 mm nominal size) as per direction of Engineer-in-charge and finished
8.10. smooth.
8.10.1 White Agaria Marble Stone
8.10.2 Granite Stone of approved shade
Providing and fixing machine cut, mirror/ eggshell polished , Marble stone work for
wall lining (veneer work) including dado, skirting, risers of steps etc., in required
design and pattern wherever required, stones of different finished surface texture, on
12 mm (average) thick cement mortar 1:3 (1 cement : 3 coarse sand) laid and jointed
with white cement slurry @ 3.3 kg/sqm including pointing with white cement slurry
admixed with pigment of matching shade, including rubbing, curing, polishing etc. all
complete as per Architectural drawings, and as directed by the Engineer-in-
Charge.“a. 18 mm thick Italian Marble stone slab,Perlato, Rosso
8.11 verona, Fire Red or Dark Emperadore etc

Providing and laying flamed finish Granite stone flooring in required design and
patterns, in linear as well as curvilinear portions of the building all complete as per the
architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base
of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry
and pointing with white cement slurry admixed with pigment of matching shade
including rubbing, curing and polishing etc. all complete as specified and as directed
by the Engineer-in-Charge : a. Flamed finish granite stone slab Jet Black, Cherry
8.12 Red, Elite Brown, Cat Eye or equivalent

Providing and laying Polished Granite stone flooring in required design and patterns,
in linear as well as curvilinear portions of the building all complete as per the
architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base
of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry
and pointing with white cement slurry admixed with pigment of matching shade
including rubbing , curing and polishing etc. all complete as specified and as directed
8.13 by the Engineer-in-Charge.

8.13.1 Polished Granite stone slab jet Black, Cherry Red, Elite Brown, Cat Eye or equivalent.
Code as per QUALITY
DAR
8
8.1
8.1.1
8.1.1.1
8.1.1.2
8.2
8.2.1
8.2.1.1
8.2.1.2
8.2.1
8.2.1.1
8.2.1.2
8.3
8.3.1
8.3.2
8.4
8.5
8.6
8.7
8.7.1
8.7.2

8.8
8.8.1
8.8.1.1
8.8.1.2
8.8.1.3

8.9
8.9.1
8.9.1.1
8.9.1.2

8.10.
8.10.1
8.10.2
8.11

8.12

8.13

8.13.1
QUALITY
Description
Check for cleanliness of base surface before the tiling work is done. Has the loose mortar & debris been removed from
Have the preceding activities like fixing of doors, partitions, false ceiling, etc have been completed properly?
Check if the provision of service conduits, junction boxes, etc are done as specified.
Is the approved pattern of laying available for reference?
Are slopes for the tiled surface finalized?
Check for availability of tiles & other construction aids before the work starts.
Check for availability of tiling masons
Is the mortar mixing proportion done as specified?
Check if the thickness of mortar bed acceptable?
Check for pattern of laying
Check for the thickness of joints between tiles
Check for tiling around doors, sanitary fittings, columns, partitions, etc
Check the finishing of edges for cut tiles
Check for the addition of pigment to cement, if required
Check if the curing of tiling is done for a specified period
Check for cleaning of tile surface
Check for grinding & polishing
Final check for true level surface, pattern, surface finishes, slope, etc
Has the coloured cement been used to fill the joints between tiles properly?
Yes/No References/ Remarks Sr. No.
ar & debris been removed from the work area?
completed properly?
SAFETY
Activity Description Yes/NoReferences/ Remarks
ces/ Remarks
Code as per QUALITY
Sr. No. Activity
the joints with same mortar, with common burnt clay DAR
10.1 non modular bricks
1:4 (1 cement : 4 coarse sand)
1:6 (1cement : 6 coarse sand)

mud mortar, including filling joints with Jamuna sand,


10.2 with common burnt clay non modular bricks.

but excluding the cost of nosing of steps etc.


10.3 complete.
40 mm thick with 20 mm nominal size stone
aggregate

cement slurry, but excluding the cost of nosing of


10.4 steps etc. complete.

62 mm thick cement concrete flooring with concrete


hardener topping, under layer 50 mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20mm nominal size) and top layer
12mm thick cement hardener consisting of mix 1:2 (1
cement hardener mix : 2 graded stone aggregate,
6mm nominal size) by volume, hardening compound
mixed @ 2 litre per 50 kg of cement or as per
manufacture’s specifications. This includes cost of
cement slurry, but excluding the cost of nosing of
10.5 steps etc. complete.

Cement plaster skirting up to 30 cm height, with


cement mortar 1:3 (1 cement : 3 coarse sand),
10.6 finished with a floating coat of neat cement.
18 mm thick
Cement concrete pavement with 1:2:4 (1 cement : 2
coarse sand : 4 graded stone aggregate 20 mm
10.7 nominal size), including finishing complete.

Extra for making chequers of approved pattern on


cement concrete floors, steps, landing, pavements
10.8 etc.

40 mm thick marble chips flooring rubbed and


polished to granolithic finish, under layer 34 mm thick
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4
graded stone aggregate 12.5 mm nominal size) and
top layer 6mm thick with white, black, chocolate, grey,
yellow or green marble chips of sizes from 1 mm to 4
mm nominal size, laid in cement marble powder mix
3:1 (3 cement : 1 marble powder) by weight in
proportion of 4:7 (4 cement marble powder mix : 7
marble chips) by volume, including cement slurry etc.
10.9 complete
Dark shade pigment with ordinary cement
Light shade pigment with white cement
Medium shade pigment with 50% white cement and
50% ordinary cement
White cement without any pigment

10.10 Light shade pigment with ordinary cement


10.11 Ordinary cement without any pigment

40 mm thick marble chips flooring, rubbed and


polished to granolithic finish, under layer 31 mm thick
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4
graded stone aggregate 12.5 mm nominal size) and
top layer 9 mm thick with white, black, chocolate,
grey, yellow or green marble chips of sizes from 4 mm
to 7 mm nominal size, laid in cement marble powder
mix 3:1 (3 cement : 1 marble powder) by weight in
proportion of 4:7 (4 cement marble powder : 7 marble
chips) by volume, including cement slurry etc.
10.12 complete.
Dark shade pigment with Ordinary cement
Light shade pigment with white cement
Medium shade pigment with 50% white cement and
50% ordinary cement
White cement without any pigment
Light shade pigment with ordinary cement
Ordinary cement without any pigment

40 mm thick marble chips flooring, rubbed and


polished to granolithic finish, under layer 28 mm thick
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4
graded stone aggregate 12.5 mm nominal size) and
top layer 12 mm thick with white, black, chocolate,
grey yellow or green marble chips of sizes from 7 mm
to 10 mm nominal size, laid in cement marble powder
mix 3:1 (3 cement : 1 marble powder) by weight in
proportion of 2:3 (2 cement marble powder mix : 3
marble chips) by volume, including cement slurry etc.
10.13 complete :
Dark shade pigment with ordinary cement
Light shade pigment with white cement
Medium shade pigment with 50% white cement and
50% ordinary cement
White cement without any pigment
Light shade pigment with ordinary cement
Ordinary cement without any pigment

Marble chips skirting up to 30 cm height, rubbed and


polished to granolithic finish, top layer 6 mm thick with
white, black, chocolate, grey, yellow or green marble
chips of sizes from smallest to 4 mm nominal size,
laid in cement marble powder mix 3:1 (3 cement : 1
marble powder) by weight in proportion of 4:7 (4
cement marble powder mix : 7 marble chips) by
10.14 volume :
18 mm thick with under layer 12 mm thick in cement
.12.1 plaster 1:3 (1 cement : 3 coarse sand) :
.12.1.1 Dark shade pigment with ordinary cement
Light shade pigment with white cement
Medium shade pigment with 50% white cement and
50% ordinary cement
White cement without any pigment
Light shade pigment with ordinary cement
Ordinary cement without any pigment

Providing and fixing glass strips in joints of terrazo/


10.15 cement concrete floors
40 mm wide and 4 mm thick

Extra for laying terrazo flooring on staircase treads


not exceeding 30 cm in width, including cost of
10.16 forming, nosing etc.
Crazy marble stone flooring, including filling the gaps
with light shade pigment with white cement marble
powder mixture (3 parts of white cement : 1 part of
marble powder) by weight in proportion of 4:7 (4
cement marble powder mix : 7 white, black or white
and black marble chips of sizes from 1 mm to 4 mm
nominal size by volume), with under layer 25 mm thick
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4
graded stone aggregate 12.5 mm nominal size),
including rubbing, polishing and cement slurry etc.
10.17 complete :
18 mm thick crazy marble stone white, black or as
specified

Precast terrazo tiles 22 mm thick with graded marble


chips of size upto 12 mm, laid in floors, and landings,
jointed with neat cement slurry mixed with pigment to
match the shade of the tiles, including rubbing and
polishing complete, on 20 mm thick bed of cement
10.18 mortar 1:4 (1 cement:4 coarse sand) :
Light shade pigment using white cement
Medium shade pigment using 50% white cement and
50% ordinary cement
Dark shade pigment using ordinary cement
Ordinary cement without any pigment

Extra if terrazo tiles are laid in treads of steps not


10.19 exceeding 30 cm in width.

Precast terrazo tiles 22 mm thick with graded marble


chips of sizes upto 12 mm, in skirting and risers of
steps not exceeding 30 cm in height, on 12 mm thick
cement plaster 1:3 (1 cement : 3 coarse sand), jointed
with neat cement slurry mixed with pigment to match
the shade of the tiles, including rubbing and polishing
10.20 complete with tiles of :
Light shade pigment using white cement
Medium shade pigment using 50% white cement and
50% ordinary cement
Dark shade pigment using ordinary cement
Ordinary cement without any pigment

Chequered terrazo tiles 22 mm thick with graded


marble chips of size up to 6 mm in floors, jointed with
neat cement slurry mixed with pigment to match the
shade of the tiles, including rubbing and polishing
complete, on 20 mm thick bed of cement mortar 1:4
10.21 (1 cement :4 coarse sand) :
Light shade pigment using white cement
Medium shade pigment using 50% white cement and
50% ordinary cement
Dark shade pigment using ordinary cement
Ordinary cement without any pigment

Chequerred precast cement concrete tiles 22 mm


thick in footpath & courtyard, jointed with neat cement
slurry mixed with pigment to match the shade of tiles,
including rubbing and cleaning etc. complete, on 20
mm thick bed of cement mortar 1:4 (1 cement: 4
10.22 coarse sand).
Light shade pigment using white cement
Medium shade pigment using 50% white cement and
50% ordinary cement
Dark shade pigment using ordinary cement
Ordinary cement without any pigment

Providing and fixing 10 mm thick acid and/or alkali


resistant tiles of approved make and colour using acid
and/or alkali resisting mortar bedding, and joints filled
with acid and/or alkali resisting cement as per IS :
4457, complete as per the direction of Engineer-in-
10.23 Charge
In flooring on a bed of 10 mm thick mortar 1:4 (1 acid
.21.1 proof cement : 4 coarse sand)
.21.1.1 Acid and alkali resistant tile
In dado/skirting on 12 mm thick mortar 1:4 (1 acid
.21.2 proof cement : 4 coarse sand)
.21.2.1 Acid and alkali resistant tile

Tile work in skirting, risers of steps and dado up to 2


m height over 12 mm thick bed of cement mortar 1:3
(1 cement :3 coarse sand) and jointed with grey
cement slurry @ 3.3 kg/sqm, including pointing in
white cement mixed with pigment of matching shade
10.24 complete.
0.22 Marble tiles (polished) Raj Nagar
.22.1 8 mm thick

Marble stone flooring with 18 mm thick marble stone,


as per sample of marble approved by Engineer-in-
charge, over 20 mm (average) thick base of cement
mortar 1:4 (1 cement : 4 coarse sand) laid and jointed
with grey cement slurry, including rubbing and
10.25 polishing complete with
Makrana white second quality
Raj Nagar plain
Agaria White
Black Zebra
Udaipur green marble
Pink plain marble

Extra for pre finished nosing to treads of steps of


10.26 marble stone.

Extra for marble stone flooring in treads of steps and


10.27 risers using single length up to 2.00 metre.
Kota stone slab flooring over 20 mm (average) thick
base laid over and jointed with grey cement slurry
mixed with pigment to match the shade of the slab,
including rubbing and polishing complete with base of
10.28 cement mortar 1 : 4 (1 cement : 4 coarse sand) :
25 mm thick

Kota stone slabs 20 mm thick in risers of steps,


skirting, dado and pillars laid on 12 mm (average)
thick cement mortar 1:3 (1 cement: 3 coarse sand)
and jointed with grey cement slurry mixed with
pigment to match the shade of the slabs, including
10.29 rubbing and polishing complete.

40 mm thick fine dressed stone flooring over 20 mm


(average) thick base of cement mortar 1:5 (1 cement :
10.30 5 coarse sand) with joints finished flush.
Red sand stone
White sand stone

40 mm thick fine dressed stone flooring over 20 mm


(average) thick base of cement mortar 1:5 (1 cement :
5 coarse sand), including pointing with cement mortar
1:2 (1 cement : 2 stone dust) with an admixture of
10.31 pigment to match the shade of stone.
Red sand stone
White sand stone
40 mm thick rubbed stone flooring over 20 mm
(average) thick base of cement mortar 1:5 (1 cement :
5 coarse sand) with joints 3 mm thick, side buttered
with cement mortar 1:2 (1 cement : 2 stone dust)
admixed with pigment to match the shade of stone
10.32 and pointing with same mortar.
Red sand stone
White sand stone

Extra for pre finished nosing in treads of steps of Kota


10.33 stone/ sand stone slab.

Extra for Kota stone/ sand stone in treads of steps


10.34 and risers using single length up to 1.05 metre.

25 mm wooden planking, tongued and grooved in


flooring, including fixing with iron screws complete
10.35 with :
Second class teak wood
Second class deodar wood

38 mm thick wood block flooring of first class teak


wood laid over 25 mm thick leveling layer of cement
concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 10 mm nominal size) to be paid
separately, coated with a thin layer of hot bitumen
penetration 80/25 (blown type) @ 2.45 kg per sqm,
including fixing blocks in position after dipping in hot
bitumen (blown type) up to half depth, planed, levelled
10.36 smooth and finished complete
Providing and fixing M.S. angle 50x50x5 mm to act as
nosing with lugs of M.S. flat 10x5 mm, 10 cm long,
forked at end 60cm apart (minimum three lugs to be
provided), including necessary welding and applying a
priming coat of approved primer on exposed surface
10.37 etc. complete.

Providing and fixing Ist quality ceramic glazed wall


tiles conforming to IS: 15622 (thickness to be
specified by the manufacturer), of approved make, in
all colours, shades except burgundy, bottle green,
black of any size as approved by Engineerin-Charge,
in skirting, risers of steps and dados, over 12 mm
thick bed of cement mortar 1:3 (1 cement : 3 coarse
sand) and jointing with grey cement slurry @ 3.3kg
per sqm, including pointing in white cement mixed
10.38 with pigment of matching shade complete.

Providing and laying Ceramic glazed floor tiles of size


300x300 mm (thickness to be specified by the
manufacturer) of 1st quality conforming to IS : 15622
of approved make in colours such as White, Ivory,
Grey, Fume Red Brown, laid on 20 mm thick cement
mortar 1:4 (1 Cement : 4 Coarse sand), Jointing with
grey cement slurry @ 3.3 kg/sqm including pointing
the joints with white cement and matching pigment
10.39 etc., complete.
Providing and fixing 1st quality ceramic glazed floor
tiles conforming to IS : 15622 (thickness to be
specified by the manufacturer ) of approved make in
all colours, shades except burgundy, bottle green,
black of any size as approved by Engineer-in-Charge
in skirting, risers of steps and dados over 12 mm thick
bed of cement Mortar 1:3 (1 cement: 3 coarse sand)
and jointing with grey cement slurry @ 3.3kg per sqm
including pointing in white cement mixed with pigment
10.40 of matching shade complete.

Providing and laying Ceramic glazed floor tiles of size


300x300 mm (thickness to be specified by the
manufacturer), of 1st quality conforming to IS : 15622,
of approved make, in all colours, shades, except
White, Ivory, Grey, Fume Red Brown, laid on 20 mm
thick bed of cement mortar 1:4 (1 Cement : 4 Coarse
sand), jointing with grey cement slurry @ 3.3 kg/ sq.m
including pointing the joints with white cement and
10.41 matching pigments etc., complete.

Providing and laying rectified Glazed Ceramic floor


tiles of size 300x300 mm or more (thickness to be
specified by the manufacturer), of 1st quality
conforming to IS : 15622, of approved make, in
colours White, Ivory, Grey, Fume Red Brown, laid on
20 mm thick cement mortar 1:4 (1 Cement: 4 Coarse
sand), jointing with grey cement slurry @ 3.3 kg/ sqm
including grouting the joints with white cement and
10.42 matching pigments etc., complete.

Providing and laying rectified Glazed Ceramic floor


tiles of size 300x300 mm or more (thickness to be
specified by the manufacturer), of 1st quality
conforming to IS : 15622, of approved make, in all
colours, shades, except White, Ivory, Grey, Fume
Red Brown, laid on 20 mm thick Cement Mortar 1:4 (1
Cement : 4 Coarse sand), jointing with grey cement
slurry @ 3.3 kg/ sqm including pointing the joints with
10.43 white cement and matching pigments etc., complete.
Providing and laying vitrified floor tiles in different
sizes (thickness to be specified by the manufacturer)
with water absorption less than 0.08% and
conforming to IS: 15622, of approved make, in all
colours and shades, laid on 20mm thick cement
mortar 1:4 (1 cement : 4 coarse sand), jointing with
grey cement slurry @ 3.3 kg/ sqm including grouting
the joints with white cement and matching pigments
10.44 etc., complete.
Size of Tile 500x500 mm
Size of Tile 600x600 mm
Size of Tile 800x800 mm
Size of Tile 1000x1000 mm

Deduct for not using 20 mm thick cement mortar 1:4


(1 cement : 4 coarse sand) bedding in laying of floor
tiles and jointing with grey cement slurry @ 3.3 kg/
10.45 sqm.

Fixing glazed/ Ceramic/ Vitrified floor tiles with cement


based high polymer modified quick-set tile adhesive
(Water based) conforming to IS: 15477, in average
10.46 3mm thickness.

Crazy ceramic tile flooring, with under layer 12 mm


thick cement mortar 1:4 (1 cement: 4 coarse sand),
with joints not exceeding 5 mm, including filling the
gaps with ordinary cement mixture & mixing with
synthetic polyester fibre, triangular in shape having
specific gravity of 1.34 to 1.40, cross section size
ranging from 10 to 40 micron & length upto 6 mm ,
mixing fibre @ 125 grams per 50 kg of cement in
cement mortar, including providing and mixing water
proofing material in mortar @ 1 kg per 50 kg of
cement, all complete as per direction of Engineer-in-
10.47 charge.
Providing and laying 500x500x40 mm thick Turf paver
(Turfpave XD) on 150 mm thick sub grade of
compacted bed of 20 mm thick nominal size stone
aggregate and base course and filling with 150 mm
thick jamuna sand, including spreading, well ramming,
consolidating and finishing smooth etc. all complete
10.48 as per direction of Engineer-in-charge.

Providing and laying Vitrified tiles in different sizes


(thickness to be specified by manufacturer), with
water absorption less than 0.08 % and conforming to
I.S. 15622, of approved make, in all colours & shade,
in skirting, riser of steps, over 12 mm thick bed of
cement mortar 1:3 (1 cement: 3 coarse sand), jointing
with grey cement slurry @ 3.3 kg/ sqm including
grouting the joint with white cement & matching
10.49 pigments etc. complete.
Size of Tile 500x500 mm
Size of Tile 600x600 mm
Size of Tile 800x800 mm
.46.4 Size of Tile 1000x1000 mm

Providing and fixing glazed screen printed border tile


75mm wide having thickness 5mm, of approved
quality & make, in all shades, design and prints, in
dado, over 12mm thick bed of cement mortar 1:3 (1
Cement : 3 Coarse sand) and jointing with grey
cement slurry @ 3.3 kg/sqm including pointing with
white cement mixed with pigment of matching shade,
10.50 all complete as approved by Engineer - in - Charge

Providing and laying Vitrified tiles in different sizes


(thickness to be specified by the manufacturer), with
water absorption less than 0.08% and conforming to
IS: 15622, of approved brand & manufacturer, in all
colours and shade, in skirting, riser of steps, laid with
cement based high polymer modified quick set tile
adhesive (water based) conforming to IS: 15477, in
average 6 mm thickness, including grouting of joints
(Payment for grouting of joints to be made
10.51 separately).
Size of Tile 500x500 mm
Size of Tile 600x600 mm
Size of Tile 800x800 mm
Size of Tile 1000x1000 mm

Grouting the joints of flooring tiles having joints of 3


mm width, using epoxy grout mix of 0.70 kg of organic
coated filler of desired shade (0.10 kg of hardener
and 0.20 kg of resin per kg), including filling / grouting
and finishing complete as per direction of Engineer-in-
10.52 charge.
Size of Tile 500x500 mm
Size of Tile 600x600 mm
Size of Tile 800x800 mm
Size of Tile 1000x1000 mm

Providing and laying Vitrified tiles in floor with different


sizes (thickness to be specified by the manufacturer),
with water absorption less than 0.08% and
conforming to IS:15622, of approved brand &
manufacturer, in all colours and shade, laid with
cement based high polymer modified quick set tile
adhesive (water based) conforming to IS : 15477, in
average 6 mm thickness, including grouting of joints
(Payment for grouting of joints to be made
10.53 separately).
Size of Tile 500x500 mm
Size of Tile 600x600 mm
Size of Tile 800x800 mm
Size of Tile 1000x1000 mm

Deduct for not grouting the joints with white cement


and matching pigment in the items of fixing of vitrified
10.54 tiles.
Providing and laying machine cut, mirror polished,
Italian Marble stone flooring laid in required pattern in
linear portion of the building all complete as per
architectural drawings, with 18 mm thick stone slab
laid over 20 mm (average) thick base of cement
mortar 1:4 (1 cement : 4 coarse sand) laid and jointed
with white cement slurry @ 4.4 kg/sqm including
pointing with white cement slurry admixed with
pigment to match the marble shade including rubbing,
curing and polishing etc. all complete as specified and
10.55 as directed by the Engineer-in-Charge
18 mm thick Italian Marble stone slab, Perlato, Rosso
verona, Fire Red or Dark Emperadore etc.

Providing and laying machine cut, mirror polished


Marble stone flooring, in required design (Simple
geometrical, abstract etc.) and in patterns in
combination with Italian marble stones of different
colours, shades and finished surface texture etc., in
linear portions of the building, all complete as per the
architectural drawings, with 18 mm thick stone slab
laid over 20 mm (average) thick base of cement
mortar 1:4 (1 cement : 4 coarse sand) laid and jointed
with white cement slurry @ 4.4 kg/sqm, including
pointing with white cement slurry admixed with
pigment to match the marble shade, including
rubbing, curing and polishing etc. all complete as
10.56 specified and as directed by the Engineer-in-Charge.
18 mm thick Italian Marble stone slab, Perlato, Rosso
verona, Fire Red or Dark Emperadore etc

Providing and fixing Glass mossaic tiles on finished


plain wall surface of size 20 mm x 20 mm x 4 mm in
all colour, design , fixing in customize design as per
direction of Engineer-in- Charge. The glass mosaic
tiles to be fixed on the wall surface with the help of
approved adhesive applied at the rate of 2.5 kg per
sqm and grouting of the same. The rate is inclusive of
all operation, material and required pattern approved
10.57 by Engineer-in-Charge:
Providing and fixing removable raised/false access
flooring with system and its components of approved
make for different plenum height with possible height
adjustment upto 50 mm, comprising of modular load
bearing floor panels supported on G.I. rectangular
stinger frame work and G.I. Pedestal etc. all
complete, as per the architectural drawings, as
specified and as directed by Engineer-in-charge
10.58 consisting of:
300 mm Finished Floor Height (FFH)
450 mm Finished Floor Height (FFH).
QUALITY
Description Yes/No
Is grouting completed with no grout smear on tiles?
Is Internal floor tile junction to Streamline angle siliconed?
Shower and door water stops remain and undamaged.
Skirting tiles complete and height as per plan.
Spare Full boxes only stacked neatly under stairs.

Splash backs
Wall tiles complete
complete and correct
and feature tiles to plan in correct location and
included
correct size.
Waterproofing complete and inspected prior to tiling.

Floor tiles complete and falls to wastes.


Floor waste clear of tiling / bedding material
Floor waste grates installed.

Grouting completed with no grout smear on tiles

Internal floor tile junction to Streamline angle is siliconed

Shower and door water stops remain and undamaged.


Skirting tiles complete and height as per plan.
Spare Full boxes only stacked neatly under stairs.
Splash backs complete and correct to plan

Wall tiles complete and feature tiles included in correct location to


correct size.
Waterproofing complete and inspected prior to tiling.
Floor tiles complete.

Floor waste clear of tiling / bedding material


Floor waste grates installed.
Skirting tiles complete and height as per plan.
Splash back over laundry tub complete as per detail.

Floor tiles complete.


Grouting completed with no grout smear on tiles
Skirting tiles complete and height as per plan.
Spare Full boxes only stacked neatly under stairs.

Splash back over vanity complete as per detail.


External door sills completed

Kitchen splash back complete to detail.


Sliding door sills complete.
All rubbish and packaging removed from garage and placed in bin/
cage.
House fully swept out and rubbish placed in bins provided.

Spare full boxes of tiles neatly stacked under stairs around corner so
painter can paint wall linings.
Timber delivery pallets placed in bin provided.
References/ Remarks
QUALITY
Code as per
Sr. No. lugs or with dash fasteners of Activity
required dia & length ( hold fast lugs or DAR
9.1 dash fastener shall be paid for separately). 9.1

position with hold fast lugs or with dash fasteners of required dia &
9.2 length (hold fast lugs or dash fastener shall be paid for separately). 9.2

Providing wood work in frames of false ceiling, partitions etc. sawn


9.3 and fixed in position : 9.3
Sal wood
Kiln seasoned and chemically treated hollock wood

Extra for additional labour for circular works, such as in frames of fan
9.4 ligh 9.4
Sal wood
Kiln seasoned and chemically treated hollock wood

Providing and fixing panelled or panelled and glazed shutters for


doors, windows and clerestory windows, including ISI marked M.S.
pressed butt hinges bright finished of required size with necessary
screws, excluding panelling which will be paid for separately, all
9.5 complete as per direction of Engineer-in-charge. 9.5

Providing and fixing 35 mm thick factory made laminated veneer


lumber door shutter conforming to IS : 14616 and TADS 15:2001
(Part B), including ISI marked M.S. pressed butt hinges bright finished
of required size with necessary screws, all complete as per directions
9.6 of Engineer- in-charge and panelling with panels of : 9.6
Providing and fixing panelling or panelling and glazing in panelled or
panelled and glazed shutters for doors, windows and clerestory
windows (Area of opening for panel inserts excluding portion inside
grooves or rebates to be measured). Panelling for panelled or
9.7 panelled and glazed shutters 25 mm to 40 mm thick : 9.7

Fly proof stainless steel grade 304 wire gauge with 0.5 mm dia. wire
9.8 and 1.4 mm wide aperture with matching wood beading 9.8

Providing and fixing glazed shutters for doors, windows and


clerestory windows using 4 mm thick float glass panes, including ISI
marked M.S. pressed butt hinges bright finished of required size with
9.9 necessary screws. 9.9

Providing and fixing factory made laminated veneer lumber glazed


shutter conforming to IS: 14616 and TADS 15:2001 (Part B), using 4
mm thick float glass panes for doors, windows and clerestory
windows, including ISI marked M.S. pressed butt hinges bright
finished of required size with necessary screws, all as per directions
9.10 of Engineer-in-charge. 9.10

Extra for providing heavy sheet float glass panes instead of ordinary
float glass in glazed doors, windows and clerestory window shutters.
(Area of opening for glass panes excluding portion inside rebate shall
9.11 be measured) 9.11
Extra for providing frosted glass panes 4 mm thick instead of ordinary
float glass panes 4 mm thick in doors, windows and clerestory
window shutters. (Area of opening for glass panes excluding portion
9.12 inside rebate shall be measured). 9.12

Deduct for providing pin headed glass panes instead of ordinary float
glass panes weighing 4 mm thick in doors, windows and clerestory
windows shutters (Area of opening for glass panes excluding portion
9.13 inside rebate shall be measured). 9.13

Extra for providing ISI marked Stainless Steel butt hinges instead of
M.S. pressed butt hinges bright finished of required size with
9.14 necessary screws. (Shutter area to be measured). 9.14

Deduct for not providing hinges in doors, windows or clerestory


9.15 window shutters with : 9.15
9.16 Providing and fixing 25 mm thick shutters for cup board etc. : 9.16

Providing and fixing flat pressed 3 layer particle board medium


density exterior grade (Grade I) or graded wood particle board IS :
3087 marked, to frame, backing or studding with screws etc.
9.17 complete (Frames, backing or studding to be paid separately): 9.17

Providing and fixing Pre-laminated flat pressed 3 layer (medium


density) particle board or graded wood particle board IS : 3087
marked, with one side decorative and other side balancing lamination
Grade I, Type II exterior grade IS : 12823 marked, in shelves with
screws and fittings wherever required, edges to be painted with
9.18 polyurethane primer (fittings to be paid separately). 9.18

Providing and fixing ISI marked flush door shutters conforming to IS :


2202 (Part I) decorative type, core of block board construction with
frame of 1st class hard wood and well matched teak 3 ply veneering
with vertical grains or cross bands and face veneers on both faces of
9.19 shutters. 9.20
QUALITY
Description
Are all required brackets/holddowns/anchors Yes/No References/ Remarks
installed
Are peramount
correct plan and
of schedule?
kings and cripple studs
installed?
Are correct headers installed for load bearing walls/
non load bearing walls?
Are interior walls plumb?
Are sheer walls sheeted and nailed off according to
schedule?
Are walls fastened to substrate with correct
fasteners?
Are walls free of brace blocks and nails?
Is weather barrier installed and fastened to
withstand weather and wind?
Has layout been verified?
Has rafter layout been verified?
Are ceilings framed flat and level?

Do all hold down posts match required schedule for


plyrequired
Is size? blocking for fire/mounting/nailing
installed
Is weatherper plan? installed and fastened to
barrier
withstand weather and wind?
Are correct hanger brackets used for floor system?

Are hold down clips installed per plan?


Are joist toe nailed to plates?

Are the correct floor joists series installed per plan?


Do all joists meet minimum bearing depth?

Is all rim board installed to support joists?


Are correct hanger and hold down clips installed
per schedule and rafter plan?
Are lateral braces installed per plan?
Are press plate seated with out kinks and bends?
Are rafter cords and members free of splits and
cracks?
Are rafter installed per plan?
Are joists the correct size per plan?
Is ceiling framing clear of bracing and nails?

Are joists crowned all the same direction?


Are joists confirmed to be under span?
Are joist hangers installed according to plan and
materials used?
Are ceilings framed flat and level?

Are all blocking and backing flush with face of


framing?
Are correct amount of kings and cripple studs
installed?
Are correct headers installed for load bearing walls/
non load bearing walls?
Are sheer walls sheeted and nailed off according to
schedule?

Are walls fastened to substrate with correct


fasteners?
Check sill plates for exterior grade, pressure treated
lumber
Check sill sealer installed between sill plate &
foundation

Check beams for straightness and consistent height


Check trim/molding installed to finish standards

All material is void of major defects


Trim intersects with walls, ceilings, floors evenly with
no gaps or irregularities
Trim joints are tight and caulked, sanded, and smooth
All finishing nails set below surface
Allow for clearance from finish floor surface
Check specialty molding/trim for type

Check that all door glass is free from scratches

Verify with City approved stamped structural framing


plans and architectural floor plans, the location and
length of all shear walls to be installed.

Check trim/molding installed to finish standards

Check condition of door and hardware at delivery


Check door type, quantity, size, swing, finish,
hardware per print/specs

Check location of all doors per door schedule

Check wood species, cabinet style, and type of finish


Allow for clearance from finish floor surface
Check that all thresholds are level
Verify that cabinet layout will work with appliances
selected

Verify the nailing of the sheathing agrees with the


shear wall schedule.
Verify sheathing material agrees with the structural
notes and:
Verify lumber size and grade agrees with the
structural notes.
Verify bottom of wall shear transfer (sill/sole plate)
connection is based on the structural notes or sections
and details.
Verify square plate washer is used on bolts.
Check all door gaps are consistent and equal on flush
inset doors/drawers

Check finish nails set below surface


Check doors free from mars, scratches, dents

Check that all door glass is free from scratches


Verify bolt hole in sill plate is not more than 1/16"
larger than bolt diameter.

Nailing size and spacing of wall sole plate to floor


framing below from shear walls schedule verify nails
penetrate framing below.

Check on plan if gutters & downspouts are included

Check downspout termination extends 5’ from house


Check galvanized metal connectors installed using
approved nails

Check flashing located/installed per applicable code


Check stair dimensions conform to applicable
building code
Check structural lumber stamped pressure-treated
outdoor wood
Check columns, posts,, beams certified to carry load
and not merely ornamental

Check for plumb for the door frame w.R.T. Masonry opening.
Check for plumb for the door w.R.T. Masonry plumb.
Check for plastering of window frames to walls by screws

Check for dimensions of jambs & reveals

Final check for paint, surface finishes & glazing


Check for removal of protective coating &
cleaning of the aluminium door before handover
QUALITY
Code as per
Sr. No. and shape wherever required.Activity DAR
10.1 12.1

Extra for straight cutting in C.G.S. sheet roofing for making opening of
10.2 area exceeding 40 sq. decimeter for chimney stacks, sky light etc.: 12.2

Extra for circular cutting in C.G.S. sheet roofing for making opening of
10.3 area exceeding 40 sq. decimeter: 12.3

fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I.
10.4 limpet and bitumen washers complete. 12.4

polymer coated J, or L hooks, bolts and nuts 8 mm dia G.I. limpet and
10.5 bitumen washers complete : 12.5

washer complete, bent to shape and fixed in wall with cement mortar
10.6 1:3 (1 cement : 3 coarse sand). 12.6

washers etc., including making necessary connections with rain water


10.7 pipes complete. 12.7

trusses), including cutting sheets to size and shape wherever


10.8 required. 12.8

openings of area exceeding 40 square decimeter for chimney stacks,


10.9 skylights etc. 12.9

corrugated/ semicorrugated 6 mm thick sheet roofing for making


10.10. openings of area exceeding 40 square decimeter. 12.10.

10.11 Extra for providing and fixing wind ties of 40x 6 mm flat iron section 12.11

Providing and fixing ridges and hips in fibre cement high impact
polypropylene reinforced roofing with suitable fixing accessories or
10.12 self drilling fastener and EPDM washer etc. complete. 12.12

Providing and fixing fibre cement high impact polypropylene


reinforced roofing accessories in all colours with polymer coated J or
L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain
and bitumen washers or with self drilling fastener and EPDM washer
10.13 etc. complete: 12.13

Providing flat iron brackets 50x3 mm size with necessary bolts, nuts
and washers etc. for fixing asbestos cement / G.S. sheets gutters with
10.14 purlins. 12.14

Painting top of roofs with bitumen of approved quality @ 17kg per 10


sqm impregnated with a coat of coarse sand at 60 cudm per 10 sqm,
including cleaning the slab surface with brushes and finally with a
10.15 piece of cloth lightly soaked in kerosene oil complete : 12.15
10 cm thick (average) mud phaska of damped brick earth on roofs
laid to slope consolidated and plastered with 25 mm thick mud mortar
mixed with bhusa @ 35 kg per cum of earth and gobri leaping with
mix 1:1 (1 clay : 1 cow dung) and covered with flat tile bricks, grouted
with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of
integral water proofing compound by weight of cement and finished
10.16 neat: 12.16

10cm thick (average) mud phaska of damped brick earth on roofs laid
to slope consolidated and plastered with 25 mm thick mud mortar with
bhusha @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1
clay : 1 cow-dung) and covered with machine moulded tile bricks,
grouted with cement mortar 1:3 ( 1 cement : 3 fine sand) mixed with
2% of integral water proofing compound by weight of cement and
10.17 finished neat. 12.17

10.18 Extra for every additional 1 cm thickness of mud phaska. 12.18

Providing and laying brick tiles over mumty roofs, grouted with
cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral
water proofing compound by weight of cement, over 12 mm layer of
10.19 cement mortar 1:3 (1 cement : 3 fine sand) and finished neat: 12.19

Providing and laying pressed clay tiles (as per approved pattern 20
mm nominal thickness of approved size) on roofs jointed with cement
mortar 1:4 (1 cement : 4 coarse sand) mixed with 2% integral water
proofing compound, laid over a bed of 20 mm thick cement mortar 1:4
10.20. (1 cement : 4 coarse sand) and finished neat complete. 12.20.

Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement : 2


coarse sand : 4 stone aggregate 10 mm and down gauge), including
finishing with cement mortar 1:3 (1 cement : 3 fine sand) as per
10.21 standard design : 12.21

Making khurras 45x45 cm with average minimum thickness of 5 cm


cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone
aggregate of 20 mm nominal size) over P.V.C. sheet 1 m x1 m x 400
micron, finished with 12 mm cement plaster 1:3 (1 cement : 3 coarse
sand) and a coat of neat cement, rounding the edges and making and
10.22 finishing the outlet complete 12.22

Providing sand stone slab for roofing and laying them in cement
mortar 1 : 4 (1 cement : 4 coarse sand) over wooden karries or
R.C.C. battens or structural steel sections (Karries or battens or
structural steel sections to be paid separately), including pointing the
ceiling joints with cement mortar 1:3 (1 cement : 3 fine sand )
10.23 complete : 12.23

Providing and fixing insulating board ceiling of approved quality with


10.24 necessary nails etc. complete (frame work to be paid separately) : 12.24
Providing and fixing flat pressed 3 layer medium density particle
board or graded particle board (Grade I) IS: 3087 marked, in ceiling
10.25 with necessary nails etc. complete (frame work to be paid separately): 12.25

Providing and fixing plain multipurpose cement board(Hight pressure


steam cured) with suitable screws for cement particle board in ceiling
10.26 etc. complete (frame work to be paid seperatately). 12.26

10.27 Extra for Circular cutting including wastages in ceiling with: 12.27

Extra for providing and fixing ceiling to curved surfaces in narrow


10.28 widths 12.28

Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling up


to a height of 5 m above floor level, over first class kail wood strips
25x6 mm with 10 mm gap in between and reinforced with rabbit wire
10.29 mesh fixed to wooden frame (frame work to be paid separately): 12.31

Extra for sunk or raised mouldings in the plaster of Paris (Gypsum


10.30. anhydrous) ceiling. 12.32

Extra for providing plaster of Paris (Gypsum anhydrous) ceiling above


10.31 5 metres height from floor level. 12.33

Providing fixing thermal insulation of ceiling (under deck insulation)


with Resin Bonded Fibre glass wool conforming to IS : 8183, density
24kg / m3, 50mm thick, wrapped in 200 G Virgin Polythene bags,
fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire
mesh of 12.5 mm x 24 gauge wire mesh, for top most ceiling of
10.32 building. 12.34

Providing and fixing thermal insulation with Resin Bonded Fibre glass
wool conforming to IS: 8183. Density 16 kg/m³, 50 mm thick, wrapped
in 200G Virgin Polythene bags placed over existing false ceiling and
10.33 held in position by criss-crossing GI wire 12.35

Thermal Insulation of roofing with Expanded polystyrene fixed with


suitable adhesive to the false ceiling as per the directions of the
10.34 Engineer-in-charge: 12.36

Providing and fixing 100 mm diameter and 60 cm long rain water


10.35 spout in cement mortar 1:4 (1 cement : 4 fine sand) 12.37
Providing and fixing M.S. holder bat clamps of approved design to
C.I. or S.C.I. rain water pipes embedded in and including cement
concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse
sand : 4 graded stone aggregate 20 mm nominal size) and cost of
10.36 cutting holes and making good the walls etc. : 12.38

Providing lead caulked joints to sand cast iron rain water pipes and
10.37 fittings: 12.39

Providing, fixing and embedding sand cast iron accessories for rain
water pipes in the masonry surrounded with 12 mm thick cement
mortar of the same mix, as that of masonry (lead caulking will be paid
10.38 for separately): 12.40.

Providing and fixing on wall face unplasticised Rigid PVC rain water
pipes conforming to IS : 13592 Type A, including jointing with seal
ring conforming to IS : 5382, leaving 10 mm gap for thermal
10.39 expansion, (i) Single socketed pipes. 12.41

Providing and fixing on wall face unplasticised - PVC moulded fittings/


accessories for unplasticised Rigid PVC rain water pipes conforming
to IS : 13592 Type A, including jointing with seal ring conforming to IS
10.40. : 5382, leaving 10 mm gap for thermal expansion. 12.42

Providing and fixing unplasticised -PVC pipe clips of approved design


to unplasticised - PVC rain water pipes by means of 50x50x50 mm
hard wood plugs, screwed with M.S. screws of required length,
including cutting brick work and fixing in cement mortar 1:4 (1
10.41 cement : 4 coarse sand) and making good the wall etc. complete. 12.43

Providing and fixing to the inlet mouth of rain water pipe cast iron
10.42 grating 15 cm diameter and weighing not less than 440 grams. 12.44
Providing and fixing false ceiling at all height including providing and
fixing of frame work made of special sections, power pressed from
M.S. sheets and galvanized with zinc coating of 120 gms/sqm (both
side inclusive) as per IS : 277 and consisting of angle cleats of size
25 mm wide x 1.6 mm thick with flanges of 27 mm and 37mm, at
1200 mm centre to centre, one flange fixed to the ceiling with dash
fastener 12.5 mm dia x 50mm long with 6mm dia bolts, other flange of
cleat fixed to the angle hangers of 25x10x0.50 mm of required length
with nuts & bolts of required size and other end of angle hanger fixed
with intermediate G.I. channels 45x15x0.9 mm running at the spacing
of 1200 mm centre to centre, to which the ceiling section 0.5 mm thick
bottom wedge of 80 mm with tapered flanges of 26 mm each having
lips of 10.5 mm, at 450 mm centre to centre, shall be fixed in a
direction perpendicular to G.I. intermediate channel with connecting
clips made out of 2.64 mm dia x 230 mm long G.I. wire at every
junction, including fixing perimeter channels 0.5 mm thick 27 mm high
having flanges of 20 mm and 30 mm long, the perimeter of ceiling
fixed to wall/partition with the help of rawl plugs at 450 mm centre,
with 25mm long dry wall screws @ 230 mm interval, including fixing of
gypsum board to ceiling section and perimeter channel with the help
of dry wall screws of size 3.5 x 25 mm at 230 mm c/c, including
jointing and finishing to a flush finish of tapered and square edges of
the board with recommended jointing compound , jointing tapes ,
finishing with jointing compound in 3 layers covering upto 150 mm on
both sides of joint and two coats
of primer suitable for board, all as per manufacturer's specification
and also including
the cost of making openings for light fittings, grills, diffusers, cutouts
made with frame of
perimeter channels suitably fixed, all complete as per drawings,
specification and direction
of the Engineer in Charge but excluding the cost of painting with :
10.43 12.45

Providing and fixing to the inlet mouth of rain water pipe PTMT (an
Engineering Thermoplastic) grating square (Slit) 150 mm square with
10.44 a height of 8 mm and weighing not less than 100 gms. 12.46

Providing & fixing UV stabilised fiberglass reinforced plastic sheet


roofing up to any pitch, including fixing with polymer coated 'J' or 'L'
hooks, bolts & nuts 8mm dia. G.I plain/bitumen washers complete but
excluding the cost of purlins, rafters, trusses etc. The sheets shall be
manufactured out of 2400 TEX panel rovigs incorporating minimum
0.3% ultra-violet stabiliser in resin system under approximately 2400
psi and hot cured. They shall be of uniform pigmentation and
thickness without air pockets and shall conform to IS 10192 and IS
12866.The sheets shall be opaque or translucent, clear or pigmented,
10.45 textured or smooth as specified. 12.47
Providing & fixing on roof pressed clay tile (Mangalore tile) of 20 mm
nominal thickness and of approved size and as per approved pattern
on steel frame work complete (steel frame work to be paid
10.46 separately). 12.48

Providing & laying on roof pressed clay tile ridge (Mangalore tile) of
20mm thickness and of approved pattern on steel frame work
10.47 complete (steel frame work to be paid separately) 12.49

Providing and fixing precoated galvanised iron profile sheets (size,


shape and pitch of corrugation as approved by Engineer-in-charge)
0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120
grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns
epoxy primer on both side of the sheet and polyester top coat 15-18
microns. Sheet should have protective guard film of 25 microns
minimum to avoid scratches during transportation and should be
supplied in single length upto 12 metre or as desired by Engineer-in-
charge. The sheet shall be fixed using self drilling /self tapping screws
of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in
horizontal/ vertical or curved surfaces, excluding the cost of purlins,
rafters and trusses and including cutting to size and shape wherever
10.48 required. 12.50.

Providing and fixing precoated galvanised steel sheet roofing


accessories 0.50 mm (+ 0.05 %) total coated thickness, Zinc coating
120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7
microns epoxy primer on both side of the sheet and polyester top coat
10.49 15- 18 microns using self drilling/ self tapping screws complete : 12.51
Providing and fixing tiled false ceiling of specified materials of size
595x595 mm in true horizontal level, suspended on inter locking
metal grid of hot dipped galvanized steel sections ( galvanized @ 120
grams/ sqm, both side inclusive) consisting of main "T" runner with
suitably spaced joints to get required length and of size 24x38 mm
made from 0.30 mm thick (minimum) sheet, spaced at 1200 mm
center to center and cross "T" of size 24x25 mm made of 0.30 mm
thick (minimum) sheet, 1200 mm long spaced between main "T" at
600 mm center to center to form a grid of 1200x600 mm and
secondary cross "T" of length 600 mm and size 24x25 mm made of
0.30 mm thick (minimum) sheet to be interlocked at middle of the
1200x600 mm panel to form grids of 600x600 mm and wall angle of
size 24x24x0.3 mm and laying false ceiling tiles of approved texture
in the grid including, required cutting/making, opening for services like
diffusers, grills, light fittings, fixtures, smoke detectors etc. Main "T"
runners to be suspended from ceiling using GI slotted cleats of size
27 x 37 x 25 x1.6 mm fixed to ceiling with 12.5 mm dia and 50 mm
long dash fasteners, 4 mm GI adjustable rods with galvanised
butterfly level clips of size 85 x 30 x 0.8 mm spaced at 1200 mm
center to center along main T, bottom exposed width of 24 mm of all
T-sections shall be pre-painted with polyester paint, all complete for
all heights as per specifications, drawings and as directed by
10.50. Engineer-in-charge. 12.52
Providing and Fixing 15 mm thick densified tegular edged eco friendly
light weight calcium silicate false ceiling tiles of approved texture of
size 595 x 595 mm in true horizontal level, suspended on inter locking
metal grid of hot dipped galvanised steel sections (galvanising @ 120
grams per sqm including both side) consisting of main ‘T’ runner
suitably spaced at joints to get required length and of size 24x38 mm
made from 0.33 mm thick (minimum) sheet, spaced 1200 mm centre
to centre, and cross “T” of size 24x28 mm made out of 0.33 mm
(Minimum) sheet, 1200 mm long spaced between main’T’ at 600 mm
centre to centre to form a grid of 1200x600 mm and secondary cross
‘T’ of length 600 mm and size 24 x28 mm made of 0.33 mm thick
(Minimum) sheet to be inter locked at middle of the 1200x 600 mm
panel to from grid of size 600x600 mm, resting on periphery walls
/partitions on a Perimeter wall angle pre-coated steel of
size(24x24X3000 mm made of 0.40 mm thick (minimum) sheet with
the help of rawl plugs at 450 mm centre to centre with 25 mm long dry
wall screws @ 230 mm interval and laying 15 mm thick densified
edges calicum silicate ceiling tiles of approved texture in the grid,
including, cutting/ making opening for services like diffusers, grills,
light fittings, fixtures, smoke detectors etc., wherever required. Main
‘T’ runners to be suspended from ceiling using G.I. slotted cleats of
size 25x35x1.6 mm fixed to ceiling with 12.5 mm dia and 50 mm long
dash fasteners, 4 mm G.I. adjustable rods with galvanised steel level
clips of size 85 x 30 x 0.8 mm, spaced at 1200 mm centre to centre
along main ‘T’, bottom exposed with 24 mm of all Tsections shall be
pre-painted with polyster baked paint, for all heights, as per
10.51 specifications, drawings and as directed by Engineer-in-Charge 12.53

Providing and fixing Gl Clip in Metal Ceiling System of 600x600 mm


module which includes providing and fixing 'C' wall angle of size
20x30x20 mm made of 0.5 mm thick pre painted steel along the
perimeter of the room with help of nylon sleeves and wooden screws
at 300 mm center to centre, suspending the main C carrier of size
10x38x10 mm made of G.I steel 0.7 mm thick from the soffit with help
of soffit cleat 37x27x25x1.6 mm, rawl plugs of size 38x12 mm and C
carrier suspension clip and main carrier bracket at 1000 mm c/c.
Inverted triangle shaped Spring Tee having height of 24 mm and
width of 34 mm made of Gl steel 0.45 mm thick is then fixed to the
main C carrier and in direction perpendicular to it at 600 mm centers
with help of suspension brackets. Wherever the main C carrier and
spring T have to join, C carrier and spring T connectors have to be
used. All sections to be galvanized @ 120 gms/sqm (both side
10.52 inclusive), fixing with clip in tiles into spring T with : 12.54
Providing and fixing Heat Resistant Terrace Tiles (300 mm x 300 mm
x 20 mm) with SRI (solar refractive index) > 78, solar reflection > 0.70
and initial emittance > 0.75 on waterproof and sloped surface of
terrace, laid on 20 mm thick cement sand mortar in the ratio of 1:4 (1
cement : 4 coarse sand) and grouting the joints with mix of white
cement & marble powder in ratio of 1:1, including rubbing and
polishing of the surface upto 3 cuts complete, including providing
skirting upto 150 mm height along the parapet walls in the same
10.53 manner. 12.55

Providing and laying roof insulation with 40 mm thick impervious


sprayed, closed cell free Rigid Polyurethane foam over deck
insulation conforming to IS - 12432 Pt. III (density of foam being 40-
45 kg/ cum), over a coat of polyurethane primer applied @ 6-8 sqm
per litre, laying 400 G polythene sheet over PUF spray and providing
a wearing course of 40 mm thick cement screed 1:2:4 (1 cement : 2
coarse sand : 4 stone aggregate 20 mm nominal size) in chequered
rough finish, in panels of 2.5 m x 2.5 m and embedding with 24 G
wire netting and sealing the joints with polymerized mastic, all
10.54 complete as per direction of Engineer-in-Charge 12.56

Providing and fixing thermal insulation with Resin Bonded Fibre glass
wool conforming to IS: 8183 having density 24 kg/m3, 50 mm thick,
wrapped in 200G Virgin Polythene Bags fixed to wall with screw,
rawel plug & washers and held in position by criss crossing GI wire
10.55 etc. complete as per directions of Engineer-in-Charge 12.57

Providing and fixing tiled false ceiling of specified materials of size


595x595 mm in true horizontal level, suspended on interlocking metal
grid of hot dipped galvanized steel sections ( galvanized @ 120
grams/ sqm, both side inclusive) consisting of main "T" runner with
suitably spaced joints to get required length and of size 24x38 mm
made from 0.30 mm thick (minimum) sheet, spaced at 1200 mm
center to center and cross "T" of size 24x25 mm made of 0.30 mm
thick (minimum) sheet, 1200 mm long spaced between main "T" at
600 mm center to center to form a grid of 1200x600 mm and
secondary cross "T" of length 600 mm and size 24x25 mm made of
0.30 mm thick (minimum) sheet to be interlocked at middle of the
1200x600 mm panel to form grids of 600x600 mm and wall angle of
size 24x24x0.3 mm and laying false ceiling tiles of approved texture
in the grid including, required cutting/making, opening for services like
diffusers, grills, light fittings, fixtures, smoke detectors etc. Main "T"
runners to be suspended from ceiling using GI slotted cleats of size
27 x 37 x 25 x1.6 mm fixed to ceiling with 12.5 mm dia and 50 mm
long dash fasteners, 4 mm GI adjustable rods with galvanized
butterfly level clips of size 85 x 30 x 0.8 mm spaced at 1200 mm
center to center along main T, bottom exposed width of 24 mm of all
T-sections shall be pre-painted with polyester paint, all complete for
all heights as per specifications, drawings and as directed by
10.56 Engineer-in-charge. 12.58
Providing & fixing false ceiling at all height including providing & fixing
of framework made of special section, power pressed from M.S.
sheets and galvanised with zinc coating of 120 gms/ sqm (both side
inclusive) as per IS : 277 and consisting of angle cleat of size 25mm
wide x 1.6mm thick with flanges of 27mm and 37mm, at 1200mm c/c,
one flange fixed to the ceiling with dash fastener 12.5mm dia x 50mm
long with 6mm dia bolts, other flange of cleat fixed to the angle
hangers of 25 x10 x0.50mm of required length with nuts & bolts of
required size and other end of angle hanger fixed with intermediate
G.I chanels 45 x15 x 0.90mm running at the spacing of 1200 mm c/ c,
to which the ceiling section 0.5mm thick bottom wedge of 80mm with
tapered flanges of 26 mm each having lips of 10.5mm, at 450mm c/c,
shall be fixed in a direction perpendicular to G.I intermediate channel
with connecting clip made out of 2.64mm dia x 230mm long G.I wire
at every junction, including fixing perimeter channels 0.50mm thick
27mm high having flanges of 20mm and 30mm long, the perimeter of
ceiling fixed to wall/ partitions with the help of Rawl plugs at 450mm
centre, with 25mm long dry wall screws @ 230mm interval, including
fixing of Calcium Silicate Board to ceiling section and perimeter
channels with the help of dry wall screws of size 3.5 x25mm at
230mm c/c, including jointing & finishing to a flush finish of tapered
and square edges of the board with recommended jointing
compounds, jointing tapes,finishing with jointing compounds in three
layers covering up to 150mm on both sides of joints and two coats of
primer suitable for boards, all as per manufacture's specification and
also including the cost of making opening for light fittings, grills,
diffusers, cut outs made with frame of perimeter channels suitably
fixed, all complete as per drawings, specificaton and direction of the
10.57 Engineer in charge but excluding the cost of painting with: 12.59

Providing and fixing thermal insulation of ceiling (under deck


insulation) with Resin Bonded Rockwool conforming to IS:
8183,density 48 kg/ m3, 50 mm thick, wrapped in 200 G Virgin
Polythene bags fixed to ceiling with metallic cleats (50x50x3 mm) @
60 cm and wire mesh of 12.5mm x 24 gauge wire mesh, for top most
10.58 ceiling of building. 12.60.

Providing and fixing thermal insulation with Resin bonded rock wool
conforming to IS: 8183, density 48 kg/m3, 50 mm thick, wrapped in
200 G virgin Polythene bags placed over existing false ceilng and
10.59 held in position by crisscrossing Gl wire. 12.61

Providing and fixing thermal insulation with Resin Bonded rock wool
conforming to IS: 8183, having density 48 kg/m3,50 mm
thick,wrapped in 200 G Virgin Polythene Bags fixed to wall wirh
screw, rawel plug & washers and held and in position by criss cossing
10.60. GI wire etc. complete as per directions of Engineer-in-Charge. 12.62
Providing and applying two coats of High Albedo paint having
minimum Solar Reflective Index (SRI) 108 (with solar reflectance &
thermal emittance tested as per ASTM) C 1549 and ASTM C 1371
respectively), VOC less than 10 cc/gm. The coating thickness and the
methodology of application shall strctly as per manufacturer's
specifications and as approved by Engineer-in-Charge. Surface
preparation includes cleaning with metal wire brush to remove all
dust, fungus etc., washing with water all complete. The contractor
shall give guarantee for the perfomance of SRI and also the durabitity
10.61 of coating, all complete as per direction of Engineer-in-Charge. 12.63
QUALITY
Description Yes/No References/ Remarks
Are the weather
All employees conditions
have acceptable?
been informed of the work taking
place
A safe way to access the roof has been established
and will be used
If applicable
Safety only fixed
belts must be wornwalkways
where will be usedand
necessary,
safety lines must
a competent be fit– for
person. the job and toeboards are
Guardrails
included.
once a week to ensure that it is still well balanced and
stable
No work is to be ever done alone. There must be two
workers present
Any ladder beingatused
all times
should be tied off and properly
secured
displayed as required (consider items which may fall
through
issued tothe
theroof as well asemployees
appropriate from the roof)
that would
require them
If working withtoshingles
perform do
or supervise work while
not stack them beingon
done.
the
roof
Shingles on the roof will be secured against high
winds
Existing overhead services crossing or adjacent to the
intended roofoutlets
Ducts or air work have
on thebeen
roof considered
have been considered
and any hazard from fumes have
If there are overhead obstruction theybeenhave
dealtbeen
with
indentified
All suitableto the employees
Personal Protective Equipment has been
identified and is required that it will be worn
How will we access the roof on an ongoing basis?
Are access points in good repair?
How will materials be transported to the roof?
Are there any open sides or unprotected edges?
Are guardrails present and to code?

Are walkways present and clearly visible?

Are there any obstructions on the roof or in walkways?

Are there any pipes, tanks, or equipment on the roof?


How will you manage them?
Do skylights have screens?

Do vents and hatches have guardrails?


Is there any risk of falling present from equipment or
holes?

Does everyone have proper safety equipment for their


specific jobs?
Are communication protocols in place and
understood?
Is the necessary signage present?
Do roofers have adequate water?

Was every roofer provided with proper knowledge and


understanding of the equipment and duties of the job?
QUALITY
Code as per
Sr. No. Activity DAR
11.1 12 mm cement plaster of mix : 13.1

15 mm cement plaster on the rough side of single or half brick wall of


11.2 mix : 13.2

11.3 20 mm cement plaster of mix : 13.3

11.4 12 mm cement plaster of mix : 13.4

11.5 15 mm cement plaster on rough side of single or half brick wall of mix: 13.5

11.6 20 mm cement plaster of mix : 13.6

12 mm cement plaster finished with a floating coat of neat cement of


11.7 mix : 13.7

15 mm cement plaster on rough side of single or half brick wall


11.8 finished with a floating coat of neat cement of mix : 13.8

Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating


11.9 coat of neat cement. 13.9

15 mm cement plaster 1:3 (1 cement: 3 coarse sand) finished with a


floating coat of neat cement on the rough side of single or half brick
11.10. wall. 13.10.

18 mm cement plaster in two coats under layer 12 mm thick cement


plaster 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm
11.11 thick cement plaster 1:6 (1 cement : 6 fine sand). 13.11

18 mm cement plaster in two coats under layer 12 mm thick cement


plaster 1:5 (1 cement : 5 coarse sand) and a top layer 6 mm thick
cement plaster 1:3 (1 cement : 3 coarse sand) finished rough with
11.12 sponge. 13.12

11.13 12 mm cement plaster 1:2 (1 cement : 2 stone dust). 13.13

15 mm cement plaster 1:2 (1 cement : 2 stone dust) on the rough side


11.14 of single or half brick wall. 13.14

11.15 20 mm cement plaster 1:2 (1 cement : 2 stone dust) 13.15

11.16 6 mm cement plaster of mix : 13.16


6 mm cement plaster 1:3 (1 cement : 3 fine sand) finished with a
floating coat of neat cement and thick coat of Lime wash on top of
11.17 walls when dry for bearing of R.C.C. slabs and beams. 13.17

11.18 Neat cement punning. 13.18

Rough cast plaster upto 10 m height above ground level with a


mixture of sand and gravel or crushed stone from 6 mm to 10 mm
nominal size, dashed over and including the fresh plaster in two
layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse
sand) and top layer 10 mm cement plaster 1:3 (1 cement : 3 fine
sand) mixed with 10% finely grounded hydrated lime by volume of
11.19 cement. 13.19

Pebble dash plaster upto 10 m height above ground level with a


mixture of washed pebble or crushed stone 6 mm to 12.5 mm
nominal size, dashed over and including fresh plaster in two layers
under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand)
and top layer 10 mm cement plaster with cement mortar 1:3 (1
cement : 3 fine sand) mixed with 10% finely grounded hydrated lime
11.20. by volume of cement. 13.20.

Providing and applying plaster of paris putty of 2 mm thickness over


11.26 plastered surface to prepare the surface even and smooth complete 13.26

12 mm thick plain cement mortar bands in cement mortar 1:4 (1


11.28 cement : 4 fine sand): 13.28

18 mm thick plain cement mortar band in cement mortar 1:4 (1


11.29 cement : 4 fine sand): 13.29

18 mm thick moulded cement mortar band in two coats under layer


12 mm thick with cement mortar 1:5 (1 cement : 5 coarse sand) top
11.30. layer 6 mm thick with cement mortar 1:4 (1 cement : 4 fine sand). 13.30.

Pointing on brick work or brick flooring with cement mortar 1:3 (1


11.31 cement : 3 fine sand): 13.31

Pointing on tile brick work with cement mortar 1:3 (1 cement : 3 fine
11.32 sand): 13.32

Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine


11.33 sand) : 13.33
Raised and cut pointing on stone work in white cement mortar 1:3 (1
11.34 white cement : 3 marble dust). 13.34

Pointing on stone slab ceiling with cement mortar 1:2 (1 cement : 2


11.35 fine sand): 13.35

11.37 White washing with lime to give an even shade : 13.37

11.38 Satna lime wash on walls with one coat. 13.38

11.39 Colour washing such as green, blue or buff to give an even shade : 13.39

Distempering with dry distemper of approved brand and manufacture


(two or more coats) of required shade on new work, over and
11.40. including water thinnable priming coat to give an even shade. 13.40.

Distempering with oil bound washable distemper of approved brand


11.41 and manufacture to give an even shade : 13.41

Distempering with 1st quality acrylic distemper (ready mixed) of


approved manufacturer, of required shade and colour complete, as
11.42 per manufacturer's specification. 13.42

Applying one coat of water thinnable cement primer of approved


11.43 brand and manufacture on wall surface : 13.43

11.44 Finishing walls with water proofing cement paint of required shade : 13.44

11.45 Finishing walls with textured exterior paint of required shade : 13.45

11.46 Finishing walls with Acrylic Smooth exterior paint of required shade : 13.46

Finishing walls with Premium Acrylic Smooth exterior paint with


11.47 Silicone additives of required shade: 13.47

Finishing with Deluxe Multi surface paint system for interiors and
11.48 exteriors using Primer as per manufacturers specifications : 13.48

11.49 Applying priming coat: 13.50.

Painting with silicon & acrylic emulsion based water thinnable sealer
of approved brand and manufacture on wet or patchy portion of
11.50. plastered surfaces : 13.51
Finishing with Epoxy paint (two or more coats) at all locations
prepared and applied as per manufacturer's specifications including
11.51 appropriate priming coat, preparation of surface, etc. complete. 13.52

Painting on G.S. sheet with synthetic enamel paint of approved brand


11.52 and manufacture of required colour to give an even shade : 13.53

11.53 Applying a coat of mordant solution on G.S. sheet: 13.54

Painting (two or more coats) on rain water, soil, waste and vent pipes
and fittings with black anticorrosive bitumastic paint of approved
brand and manufacture, over and including a priming of ready mixed
11.54 zinc chromate yellow primer on new work: 13.55

Painting (two or more coats) on rain water, soil, waste and vent pipes
and fittings with synthetic enamel paint of approved brand and
manufacture and required colour over a priming coat of approved
11.55 steel primer on new work. 13.56

Painting with oil type wood preservative of approved brand and


11.56 manufacture : 13.57

Providing and applying two coats of fire retardant paint on cleaned


wood / ply surface @ 3.5 sqm per litre per coat including preparation
of base surface as per recommendations of manufacturer to make the
11.57 surface fire retardant. 13.58

Coal tarring two coats on new work using 0.16 Litre and 0.12 litre coal
11.58 tar per sqm in the first coat and second coat respectively. 13.59

Wall painting with acrylic emulsion paint of approved brand and


11.59 manufacture to give an even shade : 13.60.

Painting with synthetic enamel paint of approved brand and


11.60. manufacture to give an even shade : 13.61

Painting with synthetic enamel paint of approved brand and


11.61 manufacture of required colour to give an even shade : 13.62

Painting with aluminium paint of approved brand and manufacture to


11.62 give an even shade . 13.63

Painting with acid proof paint of approved brand and manufacture of


11.63 required colour to give an even shade : 13.64

Painting with black anti-corrosive bitumastic paint of approved brand


11.64 and manufacture to give an even shade : 13.65

Floor painting with floor enamel paint of approved brand and


11.65 manufacture of required colour to give an even shade : 13.66
11.66 Varnishing with varnish of approved brand and manufacture : 13.67

11.67 French spirit polishing : 13.68

9 Polishing on wood work with ready mixed wax polish of approved


11.68 brand and manufacture : 13.69

Floor polishing on masonry or concrete floors with wax polish of


11.69 approved brand and manufacture. 13.70.

11.70. Lettering with black Japan paint of approved brand and manufacture 13.71
QUALITY
Description
The blockwork has been cured for 7 days and dry Yes/No References/ Remarks
before plastering is started?
Ceiling
sponge plastering is done
finish, rough before
plaster wall plastering?
and zone of application
are clarified?
silt content low (<6%) and potable water should be
used for mixing
All surfaces mortar.
to be plastered must be wet to prevent
absorption of water from plaster.
Mortar
Ensureshould be used
plastering withinis½even
thickness to 1 at
hour of the mix.
all points during
plastering.
All chasing, installation of conduit, boxes etc are
ensured before
sufficiently commencement
and is of plastering
kept continuously work
damp for proper
curing for at least 7 days?
Check for cracks
The grade of fine aggregate is as specified in the
specifications?
Is
Is the
the scaffolding
scaffolding safe to work
built and on? by the person in
approved
charge?
Cement plaster shall be 6 mm thick finished with a
floating coat of neat cement and thick coat
of lime wash on top of walls for bearing of slabs

Lime wash applied after curing the plaster for 3 days?

Check for hollow spaces if any, shall be filled by


pressing pebbles or crushed stone
QUALITY
Code as per
Sr. No. Activity DAR

Dismantling precast concrete or stone slabs in walls, partition walls


12.40. etc. including stacking within 50 metres lead : 15.40.

walls including stacking of serviceable materials and disposal of


12.41 unserviceable materials within 50 metres lead. 15.41

Dismantling C.I. or asbestos rain water pipe with fittings and clamps
12.42 including stacking the material within 50 metres lead : 15.42

serviceable material and disposal of unserviceable material within 50


12.43 metres lead as per direction of Engineer-in-charge : 15.43

means including stacking of pipes within 50 metres lead as per


12.44 direction of Engineer-in-charge : 15.44

stacking of pipes & lead at site within 50 metre lead as per direction
12.45 of Engineer-in-charge: 15.45

including stacking of pipes & lead at site within 50 metres lead as per
12.46 direction of Engineer-in-charge : 15.46

mechanical means and stacking the pipes within 50 metres lead as


12.47 per direction of Engineer-in-charge : 15.47

disposal of unserviceable materials within 50 metres lead as per


12.48 direction of Engineer-in-charge 15.48

the site and disposal of unserviceable materials within 50 metres lead


12.49 as per direction of Engineer-incharge. 15.49

Dismantling of R.C.C. spun vent shaft including excavating the


cement concrete pit completely, taking out the shaft, refilling the
excavated gap, stacking the useful materials near the site and
12.50. disposal of unserviceable materials within 50 metres lead. 15.50.

Dismantling of road gully chamber of various sizes including C.I.


grating with frame including stacking of useful materials near the site
and disposal of unserviceable materials within 50 metres lead
12.51 including refilling the excavated gap 15.51

Dismantling of flushing cistern of all types (C.I./PVC/Vitrious China)


including stacking of useful materials near the site and disposal of
12.52 unserviceable materials within 50 metres lead. 15.52
Dismantling of C.I. sluice valve including stacking of useful materials
12.53 within a lead of 50 metres 15.53

Dismantling of spindle fire hydrant including stacking of useful


12.54 materials within 50 metres lead. 15.54

Dismantling of cement concrete platform along with curtain walls and


base concrete etc. including stacking of useful materials near the site
12.55 and disposal of unserviceable materials within 50 metres lead : 15.55

Dismantling old plaster or skirting raking out joints and cleaning the
surface for plaster including disposal of rubbish to the dumping
12.56 ground within 50 metres lead. 15.56

Dismantling aluminium/ Gypsum partitions, doors, windows, fixed


glazing and false ceiling including disposal of unserviceable surplus
material and stacking of serviceable material with in 50 meters lead
12.57 as directed by Engineer-in-charge. 15.57

Demolishing R.C.C. work by mechanical means and stockpiling at


designated locations and disposal of dismantled materials up to a
lead of 1 kilometre, stacking serviceable and unserviceable material
12.58 separately including cutting reinforcement bars 15.58

Dismantling of flexible pavement (bituminous courses) by mechanical


means and disposal of dismantled material up to a lead of 1
12.59 kilometre, as per direction of Engineer-in-charge. 15.59
Disposal of building rubbish / malba / similar unserviceable,
dismantled or waste materials by mechanical means, including
loading, transporting, unloading to approved municipal dumping
ground or as approved by Engineer-in-charge, beyond 50 m initial
12.60. lead, for all leads including all lifts involved. 15.60.
QUALITY
Description Yes/No References/ Remarks
manner in which the loads of the various
structural parts are supported is prepared?
structures to be dismantled/demolished as
directed.
Any temporary service connections required for
the demolition work shall be separately taken.
EIC for the safety of the structure and also of the
adjoining building or structures.
Necessary safety appliances shall be issued to the
workers prior to starting of work.

Suitable safety precautions for fire shall be taken.


shall be left in place as long as possible and
maintained in a safe condition.
similarly marked for identification of their
position in the entire assembly.
retained shall be clearly marked before
dismantling or demolition.
Prominent danger signs shall be posted all around
the building/structures.

During night, warning lights shall be placed on or


above all barricades leading to the
building/danger zone.

Prior to the commencement of the work all


materials of fragile nature like glass, ceiling
boards, wall lining, electric, sanitary and water
supply fittings, etc., shall be removed.

All materials which are likely to be damaged by


dropping from a height during demolition of
masonry walls, roof etc., shall be carefully
dismantled first.
Where fixing has been done by nails, screws,
rivets, etc., dismantling shall be done by taking
out the fixing with proper tools and not by tearing
or ripping off

Any damage caused to the structure being


dismantled/demolished in part and/of adjacent
structures due to carelessness and negligence of
contractor shall be made good by him at his own
expenses.

Where existing building is to be extended or otherwise


incorporated in the new work, only such parts of the
existing structure shall be removed as are necessary
to provide a proper connection to the new work.

The connecting edges shall be cut, chipped and


trimmed to the required lines and grades without
weakening or damaging the part of the structure to
be retained

If sewers or drains are removed or disturbed,


arrangements shall be made for immediate
disposal of the foul matter. If sewers or drains
have to be temporarily removed, arrangements
shall be made for the temporary passage of the
flow.

Removed materials shall be lowered by containers


ropes and tackles or chutes properly designed.

Serviceable materials shall be stacked in such a


manner to avoid deterioration. Different
categories of materials shall be stacked separately
as directed by EIC.

Unless otherwise provided, excavated materials


shall be used in back filling the excavation made
in removing the structures, in levelling the ground
or otherwise disposed off as directed by EIC.
Unserviceable materials shall be disposed off as
directed by EIC. Debris shall be removed at the
earliest to ensure safe and adequate working
space.
Code as per QUALITY
Sr. No. complete, including disposal of Activity
rubbish to the dumping ground, all DAR
13.1 complete as per direction of Engineer-in-Charge.
13.1.1 With cement mortar 1:4 (1 cement : 4 fine sand)
13.1.2 With cement mortar 1:4 (1cement: 4 coarse sand)

required complete, including disposal of rubbish to the dumping ground,


13.2 all complete as per direction of Engineer-in-Charge.
13.2.1 Door chowkhats
13.2.2 Window chowkhats
13.2.3 Clerestory window chowkhats

member of door chowkhat and 2 nos on each vertical member of


13.3 window chowkhats), including Cost of dash fasteners/ chemical fastener.

mulba/ rubbish to the nearest municipal dumping ground, all complete


13.4 as per direction of Engineer-in-Charge.
13.4.1 For door/ window/ clerestory window

Renewing glass panes, with putty and nails wherever necessary


13.5 including racking out the old putty:
13.5.1 Float glass panes of thickness 4 mm
13.5.2 Float glass panes of thickness 5.5 mm

13.6 Renewing glass panes, with wooden fillets wherever necessary:


13.6.1 Float glass panes of thickness 4 mm
13.6.2 Float glass panes of thickness 5.5 mm

13.7 Renewing glass panes and refixing existing wooden fillets:


13.7.1 Float glass panes of thickness 4 mm
13.7.2 Float glass panes of thickness 5.5 mm
13.8 Supplying and fixing new wooden fillets wherever necessary:

13.8.1 2nd class teak wood fillets

13.8.2 Hollock wood fillets

13.9 Renewal of old putty of glass panes (length)

13.10 Refixing old glass panes with putty and nails

13.11 Fixing old glass panes with wooden fillets (excluding cost of fillets)

Providing and fixing 16 mm M.S. Fan clamps of standard shape and size
in existing R.C.C. slab, including cutting chase, anchoring clamp to
reinforcement bar, including cleaning, refilling, making good the chase
with matching concrete, plastering and painting the exposed portion of
13.12 the clamps complete.

Regrading terracing of mud phaska covered with tiles or brick, in cement


by dismantling tiles or bricks, removing mud plaster, preparing the
surface of mud phaska to proper slope, relaying mud plaster gobri
leaping and tiles or bricks, grouted in cement mortar 1:3 (1 cement : 3
fine sand), including replacing unserviceable tiles or bricks with new
ones and disposal of unserviceable material to the dumping ground (the
cost of the new tiles or brick excluded), all complete as per direction of
13.13 Engineer-in-Charge.

Replacing sand stone slabs in roofing, laid in cement mortar 1:4 (1


cement : 4 coarse sand), including necessary repairs and cement
pointing with same mortar complete, including disposal of rubbish to
13.14 dumping ground, all complete as per direction of Engineer-in-Charge.
13.14.1 Red/ white sand stone slabs 30 to 50 mm thick
Renewing wooden battens in roofs, including making good the holes in
wall and painting with oil type wood preservative of approved brand and
manufacture complete, including removal of rubbish to the dumping
13.15 ground, all complete as per direction of Engineer-in-Charge.
13.15.1 Sal wood battens

Renewing wooden beams in roofs including making good the holes in


walls and painting with oil type wood preservative of approved brand
and manufacture complete, including removal of rubbish to the dumping
13.16 ground, all complete as per direction of Engineer-in-Charge.
13.16.1 Not exceeding 4.00 metres in length.
13.16.1.1 Sal wood beams
13.16.1.2 Hollock wood beams
13.16.2 Above 4.00 metres and upto 5.00 metres length.
13.16.2.1 Sal wood beams
13.16.2.2 Hollock wood beams

Raking out joints in lime or cement mortar and preparing the surface for
re-pointing or replastering, including disposal of rubbish to the dumping
13.17 ground, all complete as per direction of Engineer-in-Charge.

Flush pointing with cement mortar 1:3 (1 cement : 3 fine sand) mixed
with 2% of integral water proofing compound by weight of cement for flat
13.18 tile bricks on top of mud phaska :
13.18.1 With F.P.S. brick tiles
13.18.2 With modular brick tiles

Taking out wind ties from roof including cutting out rusted bolts, nuts etc.
13.19 and removing materials to any distance within compound and stacking.

Fixing of old wind tie with new fittings including painting two or more
coats with anticorrosive bitumastic paint of approved brand &
manufacturer over and including priming coat of ready mixed zinc
13.20 chromate yellow primer of approved brand.
Renewing bottom rail and/or top runner of collapsible gate including
making good all damages and applying priming coat of zinc chromate
13.21 yellow primer of approved brand and manufacturer.

Renewing Wrought iron or M.S. Wheel or roller of steel door or gate and
fitting and fixing the same with necessary clamps, nuts and bolts/welding
13.22 and erection etc. complete
13.22.1 Wheel 50 mm dia and below
13.22.2 Wheel above 50 mm dia

Pumping out water caused by springs, tidal or river seepage, broken


13.23 water mains or drains and the like.

13.24 Mud mortar made with local clay good earth.

Brick work with common burnt clay bricks of class designation 7.5 in
13.25 mud mortar

13.26 Providing and fixing 25 mm thick shutters for cup board etc. :
13.26.1 Panelled or panelled & glazed shutters :
Superior class teak wood including nickel plated bright finished M.S.
13.26.1.1 piano hinges with necessary screws.
Ist class teak wood including nickel plated bright finished M.S. piano
13.26.1.2 hinges with necessary screws.
13.26.2 Glazed shutters :
Superior class teak wood including nickel plated bright finished M.S.
13.26.2.1 piano hinges with necessary screws.
Ist class teak wood including nickel plated bright finished M.S. piano
13.26.2.2 hinges with necessary screws.

Providing and fixing plain jaffri door and window shutters including bright
or/and black enamelled M.S. butt hinges with necessary screws 35x10
mm laths placed 35 mm apart (frames to be paid separately), including
13.27 fixing 50x12 mm beading complete with :
13.27.1 Second class teak wood
Providing and fixing brass curtain rods of wall thickness 1.25 mm with
two brass brackets fixed with brass screws and wooden plugs etc.
13.28 wherever necessary complete.

13.28.1 20 mm diameter.

13.28.2 25 mm diameter.

Providing and fixing M.S. round or square bars with M.S. flats at
13.29 required spacing in wooden frames of windows and clerestory windows.

Providing joists (karries) including hoisting, fixing in position and


13.30 applying wood preservative on unexposed surface etc. complete with :
13.30.1 Sal wood
13.30.2 Hollock wood

Providing and fixing bright finished brass single acting spring hinges with
13.31 necessary brass screws etc. complete
13.31.1 150 mm
13.31.2 125 mm
13.31.3 100 mm

Providing and fixing bright finished brass double acting spring hinges
13.32 with necessary brass screws etc. complete :

13.32.1 150 mm
13.32.2 125 mm

13.32.3 100 mm

Providing and fixing bright finished brass flush bolts with necessary
13.33 brass screws etc. complete :
13.33.1 150 mm
13.33.2 125 mm
13.33.3 100 mm

Providing and fixing 150 mm bright finished floor brass door stopper with
rubber cushion, necessary brass screws etc. to suit shutter thickness
13.34 complete

13.35 Providing and fixing bright finished brass hard drawn hooks and eyes :
13.35.1 300 mm
13.35.2 250 mm
13.35.3 200 mm
13.35.4 150 mm
13.35.5 100 mm

Providing and fixing bright finished brass fan light pivot with necessary
13.36 brass screws etc. complete.

Providing and fixing 300 mm long bright finished brass chain with hook
13.37 for fan light including necessary brass screws etc. complete.

Providing and fixing bright finished brass quadrant stay 300 mm long
13.38 with necessary brass screws etc. complete.

Providing and fixing bright finished brass helical door spring (superior
13.39 quality).
Providing and fixing chromium plated brass butt hinges with necessary
13.40 chromium plated brass screws etc. complete.
13.40.1 125x70x4 mm (ordinary type)
13.40.2 100x70x4 mm (ordinary type)
13.40.3 75x65x4 mm (heavy type)
13.40.4 75x40x2.5 mm (ordinary type)
13.40.5 50x40x2.5 mm (ordinary type)

Providing and fixing 85x42 mm chromium plated brass pull bolt lock with
necessary chromium plated brass screws, nuts, bolts and washers etc.
13.41 complete.

13.42 White washing with lime to give an even shade :


13.42.1 Old work (two or more coats)
13.42.2 Old work (one or more coats)

Removing white or colour wash by scrapping and sand papering and


preparing the surface smooth including necessary repairs to scratches
13.43 etc. complete

Distempering with dry distemper of approved brand and manufacture


(one or more coats) and of required shade on old work to give an even
13.44 shade.

Distempering with oil bound washable distemper of approved brand and


13.45 manufacture to give an even shade :
Old work (one or more coats)

Removing dry or oil bound distemper, water proofing cement paint and
the like by scrapping, sand papering and preparing the surface smooth
13.46 including necessary repairs to scratches etc. complete.
Painting on G.S. sheet with synthetic enamel paint of approved brand
13.47 and manufacture of required colour to give an even shade :
13.47.1 Old work (one or more coats)

Painting (two or more coats) on rain water, soil, waste and vent pipes
and fittings with black anticorrosive bitumastic paint of approved brand
and manufacture over and including a priming coat of ready mixed zinc
13.48 chromate yellow primer on new work :
13.48.1 75 mm diameter pipes

Painting (one or more coats) on rain water, soil, waste and vent pipes
and fittings with black anticorrosive bitumastic paint of approved brand
13.49 and manufacture on old work :
13.49.1 75 mm diameter pipes
13.49.2 100 mm diameter pipes
13.49.3 150 mm diameter pipes

Painting (two or more coats) on rain water, soil, waste and vent pipes
and fittings with aluminium paint of approved brand and manufacture
over a priming coat of ready mixed zinc chromate yellow primer on new
13.50 work :
13.50.1 75 mm diameter pipes
13.50.2 100 mm diameter pipes
13.50.3 150 mm diameter pipes

Painting (one or more coats) on rain water, soil, waste and vent pipes
and fittings with synthetic enamel paint of approved brand and
13.51 manufacture and required colour on old work :
13.51.1 75 mm diameter pipes
13.51.2 100 mm diameter pipes
13.51.3 150 mm diameter pipes

Painting with oil type wood preservative of approved brand and


13.52 manufacture:
13.52.1 Old work (one or more coats)

Wall painting with plastic emulsion paint of approved brand and


13.53 manufacture to give an even shade:
13.53.1 One or more coats on old work

Painting with synthetic enamel paint of approved brand and manufacture


13.54 of required colour to give an even shade :
13.54.1 One or more coats on old work

Painting with aluminium paint of approved brand and manufacture to


13.55 give an even shade
13.55.1 One or more coats on old work

Painting with acid proof paint of approved brand and manufacture of


13.56 required colour to give an even shade :
13.56.1 One or more coats on old work

Painting with black anti-corrosive bitumastic paint of approved brand and


13.57 manufacture to give an even shade :
13.57.1 One or more coats on old work

13.58 French spirit polishing :


13.58.1 One or more coats on old work

Polishing on wood work with ready made wax polish of approved brand
13.59 and manufacture :
13.59.1 Old work

13.60 Re-lettering with black Japan paint of approved brand and manufacture.

Painting (one or more coats) with black Japan paint of approved brand
13.61 and manufacture to give an even shade.

Providing and fixing C.P. brass chain and rubber plug complete for sink
13.62 or wash basin:
13.62.1 32 mm dia
13.62.2 40 mm dia
Distempering with 1st quality acrylic washable distemper (ready made)
of approved manufacturer and of required shade and colour complete.
13.63 as per manufacturer's specification.
13.63.1 One or more coats on old work

13.64 Finishing walls with water proofing cement paint of required shade :
Old work (one or more coats applied @ 2.20 kg/10 sqm) over priming
coat of primer applied @ 0.80 litrs/10 sqm complete including cost of
13.64.1 Priming coat.
13.64.2 Old work (one or more coats @ 2.20 kg/10 sqm) complete.

13.65 Finishing walls with textured exterior paint of required shade :


Old work (Two or more coats on existing cement paint surface applied
13.65.1 @ 3.28 ltr/10 sqm.
13.65.2 Old work (One or more coats) applied @ 1.82 ltr/10 sqm.

13.66 Finishing walls with Acrylic Smooth exterior paint of required shade :
Old work (Two or more coat applied @ 1.67 ltr/ 10 sqm) on existing
13.66.1 cement paint surface
13.66.2 Old work (One or more coat applied @ 0.90 ltr/10 sqm)

Finishing walls with Premium Acrylic Smooth exterior paint with Silicone
13.67 additives of required shade
Old work (Two or more coats applied @ 1.43 ltr/ 10 sqm) over existing
13.67.1 cement paint surface
13.67.2 Old work (one or more coats applied @ 0.83 ltr/10 sqm)

13.69 Varnishing with varnish of approved brand and manufacture:


13.69.1 One or more coats with copal varnish
13.69.2 One or more coats with spar varnish

13.70 Melamine polishing on wood work (one or more coat).

Varnishing with flatting varnish of approved brand and manufacture one


13.71 or more coats on old work.
Providing and fixing double scaffolding system (cup lock type) on the
exterior side, up to seven story height made with 40 mm dia M.S. tube
1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock
system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S.
staircase system in the scaffolding for working platform etc. and
maintaining it in a serviceable condition for the required duration as
approved and removing it there after .The scaffolding system shall be
stiffened with bracings, runners, connection with the building etc
wherever required for inspection of work at required locations with
essential safety features for the workmen etc. complete as per directions
and approval of Engineer-in-charge .The elevational area of the
scaffolding shall be measured for payment purpose .The payment will be
made once irrespective of duration of scaffolding. Note: - This item to be
used for maintenance work judicially, necessary deduction for
13.72 scaffolding in the existing item to be done.
13.72X Scaffolding

Providing and fixing bright finished brass casement window fasteners or


peg stays to windows/ ventilators with necessary welding and machine
13.73 screws etc. complete.

Providing and fixing 14 mm bright finished brass spring catch to steel


centre hung ventilators with necessary welding and machine screws etc.
13.74 complete.

Repair to plaster of thickness 12mm to 20 mm in patches of area 2.5


sqm and under, including cutting the patch in proper shape, raking out
joints and preparing plastering the wall surface with white cement based
polymer modified self curing mortar, including disposal of rubbish, all
13.75 complete as per the direction of Engineer-In-Charge.

Cleaning of terrace/loft water storage tank (inside surface area) upto


2000 litre capacity at all heights with coconut brushes, duster etc.,
removal of silt, rubbish from the tank and cleaning the tank with fresh
water disinfecting with bleaching powder @ 0.5gm per litre capacity of
tank including marking the date of cleaning on the side of tank body with
the help of stencil and paint and disposing of malba all complete as per
direction of Engineer-in-Charge. (The old date already written on tank
should be removed with paint remover or black paint and if date is not
written with the stencil or old date is not removed deduction will be made
@ Rs. 0.10 per litre) (if during cleaning any GI fittings or ball cock is
damaged that is to be repaired by contractor at his own cost and nothing
13.75A extra will be paid on this account)
Cleaning and desilting of gully trap chamber, including removal of
rubbish mixed with earth etc. and disposal of same, all as per the
13.76 direction of Engineer-in-charge.

Cleaning of chocked sewer line by diesel running vehicle mounting


hydraulic operated high pressure suction cum jetting sewer cleaning
machine fitted with pump having 4000 litres suction capacity and 6000
litres water jetting tank capacity including skilled operator, supervising
engineer etc. for cleaning and partial desilting of manholes and
dechocking of sewer lines. Dechocking and flushing of sewer line from
one manhole to another by high pressure jetting system of 2200 PSI for
13.77 sewer line from 150mm dia upto 300mm dia for all depth.

Cleaning of under ground sump, Over Head R.C.C. Tank ( independent


staging) including disposal of slit and rubbish, all as per direction of
Engineer-in-Charge. The cleaning shall consist following operations:-
(i)Tank shall be emptied of water by pumping & bottom shall be cleaned
of slit and other deposits. (ii) Entire surface area of the sump shall then
scrubbed thoroughly with wire brush etc. and pressure washed with
water. (iii) Chlorination of RCC internal surface by liquid chlorine.iv) The
treated surface shall be dried using air jetting and all loose particles shall
be
removal from the surface.
(v) Finally the surface shall be treated with ultraviolet radiation etc. as
per direction of
13.78 Engineer-in-Charge.

Disconnecting damaged overhead/terrace PVC water storage tank of


any size from water supply line and removing from the terrace including
13.79 shifting at ground level as per direction of Engineer-in-charge.

Providing & fixing White vitreous china water closet squatting pan
(Indian type) along with "S" or "P" trap including dismantling of old WC
seat and "S" or "P" trap at site complete with all operations including all
necessary materials, labour and disposal of dismantled material i/c
13.80 malba, all complete as per the direction of Engineer-in charge.
13.80.1 Long pattern W.C Pan of size 580x440 mm
13.80.2 Orissa pattern W.C Pan of size 580x440 mm
Cutting holes of required size in brick masonry wall for fixing of exhaust
fan including providing and fixing 300 mm dia PVC pipe conforming BIS-
12818 and making good the same etc. complete as per direction of
13.81 Engineer-in-charge.

Dismantling W.C. Pan of all sizes including disposal of dismantled


13.82 materials i/c malba all complete as per directions of Engineer-in-Charge.

Hacking of CC flooring including cleaning for surface etc. complete as


13.83 per direction of the Engineer-in-Charge.

Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled


pipes (within 50 metres lead) as per direction of Engineer-in-Charge. (a)
13.84 Internal Work- Exposed on wall

Taking out existing wooden door shutter, repair by cutting, painting etc.
and refixing of repaired door shutters to existing door frames, including
replacement of hinges with screws, etc. as required, all complete as per
13.85 the direction of the Engineer-in-charge.
QUALITY
Description Yes/NoReferences/ Remarks
Apply a wood protectant.
Lubricate hinges.
Lubricate hardware.
Check to see if weepInspect mechanism
holes are for free
open. Clean travel.
out dirt and dust. Lubricate
rollers and latches.
Check for cracks or any sign of dampness or leaks. Check for any
evidence of termites or wood-eating insects.
Check and clean grout.
Clean and replace filters if necessary.
Remove and clean the filter. Clean accumulated grease deposits from
the fan housing.
Clean dust from top. Clean refrigerator drain pan. Clean and defrost
freezer if necessary.
Check for leaks.
Check for wear or damage. Replace if necessary.
Test for proper operation and replace batteries if necessary.
Test for proper operation.

Inspect visible areas, vents, and ducts for cracks, leaks, or blockages.
Check for proper drainage.
Clean oil and grease.
Check interior and exterior faucets for leaks. Clean aerators. Replace
washers if necessary.
Clean with baking soda. Pour water down unused drains.
Inspect visible pipes for leaks.

Check under and around for leaks.


Check for stability and leaks.
Check area around water heater for leaks. If you have hard water, drain
1-2 gallons water.
Examine for evidence of any leaks. Check insulation and remove or add
if necessary. Check for evidence of birds, squirrels, raccoons, etc.
Check for proper ventilation.
Inspect for separations at sinks and backsplash. Recaulk where
required.
Inspect for loose or missing grout or caulking. Regrout or recaulk if
necessary.
Inspect for proper fit. Adjust if necessary. Inspect caulking and recaulk if
necessary.
Check caulking around windows and doors. Check window and door
screens. Adjust or replace if necessary.

Adjust the travel and tension.


Inspect flues. Clean if necessary. Inspect fireplace brick and mortar for
cracks or damage.

Check for leaks. Check for damaged, loose, or missing shingles. Check
vents and louvers for birds, nests, squirrels, and insects. Check flashing
around roof stacks, vents, and skylights for leaks.
Clean and check for deteriorating bricks and mortar. Check for leaks.
Check for birds, nests, squirrels, and insects.
Clean and check for leaks, misalignment, or damage.
Check for deteriorating bricks and mortar. Check siding for damage or
rot. Check painted surfaces for flaking.
Trim shrubbery around walls. Remove tree limbs, branches, or debris
that can attract insects (no wood or shrubbery should be closer than 3
inches to your house). Maintain grading.
Check for cracks or deterioration. Reseal or repair if necessary.
Examine septic system drain field for flooding and odor. Have tank
pumped yearly.

Clean and store or cover with weatherproof material.


Scrub mildewed areas and treat for water stains, mildew, and fungus.

Clean. Check for leaks. Check for damaged, loose or missing shingles.
Check vents and louvers for birds, nests, squirrels, and insects. Check
flashing around roof stacks, vents, and skylights for leaks.
Clean and check for deteriorating bricks and mortar. Check for leaks.
Check for birds, nests, squirrels, and insects.
Clean and check for leaks, misalignment, or damage.

Clean.
Check for deteriorating bricks and mortar. Check siding for damage or
rot. Check painted surfaces for flaking.
Trim shrubbery around walls. Remove tree limbs, branches, or debris
that can attract insects (no wood or shrubbery should be closer than 3
inches to your house). Maintain grading.
Check for cracks or deterioration. Reseal or repair if necessary.
Inspect for proper operation.
Drain.

Flush out hot water to remove accumulated sediment.


Check for proper flow of water. If the flow is reduced, clean the aerator
screens. During the first two months, the faucet aerators could require
more frequent cleaning.
ces/ Remarks
Code as per QUALITY
Sr. No. making good the undulations etc.Activity
and re-rolling the sub grade and DAR
14.1 disposal of surplus earth with lead upto 50 metres.

moisture conditions to give at least 95% of the maximum dry density


14.2 (proctor density).

14.3 Supplying and stacking at site.


14.3.1 90 mm to 45 mm size stone aggregate
14.3.2 63 mm to 45 mm size stone aggregate
14.3.3 53 mm to 22.4 mm size stone aggregate
14.3.4 Over burnt (Jhama) brick aggregate 120 mm to 40 mm
14.3.5 Over burnt (Jhama) brick aggregate 90 mm to 45 mm
14.3.6 Stone screening 13.2 mm nominal size (Type A)
14.3.7 Stone screening 11.2 mm nominal size (Type B)
14.3.8 Red bajri
14.3.9 Good earth
14.3.10 Moorum

Laying, spreading and compacting stone aggregate of specified sizes to


WBM specifications in uniform thickness, hand picking, rolling with 3
wheeled road / vibratory roller 8-10 tonne capacity in stages to proper
grade and camber, applying and brooming requisite type of screening /
binding material to fill up interstices of coarse aggregate, watering and
14.4 compacting to the required density .

Laying water bound macadam sub-base with brick aggregate and


binding material, earth etc. including screening, sorting and spreading
to template and consolidation with light power road-roller etc. complete.
14.5 (payment for brick aggregate and moorum etc. to be made separately)
14.5.1 Over burnt (Jhama) brick aggregate 120 mm to 40 mm
14.5.2 Over burnt (Jhama) brick aggregate 90 mm to 45 mm

Supplying, stacking and Spreading 6 mm thick red bajri, watering and


14.6 rolling complete including preparation of the surface and rolling.
14.6.1 With road roller/ hand roller
Brick edging in full brick width and half brick depth including excavation,
14.7 refilling and disposal of surplus earth lead upto 50 metres.
With common burnt clay F.P.S. (non modular) bricks of class
14.7.1 designation 7.5

Brick edging laid lengthwise with half brick depth including excavation,
14.8 refilling and disposal of surplus earth lead upto 50 metres :
With common burnt clay F.P.S. (non modular) bricks of class
14.8.1 designation 7.5

Scarifying metalled (water-bound) road surface including disposal of


rubbish, lead upto 50 m and consolidation of the aggregate received
14.9 from scarifying with power road roller of 8 to 10 tonne capacity.

Making bajri path including preparation of subgrade, supplying and


laying brick aggregate of 50 mm nominal size 7.5 cm deep with blinding
material consisting of 12 mm moorum and 12 mm red bajri consolidated
14.10 with road roller.

Dry stone pitching 22.5 cm thick including supply of stones and


14.11 preparing surface complete

Dry brick pitching half brick thick in drains including supply of bricks and
14.12 preparing the surface complete :
With common burnt clay F.P.S. (non modular) bricks of class
14.12.1 designation 7.5

Cutting road and making good the same including supply of extra
quantities of materials i.e. aggregate, moorum screening, red bajri and
14.13 labour required.
14.13.1 bituminous portion
14.13.2 Water bound macadam

Cutting bajri paths and making good the same including supply of extra
14.14 quantities of brick aggregate, moorum and red bajri required.
14.15 Supplying at site :
R.C.C. Standards post/ struts/rails/ pales of mix 1:1.5:3 (1 cement : 1.5
coarse sand : 3 graded stone aggregate 12.5 mm nominal size) with
wooden plugs or 6mm bar nibs wherever required as per direction of
Engineer-in- charge (cost of earth works in excavation, concrete works
14.15.1 in foundation to be paid separately).
Welded steel wire fabric of required width having rectangular mesh
painted with two or more coats of enamel paint of approved shade over
14.15.2 a coat of primer (Priming & Painting to be paid for separately).

14.16 DAR II - Pg 191


QUALITY

Whether Core Cutting machineDescription


test confirms bituminous layer above 50 Yes/NoReferences/ Remarks
mm thickness or as specified in the contract

Whether materials use in bituminous pavement re well graded and are


as per specifications

specifications of the contract as per job mix formula approved by the


engineer

Whether bitumen content in the bituminous pavement is ensured as


suggested in job mix design or as per written instruction of the engineer

Whether temperature control of the materials mixing with bitumen is


done as suggested in job mix design or as per instruction of the
engineer

Whether temperature of laying of bituminous mix material is controlled


as per instruction of the engineer
Whether bituminous layer compaction is done as per specifications

Whether Core cutting tests have been carried out by the department
concerned as per specifications of the contract

Whether road Camber during bituminous mix laying and compaction is


maintained as per design

Whether bituminous layer has been laid mechanically or manually or as


per instruction of the engineer

Whether use of Asphalt Plant/Bitumen mix Paver machine/Tyre Roller/


Steel Roller etc. is ensured as per contract agreement to ensure quality
work

Whether equipment/machinery positioned for the construction of


foundation works and sub-structures are using methods/ techniques as
mentioned in the drawings/design or as instructed by the engineer.

Whether in designing the bridge Navigational Clearance has been taken


into account.

Whether quality (Grade) of deformed M.S. bar to be used in the


construction (tensile strength/ elongation test/bend test has been carried
out.
ces/ Remarks

You might also like