This document provides an estimate for the construction of a proposed factory shed for Apex Tech Wood Pvt Ltd. It lists 6 items including civil and structural work, infrastructure for an RCC road, a toilet block and office, a 10KL water tank, a compound wall, and a 2.6 diameter soak pit. The total estimated cost for all items is 35,436,025.
This document provides an estimate for the construction of a proposed factory shed for Apex Tech Wood Pvt Ltd. It lists 6 items including civil and structural work, infrastructure for an RCC road, a toilet block and office, a 10KL water tank, a compound wall, and a 2.6 diameter soak pit. The total estimated cost for all items is 35,436,025.
This document provides an estimate for the construction of a proposed factory shed for Apex Tech Wood Pvt Ltd. It lists 6 items including civil and structural work, infrastructure for an RCC road, a toilet block and office, a 10KL water tank, a compound wall, and a 2.6 diameter soak pit. The total estimated cost for all items is 35,436,025.
ESTIMATE FOR THE PROPOSED FACTORY SHED - APEX TECH WOOD PVT LTD.
SR.NO. DESCRIPTION OF ITEMS AMOUNT
1 CIVIL & STRUCTURAL WORK 27465346 2 INFRA WORK FOR RCC ROAD 5967301 3 TOILET BLOCK & OFFICE 546582 4 10KL TANK 87851 5 COMPOUND WALL 1282755 6 2.6 DIA SSOAK PIT 86190 TOTAL 35436025